| Project Name | Energy Access and Efficiency Improvement Project II | ||||
| Project Number | 41155-012 | ||||
| Country / Economy | Nepal |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Gender Equity and Mainstreaming |
||||
| Sector / Subsector | Energy / Electricity transmission and distribution - Energy efficiency and conservation - Energy sector development and institutional reform |
||||
| Gender | Effective gender mainstreaming | ||||
| Description | TBD | ||||
| Project Rationale and Linkage to Country/Regional Strategy | The PPTA is included for 2010 in the Nepal Country Partnership Strategy 2010-2012 with financing expected from Japanese Fund for Poverty Reduction (JFPR) | ||||
| Impact | tbd | ||||
| Project Outcome | |
|---|---|
| Description of Outcome | tbd |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | tbd |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | TA has been completed. All activities envisaged under the TA have been implemented. |
| Business Opportunities | |
|---|---|
| Consulting Services | A total of 37 person months of consultancy services will be required to prepare the project. ADB will recruit the consultants in accordance with its Guidelines on the Use of Consultants (2010, as amended from time to time). International power system specialist and the international environmental specialist will be recruited as individual consultants. A firm will be engaged to provide the remaining consultancy services. The consulting firm will be selected according to quality- and cost-based selection procedures using the standard quality-cost ratio of 80:20. |
| Responsible ADB Officer | Cabral Wijayatunga, Priyantha |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Energy Division, SARD |
| Executing Agencies |
Nepal Electricity Authority (NEA) P. O. Box 5352 Kathmandu Nepal |
| Timetable | |
|---|---|
| Concept Clearance | 03 Aug 2010 |
| Fact Finding | 06 Aug 2010 to 11 Aug 2010 |
| MRM | - |
| Approval | 26 Nov 2010 |
| Last Review Mission | - |
| PDS Creation Date | 02 Sep 2010 |
| Last PDS Update | 27 Sep 2012 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 26 Nov 2010 | 03 Jan 2011 | 03 Jan 2011 | 30 Sep 2011 | 31 Dec 2011 | 31 Oct 2012 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 0.00 | 600,000.00 | 100,000.00 | 0.00 | 0.00 | 0.00 | 700,000.00 | 17 Jun 2022 | 416,479.82 |
| Project Page | https://www.adb.org//projects/41155-012/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=41155-012 |
| Date Generated | 05 June 2023 |