Mongolia: Tuul River Improvement Project

Project Name Tuul River Improvement Project
Project Number 47179-003
Country / Economy Mongolia
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8560-MON: Tuul River Improvement Project
Japan Fund for Prosperous and Resilient Asia and the Pacific US$ 1.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Sector / Subsector

Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Rural water supply services

Gender Some gender elements
Description The proposed loan for the Tuul River Improvement Project (the project) will provide institutional strengthening of the Tuul River Basin Authority (TRBA) and demonstrate rehabilitation of the Tuul River in the Ulaanbaatar area. The Tuul River Basin (TRB), which includes 7 districts of Ulaanbaatar, 37 soums (districts) of 5 aimags (provinces) and covers a total area of about 50,000 km2, has the highest water usage in the country. The population density and the concentration of production and services in Ulaanbaatar have been increasing sharply in the last two decades. Increasing water use and wastewater discharge in the TRB put pressure on environmental and water resources, especially in the Ulaanbaatar area.
Project Rationale and Linkage to Country/Regional Strategy

Declining water security risks becoming a serious constraint on economic development, and pollution of the Tuul River is already a public health concern. The Tuul River, and its tributaries, such as Selbe, are the largest surface water resources in Ulaanbaatar, and replenish the groundwater resources in the region. Flow rates have declined substantially in these rivers, mainly as a result of decade-long logging and to recent climate change impacts, and adequate annual groundwater recharge has become less reliable. Ulaanbaatar obtains about 98% of its water supply from groundwater, abstracting 330,000 m3 per day which is close to the estimated maximum sustainable yield. Further increase in groundwater use would likely lead to falling water tables, increased abstraction costs, and potential water shortages within a few years.

The Government of Mongolia (GOM) has taken major steps forward in improving the legal framework for the management and environmental protection of river basins in Mongolia. In 2010, the GOM divided the country into 29 river basins to improve water resources management. Principal laws on water resources have been revised and consolidated, and new laws have been adopted. The 2004 Law of Mongolia on Water has been replaced with the Water Law 2012. Also, a new and consolidated Natural Resources Use Fee Law and Water Pollution Fees Law were approved in 2012. The new Water Law formally established the TRBA, under the Ministry of Environment and Green Development (MEGD), to coordinate water management and environmental protection in the TRB.

With the new institutional and regulatory framework formally established, the GOM is determined to initiate a quick response to the increasing threats in the TRB. In 2012, the GOM approved a detailed Integrated Water Management Plan for the Tuul River Basin (IWMPTRB). TRBA, as a newly established organization, still lacks the institutional capacity to effectively coordinate with other stakeholders in the basin and regulate development activities, which is a major constraint for the implementation of the IWMPTRB.

The GOM has requested ADB to support the TRBA with the implementation of priority activities of the IWMPTRB to strengthen the management and protection of the TRB. These include: (i) the strengthening of institutional capacity of the TRBA, including the development and implementation of regulatory and economic instruments and incentive schemes for environmental compliance; (ii) .improvement of water availability through ecological measures, with a focus on groundwater resources; and (iii) improvement of riverbanks environment in Ulaanbaatar. As such, the TRBA will establish its operational effectiveness through cooperation and coordination with other government agencies and water users, mobilizing financing for improved water resources management, and supervision of the construction and operation of environmental protection infrastructure.

The proposed project will compliment other ongoing and planned initiatives by ADB and development partners to improve the urban environment and wastewater collection and treatment in Ulaanbaatar. The proposed project also builds on ADB's cooperation with Mongolia in the agriculture, natural resources management, and environmental sector since 1996. Under JFPR 9125-MON: Poverty Reduction through Community-Based Natural Resource Management, the MEGD prepared the Integrated River Basin Management Plan of the Onon River Basin, which was ratified by parliaments in two project aimags and approved by the executing agency in December 2011. ADB also supported the MEGD to strengthen its environmental impact assessment regulatory framework. ADB is providing similar support for other developing member countries to strengthen the institutional capacity of watershed and lake management agencies. The lessons learned from these projects will be integrated in the proposed project design.

The proposed project is consistent with the policies of the GOM, and specifically contributes to the implementation of the IWMPTRB. It is also in line with ADB's country partnership strategy for Mongolia, 2012 2016 to support inclusive and environmentally sustainable growth. The project scope also follows several key aspects of ADB's Water Operational Plan 2011 2020, including (i) water demand-supply gaps and unregulated groundwater abstraction, (ii) water quality and river clean-ups, (iii) water governance, and (iv) climate change adaptation. The project is proposed for ADB's lending pipeline for 2015. Project loan is proposed as financing modality of the project.

Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation The project has been cancelled.
Business Opportunities
Consulting Services It is expected that a consulting firm will be recruited. ADB will be responsible for recruiting consultants following ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). A consulting firm will be recruited using the quality- and cost-based selection (QCBS) at a quality cost ratio of 80:20. For international consultant, it will be 21 person-months; and for national consultants, it will be 54 person-moths.
Responsible ADB Officer Radstake, Frank
Responsible ADB Department East Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, EARD
Executing Agencies
Ministry of Environment and Tourism
Government Building II, United Nation's
Street 5/2, Chingeltei District,
Ulaanbaatar 15160, Mongolia
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 13 Dec 2013
Last Review Mission -
Last PDS Update 18 Sep 2017

TA 8560-MON

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Dec 2013 06 Jan 2014 06 Jan 2014 31 Mar 2015 31 Dec 2016 21 Sep 2017
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
0.00 1,000,000.00 200,000.00 0.00 0.00 0.00 1,200,000.00 17 Jun 2022 577,403.60

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.

Source URL: https://www.adb.org/projects/47179-003/main