| Project Name | Rural Infrastructure Improvement | ||||||||||
| Project Number | 31304-013 | ||||||||||
| Country / Economy | Bangladesh |
||||||||||
| Project Status | Closed | ||||||||||
| Project Type / Modality of Assistance | Loan |
||||||||||
| Source of Funding / Amount |
|
||||||||||
| Strategic Agendas | Inclusive economic growth |
||||||||||
| Drivers of Change | Governance and capacity development Partnerships |
||||||||||
| Sector / Subsector |
Agriculture, natural resources and rural development / Rural market infrastructure Transport / Road transport (non-urban) - Transport policies and institutional development - Water transport (non-urban) |
||||||||||
| Gender | |||||||||||
| Description | |||||||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||||||
| Impact | |||||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Fawcett, Brian D. |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Bangladesh Resident Mission |
| Executing Agencies |
Local Government Engineering Department |
| Timetable | |
|---|---|
| Concept Clearance | 06 Jun 2000 |
| Fact Finding | 24 Jun 2002 to 12 Jul 2002 |
| MRM | 23 Aug 2002 |
| Approval | 02 Dec 2002 |
| Last Review Mission | - |
| PDS Creation Date | 05 Feb 2007 |
| Last PDS Update | 15 Apr 2010 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 02 Dec 2002 | 03 Feb 2003 | 07 Sep 2003 | 30 Jun 2009 | - | 12 Aug 2009 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 60.00 | Cumulative Contract Awards | |||
| ADB | 60.00 | 17 Feb 2023 | 58.37 | 0.00 | 100% |
| Counterpart | 0.00 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Feb 2023 | 58.37 | 0.00 | 100% |
| Project Page | https://www.adb.org//projects/31304-013/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=31304-013 |
| Date Generated | 06 June 2023 |