Projects Documents

Results 1-14 of 14 for Bangladesh Transport and ICT Bridges
Country Document Title Type Cover Date
Bangladesh ADB Statement on the Padma Multipurpose Bridge Project Documents Produced Under Grant/Loans/TA Feb 2013
Bangladesh Preparing the Padma Multipurpose Bridge: Final Report Technical Assistance Consultant's Reports May 2007
Bangladesh Project/Program Completion Reports
Emergency Disaster Damage Rehabilitation (Sector) Project: Completion Report
Completion Reports Jun 2011
Bangladesh Padma Multipurpose Bridge Project Reports and Recommendations of the President Nov 2010
Bangladesh Padma Multipurpose Bridge Project Summary Poverty Reduction and Social Strategies Nov 2010
Bangladesh Padma Multipurpose Bridge Project Gender Action Plans Nov 2010
Bangladesh Resettlement Plans
Padma Multipurpose Bridge Design Project
Resettlement Planning Documents Nov 2009
Bangladesh Padma Multipurpose Bridge Project: Project Administration Manual Project/Program Administration Manual Oct 2010
Bangladesh Padma Multipurpose Bridge Project: Procurement Plan Procurement Plans Oct 2010
Bangladesh Environmental Impact Assessments
Padma Multipurpose Bridge Project: Draft Environmental Impact Assessment (as of Board approval)
Environmental Assessment and Measures Jul 2010
Bangladesh Resettlement Plans
Padma Multipurpose Bridge Project: Resettlement Action Plan: Main Bridge and Approach Roads (as of Board approval)
Resettlement Planning Documents Jun 2010
Bangladesh Resettlement Plans
Padma Multipurpose Bridge Project: Resettlement Action Plan: River Training Works (as of Board approval)
Resettlement Planning Documents Jun 2010
Bangladesh Resettlement Plans
Padma Multipurpose Bridge Project: Resettlement Framework (as of Board approval)
Resettlement Planning Documents Jun 2010
Bangladesh Resettlement Plans
Padma Multipurpose Bridge Project: Resettlement Action Plan: Resettlement Site Development (as of Board approval)
Resettlement Planning Documents Nov 2009