Project Name MFF - Uttarakhand State-Road Investment Program (Subproject 2)
Project Number 38255-033
Country / Economy India
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2458-IND: MFF - Uttarakhand State-Road Investment Program (Project 2) [formerly Uttaranchal State-Road Investment Program (Subproject 2)]
Ordinary capital resources US$ 140.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Private sector development
Sector / Subsector

Transport / Road transport (non-urban)

Gender No gender elements
Description Uttarakhand State Road Investment Program -Project 2 will help the State of Uttarakhand to (i) improve a sub-network of roads totaling about 898 kilometers; (ii) undertake business process re-engineering of Public Works Department (PWD); and (iii) increase PWD staff's asset management skills.
Project Rationale and Linkage to Country/Regional Strategy Increased efficiency, safety, comfort and reliability of inter-state and intra-state transport services and low road maintenance costs in Uttarakhand State .
Impact Increased economic growth and reduced poverty in Uttarakhand.
Project Outcome
Description of Outcome

1. Increased efficiency of inter- and intrastate transport services;

2. Enhanced sustainability of road network in good condition;

3. Increased operational transparency and governance of PWD;

4. National road development programs synergized.

Progress Toward Outcome Project outcomes and full benefits would be realized upon the completion of the projects under the MFF.
Implementation Progress
Description of Project Outputs

1. Paved, repaired, or rehabilitated state roads

2. Staff with improved skills and revised operating procedures

Status of Implementation Progress (Outputs, Activities, and Issues)

(A) Civil Works:

The civil works for improvement and strengthening of roads with a total length of 898 km were awarded under 20 contract packages. As on 1 January 2015, 18 civil works contracts have been completed and remaining 2 contracts are expected to be completed by 31 March 2015.

(B) Infrastructure Management Component:

Infrastructure Management Consultant (IMC) engaged under the Project, to assist PWD in the implementation of this component has already completed its services. IMC has assisted PWD in the areas of (i) planning, and management information and project management system (MIPMS); (ii) road maintenance; and (iii) human resources strategy and training. IMC has also worked with PWD on a strategic plan for the rehabilitation and maintenance of PWD roads through area based maintenance contracts.

Geographical Location Almora, Bageshwar, Chamoli, Dehra Dun, Haridwar, Naini Tal, Pauri Garhwal, Pithoragarh, Rudra Prayag, Tehri Garhwal, Uttarakhand
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects The implementation of environmental management plans is being monitored by supervision consultants and PWD of Uttarakhand has been submitting environmental monitoring reports
Involuntary Resettlement The resettlement activities have been undertaken in accordance with the resettlement plans and have been completed
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design The stakeholders including local governments and communities have been consulted during design stage.
During Project Implementation The stakeholders including local governments and communities have been consulted during implementation stage.
Business Opportunities
Consulting Services Consultants for construction supervision ,Infrastructure Management Component and program support consultancy have been recruited in accordance with ADB's Guidelines on the Use of Consultants.
Procurement Procurement under the Project has been carried out in accordance with ADB's Guidelines for Procurement. All civil works contracts have been procured under national competitive bidding (NCB) procedures and post-qualification method.
Responsible ADB Officer Motwani, Anil
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Public Works Department of Uttarakhand
Mr. G.S. Bansal
Govt. of Uttarakhand, Dehradun
Timetable
Concept Clearance 23 Nov 2005
Fact Finding -
MRM 05 Mar 2008
Approval 22 Oct 2008
Last Review Mission -
PDS Creation Date 06 Apr 2009
Last PDS Update 09 Mar 2015

LoanĀ 2458-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
22 Oct 2008 10 Feb 2009 22 Apr 2009 31 Mar 2013 31 Mar 2015 19 Aug 2015
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 200.00 Cumulative Contract Awards
ADB 140.00 17 Jun 2022 106.93 0.00 100%
Counterpart 60.00 Cumulative Disbursements
Cofinancing 0.00 17 Jun 2022 106.93 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory - Satisfactory - Satisfactory
 