Bangladesh: Rural Infrastructure Improvement

Project Name Rural Infrastructure Improvement
Project Number 31304-013
Country / Economy Bangladesh
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1952-BAN: Rural Infrastructure Improvement
Asian Development Fund US$ 60.00 million
Loan: Rural Infrastructure Improvement
KfW Bankengruppe US$ 11.90 million
Deutsche Gesellschaft fur Tech. Zusammenarbeit US$ 5.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Partnerships
Sector / Subsector

Agriculture, natural resources and rural development / Rural market infrastructure

Transport / Road transport (non-urban) - Transport policies and institutional development - Water transport (non-urban)

Gender
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Fawcett, Brian D.
Responsible ADB Department South Asia Department
Responsible ADB Division Bangladesh Resident Mission
Executing Agencies
Local Government Engineering Department
Timetable
Concept Clearance 06 Jun 2000
Fact Finding 24 Jun 2002 to 12 Jul 2002
MRM 23 Aug 2002
Approval 02 Dec 2002
Last Review Mission -
PDS Creation Date 05 Feb 2007
Last PDS Update 15 Apr 2010

LoanĀ 1952-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Dec 2002 03 Feb 2003 07 Sep 2003 30 Jun 2009 - 12 Aug 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 60.00 Cumulative Contract Awards
ADB 60.00 17 Feb 2023 58.37 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 17 Feb 2023 58.37 0.00 100%

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.