| Project Name | Participatory Irrigation Development and Management Sector | ||||||
| Project Number | 32359-012 | ||||||
| Country / Economy | Indonesia |
||||||
| Project Status | Closed | ||||||
| Project Type / Modality of Assistance | Technical Assistance |
||||||
| Source of Funding / Amount |
|
||||||
| Strategic Agendas | Environmentally sustainable growth |
||||||
| Drivers of Change | Governance and capacity development |
||||||
| Sector / Subsector | Agriculture, natural resources and rural development / Irrigation |
||||||
| Gender | No gender elements | ||||||
| Description | The proposed project aims to (i) strengthen national and regional institutional as well as water users associations (WUAs) capacity for sustainable development of water resources, (ii) improve water-use efficiencies in irrigated agriculture, and (iii) increase agricultural production and productivity. The project inputs will include technical and advisory support to national and regional agencies, and rehabilitation and development of small- and medium-scale irrigation systems with direct participation of farmers in planning, implementation, and O&M. | ||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||
| Impact | |||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | The TA will provide for the services of a team of international and domestic consultants to assist the Government in preparing the proposed investment project. Other details of consulting services to be required will be determined during the fact-finding mission. |
| Responsible ADB Officer | Rahman, M. Jamilur |
| Responsible ADB Department | Southeast Asia Department |
| Responsible ADB Division | Environment, Natural Resources & Agriculture Division, SERD |
| Executing Agencies |
Directorate General of Water Resources, Ministry of Public Works & Housing, Republic of Indonesia Dr. Ir. Moch. Basuki Hadimujono, Director Jl Pattimura No.20, Kebayoran Baru Jakarta Selatan, Indonesia |
| Timetable | |
|---|---|
| Concept Clearance | 10 Mar 2001 |
| Fact Finding | 11 Sep 2001 to 18 Sep 2001 |
| MRM | - |
| Approval | 12 Dec 2001 |
| Last Review Mission | - |
| Last PDS Update | 06 Oct 2008 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 12 Dec 2001 | 31 Jan 2002 | 31 Jan 2002 | 31 Jul 2002 | 31 Oct 2002 | 26 Oct 2004 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 17 Jun 2022 | 797,480.11 |