| Project Name | Second Textbook Development | ||||
| Project Number | 36510-013 | ||||
| Country / Economy | Uzbekistan |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Loan |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Inclusive economic growth |
||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Private sector development |
||||
| Sector / Subsector | Education / Pre-primary and primary |
||||
| Gender | Some gender elements | ||||
| Description | |||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | C |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Wu, Lan |
| Responsible ADB Department | Central and West Asia Department |
| Responsible ADB Division | Uzbekistan Resident Mission |
| Executing Agencies |
Ministry of Public Education |
| Timetable | |
|---|---|
| Concept Clearance | 04 Apr 2003 |
| Fact Finding | 10 May 2004 to 28 May 2004 |
| MRM | 18 Jun 2004 |
| Approval | 29 Sep 2004 |
| Last Review Mission | - |
| PDS Creation Date | 25 Jan 2007 |
| Last PDS Update | 27 Jul 2010 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 29 Sep 2004 | 02 Nov 2004 | 01 Dec 2004 | 30 Jan 2010 | - | 09 Aug 2010 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 55.00 | Cumulative Contract Awards | |||
| ADB | 25.00 | 17 Feb 2023 | 18.36 | 0.00 | 100% |
| Counterpart | 30.00 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Feb 2023 | 18.36 | 0.00 | 100% |
| Project Page | https://www.adb.org//projects/36510-013/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=36510-013 |
| Date Generated | 06 June 2023 |