| Project Name | Tonga-Fiji Submarine Cable Project | ||||
| Project Number | 44172-012 | ||||
| Country / Economy | Regional |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Inclusive economic growth Regional integration |
||||
| Drivers of Change | Gender Equity and Mainstreaming Private sector development |
||||
| Sector / Subsector | Information and communication technology / ICT infrastructure |
||||
| Gender | Some gender elements | ||||
| Description | The proposed project will support the Government of Tonga to develop and operate a submarine fibre optic cable for communications. Complementing the due diligence activities by the World Bank and TCL, a project preparatory technical assistance (PPTA) is proposed to carry out sector analysis; gender, poverty and social analysis; and governance risk assessment as well as prepare other inputs required for the project. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | Tonga has been the first country among the Pacific developing member countries that introduced competition in telecommunications sector. Since 2002, access to basic telecommunications has increased significantly in Tonga. Mobile teledensity is around 60%, among the highest in the Pacific, and call tariffs are among the lowest in the region. However, Internet access, particularly broadband, is extremely limited, and user prices are as high as $400 per month for 512/128kbps broadband service, and demand is apparently suppressed. The principal constraint to further telecommunications development, including introduction of new services and new market entry, has been identified by all stakeholders as the limited capacity and high cost of international bandwidth. This is due to Tonga's dependence on satellite connectivity which is inadequate to meet growing demand for bandwidth. Current market price for two-way satellite capacity is approximately $3,800 per Mbps per month. Total demand for bandwidth is projected to increase from the 2009 level of about 70 Mbps up to 332 Mbps by 2017, driven primarily by increased demand for fixed and mobile broadband. With the current satellite capacity and price, it would be impossible to meet the growing demand. Improved access to and lower cost of international connectivity in Tonga will stimulate increased access to broadband Internet, and lower the cost of telecommunications services generally. Faster and cheaper connectivity is expected to have numerous positive development impacts for Tonga, including reduced transaction costs for business, Government and household communications; new business opportunities (for example, investments in e-commerce and business process outsourcing facilities); improved public service delivery, in particular to support e-education and e-health services which are of great interest to the Government. Improved connectivity will have significant social benefits in a country with a large number of the people residing in Australia, New Zealand and the United States. Recent studies illustrate a sizable impact of broadband internet services on the economic growth especially in developing countries. The submarine cable would also facilitate regional integration by lowering communications costs between countries in the region, in particular trade in services, collaboration in health and education service delivery, and in part compensate for limited transport infrastructure between and within island countries. |
||||
| Impact | The key objective of the PPTA is to assist the Government and ADB in preparing necessary inputs for the project preparation. | ||||
| Project Outcome | |
|---|---|
| Description of Outcome | Thorough due diligence activities are required to validate the rationale, assure technical quality, examine any associated risks, and develop mitigation plans following relevant ADB guidelines. |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | The outputs of the TA include: (i) a sector analysis; (ii) a gender, social and poverty analysis looking at impact on affordability of communication services and additional social development dimensions; and (iii) a Project Administration Manual which will be included in the RRP. |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Regional |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | C |
| Indigenous Peoples | C |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | Types of consultation and participation will include group discussions and individual consultation with key government officials at all levels, regulatory authorities, private sector partners, along with focus group discussion with communities. |
| During Project Implementation | Project stakeholders include the Ministry of Finance and National Planning, Ministry of Information and Communications, Ministry of Public Enterprise, Tonga Communications Corporation and TCL. Digicel Tonga has been consulted for their interest and concerns on the proposed project as well as a possible equity investment or a long term capacity purchase agreement. |
| Business Opportunities | |
|---|---|
| Consulting Services | The PPTA requires six consultants with expertise in diverse areas for short duration. Therefore, individual consultants will be engaged for 6 person-months of international consultant services. Consultant requirements have been met. Implementation is still ongoing. |
| Responsible ADB Officer | Van Rijn, Johannes Jacobus Frederik |
| Responsible ADB Department | Pacific Department |
| Responsible ADB Division | Urban, Social Development & Public Management Division, PARD |
| Executing Agencies |
Asian Development Bank 6 ADB Avenue, Mandaluyong City 1550, Philippines |
| Timetable | |
|---|---|
| Concept Clearance | 08 Jul 2010 |
| Fact Finding | - |
| MRM | - |
| Approval | 08 Jul 2010 |
| Last Review Mission | - |
| PDS Creation Date | 13 Jul 2010 |
| Last PDS Update | 02 Sep 2011 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 08 Jul 2010 | - | 08 Jul 2010 | 31 Mar 2011 | 31 Dec 2011 | 31 Jan 2012 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 165,000.00 | 0.00 | 10,000.00 | 0.00 | 0.00 | 0.00 | 175,000.00 | 17 Jun 2022 | 71,463.99 |