Regional Power Transmission Interconnection Project: Addendum to Land Acquisition and Resettlement Plan - Section C

Date: September 2012
Country:
Subject:
Document Type: Resettlement Planning Documents / Resettlement Plans
Project Number: 40043-013

Download Document



Description

This addendum to the land acquisition and resettlement plan (LARP) for Section C of the Regional Power Transmission Interconnection Project in Afghanistan contains an assessment and measures, as well as time-bound actions and budgets, for the project components which have involuntary resettlement.

This document covers the impacts and detail compensation costs and mechanisms relative to the construction of transmission line towers in section C Kar Kar village.