Pakistan Environmental Impact Assessments
Jamshoro Power Generation Project: Environmental Impact Assessment
Environmental Assessment and Measures Oct 2013
Pakistan Environmental Impact Assessments
Jamshoro Power Generation Project: Environmental Impact Assessment (Draft)
Environmental Assessment and Measures Jun 2013
Pakistan Environmental Impact Assessments
MFF for Power Distribution Enhancement Program (Tranche 2): Conversion of Jalalpur-Nau and Kolu-Tarrar Grid Substations from 66 kV to 132 kV and Double Circuit Transmission Lines
Environmental Assessment and Measures Mar 2011
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): GEPCO Transformer Extension and Augmentation Subprojects Environmental Assessment and Measures Feb 2011
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): D.I. Khan Industrial (Gomal University) Environmental Assessment and Measures Jul 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): PESCO Transformer Extension and Augmentation Subprojects Environmental Assessment and Measures Jul 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Conversion of 66 kV Talhar Grid Station into 132 kV and Double Circuit Transmission Line Environmental Assessment and Measures Jul 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Construction of Warsak Road 132 kV Grid Station and Associated Transmission Line Environmental Assessment and Measures Jul 2009
Pakistan Environmental Assessment Review Framework
Energy Efficiency Investment Program
Environmental Assessment and Measures Jul 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Choa Saidan Shah - N.P. Sethe 132 kV Transmission Line and Upgradation of N.P. Sethe 66 kV Grid Station to 132 kV Environmental Assessment and Measures Jun 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): QESCO - Extension and Augmentation Subprojects Environmental Assessment and Measures Apr 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Central Park 132 kV Grid Station and Double Circuit Transmission Environmental Assessment and Measures Apr 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): DHA Rahber 132 kV Grid Station and Transmission Line Environmental Assessment and Measures Apr 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Doula Chuchak 132 kV Grid Station and 132 kV and Double Circuit Line Environmental Assessment and Measures Apr 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Jubilee Town 132 kV Grid Station & Associated Double Circuit Line Environmental Assessment and Measures Apr 2009
Pakistan Environmental Impact Assessments
Multitranche Financing Facility for the National Highway Development Sector Investment Program: N-65 Sukkur to Jacobabad
Environmental Assessment and Measures Apr 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): 132 kV Press Club Grid Station and Double Circuit Transmission Line Environmental Assessment and Measures Mar 2009
Pakistan MFF for Power Distribution Enhancement Program (Tranche 2): Conversion of 66 kV Grid Station Sukkur City into 132 kV and 132 kV Transmission Line Environmental Assessment and Measures Oct 2008
Pakistan Environmental Assessment Review Framework
Sindh Cities Improvement Investment Program
Environmental Assessment and Measures Aug 2008
Pakistan Summary Environmental Impact Assessments
National Highway Development Sector Investment Program: Batch II: N-65 (Sukkur–Jacobabad); N-80 (Tarnol–Fatehjang–Jand); N-50 (Zhob–Mughal Kot)
Environmental Assessment and Measures Apr 2007
Pakistan Environmental Assessment Review Framework
National Trade Corridor Highway Investment Program: Environmental Assessment and Review Framework
Environmental Assessment and Measures Apr 2007