| Project Name | Evaluation of Environmental Policy and Investment for Water Pollution Control in the Huai River Basin and the Taihu Lake Basin | ||||
| Project Number | 38555-012 | ||||
| Country / Economy | China, People's Republic of |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Governance and capacity development Knowledge solutions |
||||
| Sector / Subsector | Agriculture, natural resources and rural development / Water-based natural resources management |
||||
| Gender | |||||
| Description | |||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Bruce Carrad |
| Responsible ADB Department | East Asia Department |
| Responsible ADB Division | Environment, Natural Resources & Agriculture Division, EARD |
| Executing Agencies |
State Environment Protection Administration |
| Timetable | |
|---|---|
| Concept Clearance | 12 Aug 2004 |
| Fact Finding | 29 Oct 2004 to 15 Nov 2004 |
| MRM | - |
| Approval | 25 Nov 2004 |
| Last Review Mission | - |
| Last PDS Update | 24 Oct 2008 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 25 Nov 2004 | 31 Jan 2005 | 31 Jan 2005 | 31 Mar 2006 | 30 Sep 2008 | 30 Sep 2008 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 500,000.00 | 0.00 | 250,000.00 | 0.00 | 0.00 | 0.00 | 750,000.00 | 17 Feb 2023 | 487,713.00 |