Sustainable Power Sector Support Project: Initial Environmental Examination: New Galle Power Transmission Development (as of Board approval)

Date: November 2010
Document Type: Environmental Assessment and Measures / Initial Environmental Examination
Project Number: 39415-013

Download Document



Description

Assessment of environmental condition and potential impact, including mitigation measures, institutional requirements and environmental monitoring for the proposed new 132/33 kV New Galle substation and the 40 km 132 kV transmission line up to the 132/33 kV Ambalangoda substation, an output of the Sustainable Power Sector Support Project in Sri Lanka. It is provided as supporting document to the Report and Recommendation of the President to ADB's Board of Directors.