| Project Name | MFF - Madhya Pradesh Power Sector Investment Program (Tranche 1) | ||||
| Project Number | 32298-023 | ||||
| Country / Economy | India |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Loan |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth |
||||
| Drivers of Change | Governance and capacity development Private sector development |
||||
| Sector / Subsector | Energy / Energy sector development and institutional reform |
||||
| Gender | No gender elements | ||||
| Description | The transmission component of MP's investment program from 2007 to 2012 is predicated on building sufficient capacity for evacuation of power from existing and planned power stations and substation, and delivering power reliability and efficiency to consumers. ADB will finance key components of the transmission investment program from 2007 though to 2012. The construction of new transmission lines will remove constraints to power flow and will provide additional operational flexibility to TRANSCO in its role as independent system operator in MP. Supply reliability will be further improved and furthermore, it will promote open access and development of intra-state and inter-state power trading by probiding sufficient excess substation and line capacity to handle unplanned power transfers. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | The intervention in the Madhya Pradesh power sector is consistent with the ADB Strategy of supporting state level sector reforms, in this case with the emphasis on the transmission and distribution subsectors. | ||||
| Impact | Contributed to sustaining economic growth and social development in Madhya Pradesh. Contributed to meeting the energy demand growth in Madhya Pradesh |
||||
| Project Outcome | |
|---|---|
| Description of Outcome | Improvement in operational efficiency, voltage profile and power delivery capacity in Madhya Pradesh. |
| Progress Toward Outcome | 100% Progress |
| Implementation Progress | |
| Description of Project Outputs | Construction of transmission lines for power evacuation and strengthening of transmission systems. |
| Status of Implementation Progress (Outputs, Activities, and Issues) | 100% Progress |
| Geographical Location | Ashoknagar, Betul, Bhopal, Chhindwara, Dewas, East Nimar, Guna, Harda, Hoshangabad, Indore, Jabalpur, Katni, Narsinghpur, Panna, Rajgarh, Satna, Sehore, Shahdol, Shajapur, Shivpuri, Sidhi, Ujjain, Vidisha, West Nimar |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | B |
| Indigenous Peoples | B |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | Loan covenants relating to Environmental and Social Safeguards are met by EA in implementing the project. The Environmental Monitoring reports submitted by EA have been uploaded in ADB website. |
| Involuntary Resettlement | EA reported that there were no major land acquisition and resettlement issues under this loan. |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | At appraisal, it was assessed that MPTRANSCO has the requisite institutional capability to implement the project and hence services of consultant was not availed. Accordingly, no consultant was engaged by ADB for this project. However, MPTRANSCO appointed separate consultants for preparation of Environment and Social Safeguard reports and formulation of Resettlement Plan. M/s Xavier Institute of Development Action and Studies, Jabalpur was appointed as the Environment Specialist and another team were appointed as the Social and Resettlement Specialist. The reports on implementation of Resettlement Plan (RP), Environmental Management Plan (EMP), updated Initial Environmental Examination (IEE) reports, updated RP, Due Diligence Report (DDR) on Social Task, Environmental DDR and short resettlement plan (SRP) on Social Task. These reports were further submitted to ADB. |
| Procurement | International competitive bidding (ICB) has been used for supply and construction of the facilities being funded under the investment program (substations, tranmission lines, equipment, and transformers, etc.). ICB is utilized for supply contracts estimated to cost the equivalent of or more than $1 million. Limited international bidding (LIB) or national competitive bidding (NCB) was agreed to be used for supply contracts estimated at $250,000-$1 million, and shopping for contracts estimated at less than $250,000. Contract packages were prepared to ensure maximum competition under ICB. MPTRANSCO made use of advance procurement action as agreed by ADB. About $53 million worth of contracts could be planned within June 2007 i.e. just after the effectiveness of the loan. |
| Responsible ADB Officer | Banerjee, Jyotirmoy |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | India Resident Mission |
| Executing Agencies |
Madhya Pradesh Power Transmission Company Limited Mr. R.K. Verma, Chairman and Managing Director [email protected] Shakti Bhawan, Rampur, Jabalpur - 482 008, Mahdya Pradesh |
| Timetable | |
|---|---|
| Concept Clearance | 23 Nov 2005 |
| Fact Finding | 16 Oct 2006 to 24 Oct 2006 |
| MRM | 11 Dec 2006 |
| Approval | 04 Apr 2007 |
| Last Review Mission | - |
| PDS Creation Date | 18 Apr 2007 |
| Last PDS Update | 21 Mar 2013 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 04 Apr 2007 | 12 Apr 2007 | 14 May 2007 | 30 Jun 2011 | 30 Jun 2012 | 31 Jan 2013 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 132.50 | Cumulative Contract Awards | |||
| ADB | 106.00 | 17 Jun 2022 | 97.27 | 0.00 | 100% |
| Counterpart | 26.50 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Jun 2022 | 97.27 | 0.00 | 100% |
| Status of Covenants | ||||||
|---|---|---|---|---|---|---|
| Category | Sector | Safeguards | Social | Financial | Economic | Others |
| Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
| Project Page | https://www.adb.org//projects/32298-023/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=32298-023 |
| Date Generated | 05 June 2023 |