| Project Name | Financial Market Regulation and Intermediation Program | ||||||||
| Project Number | 38276-013 | ||||||||
| Country / Economy | Philippines |
||||||||
| Project Status | Closed | ||||||||
| Project Type / Modality of Assistance | Loan Technical Assistance |
||||||||
| Source of Funding / Amount |
|
||||||||
| Strategic Agendas | Inclusive economic growth |
||||||||
| Drivers of Change | Governance and capacity development Private sector development |
||||||||
| Sector / Subsector | Finance / Finance sector development |
||||||||
| Gender | No gender elements | ||||||||
| Description | |||||||||
| Project Rationale and Linkage to Country/Regional Strategy | The proposed program is incuded in the Philippine Country Strategy and Program 2005-2007 | ||||||||
| Impact | |||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | C |
| Involuntary Resettlement | C |
| Indigenous Peoples | C |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | Not applicable. |
| Procurement | The loan proceeds will be used to finance the foreign exchange costs of items produced and procured in ADB member countries (other than items specified in the negative list of imports financed by other bilateral and multilateral sources). |
| Responsible ADB Officer | Schuster, Stephen R. |
| Responsible ADB Department | Southeast Asia Department |
| Responsible ADB Division | Public Management, Financial Sector and Trade Division, SERD |
| Executing Agencies |
Department of Finance |
| Timetable | |
|---|---|
| Concept Clearance | 17 Jun 2005 |
| Fact Finding | 02 Feb 2006 to 10 Jun 2006 |
| MRM | - |
| Approval | 06 Dec 2006 |
| Last Review Mission | - |
| PDS Creation Date | 11 Apr 2006 |
| Last PDS Update | 23 Oct 2009 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 06 Dec 2006 | 11 Dec 2006 | 20 Dec 2006 | 31 Dec 2008 | - | 22 Dec 2006 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 200.12 | Cumulative Contract Awards | |||
| ADB | 200.00 | 17 Feb 2023 | 200.00 | 0.00 | 100% |
| Counterpart | 0.12 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Feb 2023 | 200.00 | 0.00 | 100% |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 06 Dec 2006 | 14 Feb 2007 | 14 Feb 2007 | 05 Aug 2007 | 28 Feb 2010 | 16 Mar 2010 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 17 Feb 2023 | 547,156.54 |
| Project Page | https://www.adb.org//projects/38276-013/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=38276-013 |
| Date Generated | 06 June 2023 |