Power Grid Transmission (Sector) Project in India: Consolidated Report on Implementation of Rehabilitation Action Plans

Date: June 2012
Country:
Subject:
Document Type: Environmental and Social Monitoring Reports / Social Monitoring Reports
Project Number: 38492-013

Download Document



Description

This social monitoring report prepared during project implementation of Power Grid Transmission (Sector) Project in India is a consolidated report on the implementation of the Rehabilitation Action Plan (RAP) at Arasur and Pugalur substations and the Pondicherry substation. It describes the status of social issues and the implementation of mitigation measures.