| Project Name | Promoting Best Practices in Private Sector Participation in Urban Infrastructure in South Asia | ||||||||
| Project Number | 39596-012 | ||||||||
| Country / Economy | Regional |
||||||||
| Project Status | Closed | ||||||||
| Project Type / Modality of Assistance | Technical Assistance |
||||||||
| Source of Funding / Amount |
|
||||||||
| Strategic Agendas | Inclusive economic growth Regional integration |
||||||||
| Drivers of Change | Governance and capacity development Private sector development |
||||||||
| Sector / Subsector | Water and other urban infrastructure and services / Urban policy, institutional and capacity development |
||||||||
| Gender | No gender elements | ||||||||
| Description | |||||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||||
| Impact | |||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Regional |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | The TA will be implemented from February 2006 to February 2007. It will engage international resource persons with expertise in PSP, project finance, and urban infrastructure and municipal finance to conduct the training sessions and workshops, assisted by a domestic consultant recruited in each participating country (four consultants, 3 person-months each). In addition, a domestic consultant will be engaged for 10 person-months to staff a project secretariat within ADB. The consultants will be engaged by ADB as individuals in accordance with its Guidelines on the Use of Consultants by Asian Development Bank and Its Borrowers and other arrangements satisfactory to ADB for the engagement of domestic consultants. |
| Responsible ADB Officer | Fan, Mingyuan |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Urban Development and Water Division, SARD |
| Executing Agencies |
Asian Development Bank 6 ADB Avenue, Mandaluyong City 1550, Philippines |
| Timetable | |
|---|---|
| Concept Clearance | 14 Nov 2005 |
| Fact Finding | 19 Mar 2005 to 05 Apr 2005 |
| MRM | - |
| Approval | 03 Jan 2006 |
| Last Review Mission | - |
| PDS Creation Date | 28 Apr 2006 |
| Last PDS Update | 29 Oct 2010 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 03 Jan 2006 | - | 03 Jan 2006 | 28 Feb 2007 | 28 Feb 2010 | 30 Nov 2010 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 17 Jun 2022 | 587,003.65 |