Project Name North East Community Restoration and Development - Extension Project
Project Number 38111-013
Country / Economy Sri Lanka
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2084-SRI: North East Community Restoration and Development - Extension Project
Asian Development Fund US$ 10.00 million
Strategic Agendas Environmentally sustainable growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Sector / Subsector

Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Agricultural production - Fishery - Livestock

Education / Education sector development

Finance / Inclusive finance

Health / Health system development

Public sector management / Social protection initiatives

Gender Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Rinker, Robert Gordon
Responsible ADB Department South Asia Department
Responsible ADB Division Sri Lanka Resident Mission
Executing Agencies
State Ministry of Provincial Councils & Local Government Affairs (formerly Ministry of Public Services, Provincial Councils and Local Government)
Timetable
Concept Clearance 29 May 2004
Fact Finding 17 Feb 2004 to 03 Mar 2004
MRM 26 Mar 2004
Approval 15 Jun 2004
Last Review Mission -
PDS Creation Date 05 Feb 2007
Last PDS Update 03 Oct 2008

LoanĀ 2084-SRI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
15 Jun 2004 13 Sep 2004 28 Dec 2004 30 Jun 2007 30 Jun 2009 09 Oct 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 14.30 Cumulative Contract Awards
ADB 10.00 17 Feb 2023 8.64 0.00 100%
Counterpart 4.30 Cumulative Disbursements
Cofinancing 0.00 17 Feb 2023 8.64 0.00 100%
 