| Project Name | Tonle Sap Environmental Management | ||||||||||
| Project Number | 33418-013 | ||||||||||
| Country / Economy | Cambodia |
||||||||||
| Project Status | Closed | ||||||||||
| Project Type / Modality of Assistance | Grant Loan |
||||||||||
| Source of Funding / Amount |
|
||||||||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships |
||||||||||
| Sector / Subsector | Agriculture, natural resources and rural development / Water-based natural resources management |
||||||||||
| Gender | Effective gender mainstreaming | ||||||||||
| Description | |||||||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||||||
| Impact | |||||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Serrat, Olivier D. |
| Responsible ADB Department | Southeast Asia Department |
| Responsible ADB Division | Environment, Natural Resources & Agriculture Division, SERD |
| Executing Agencies |
Ministry of Agriculture, Forestry & Fisheries |
| Timetable | |
|---|---|
| Concept Clearance | 11 Sep 1999 |
| Fact Finding | 25 Feb 2002 to 15 Mar 2002 |
| MRM | 30 Apr 2002 |
| Approval | 21 Nov 2002 |
| Last Review Mission | - |
| Last PDS Update | 04 May 2009 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 21 Nov 2002 | 07 Feb 2003 | 27 Mar 2003 | 30 Jun 2008 | 31 Dec 2008 | 02 Sep 2009 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 14.82 | Cumulative Contract Awards | |||
| ADB | 10.91 | 17 Feb 2023 | 10.40 | 0.00 | 100% |
| Counterpart | 3.91 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Feb 2023 | 10.40 | 0.00 | 100% |