Cambodia: Agriculture Sector Development

Project Name Agriculture Sector Development
Project Number 34380-012
Country / Economy Cambodia
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 3695-CAM: Agriculture Sector Development
Japan Special Fund US$ 600,000.00
Strategic Agendas Environmentally sustainable growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Sector / Subsector

Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development

Gender Gender equity
Description The TA will (i) conduct a study on the current situation and performance of the agriculture sector; (ii) assess the progress and impact of the reform measures launched under the First Agriculture Sector Program; (iii) examine past external assistance in agriculture and rural development in the country and lessons learned; (iv) examine critical issues and resource gaps remaining as constraints to agricultural growth; (v) assist the Government in formulating specific regulatory and institutional measures to achieve the sector objectives considered in the Second Socioeconomic Development Plan (SSDP: 2001-2005); (vi) prepare an investment proposal suitable for possible ADB financing; (vii) conduct necessary institutional, environmental and social assessments for the proposed investment; and (viii) examine financial and economic benefits, and risks involved in the proposed investment.
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services The TA will require (i) 15 person-months of international consultants, and (ii) 20 person-months of domestic consultants.
Procurement .
Responsible ADB Officer Masahiro Otsuka
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, SERD
Executing Agencies
Ministry of Agriculture, Forestry & Fisheries
Dr. Chan Tong Yves, Secretary of State
# 40 Norodom Blvd. Phnom Penh Cambodia
Timetable
Concept Clearance 09 Mar 2000
Fact Finding 30 Apr 2001 to 11 May 2001
MRM -
Approval 06 Aug 2001
Last Review Mission -
Last PDS Update 19 Feb 2007

TA 3695-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
06 Aug 2001 31 Aug 2001 31 Aug 2001 31 Jul 2002 31 May 2004 13 Oct 2004
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
600,000.00 0.00 0.00 0.00 0.00 0.00 600,000.00 17 Jun 2022 593,946.53

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.

Source URL: https://www.adb.org/projects/34380-012/main