China, People's Republic of: Henan Wastewater Management Project

Project Name Henan Wastewater Management Project
Project Number 34473-012
Country / Economy China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 4233-PRC: Henan Wastewater Management Project
Technical Assistance Special Fund US$ 800,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Sector / Subsector

Water and other urban infrastructure and services / Urban sewerage

Gender Some gender elements
Description The objectives of the Project are to improve the urban environment and public health through improved wastewater management, and to improve the quality of surface water and groundwater in and downstream of the project countries. Related objectives include: (i) creating municipal wastewater companies and making them efficient and commercially managed (ii) supporting comprehensive approaches to river basin wide pollution prevention and control and (iii) improving cost recovery from users through improved tariffs with gradual increases to full cost recovery.
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment A
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services A firm of international consultants, in association with domestic consultants, will be engaged by ADB in accordance with its Guidelines on the Use of Consultants based on the quality and cost based selection method and other arrangements satisfactory to ADB for the engagement of domestic consultants. The TA will require 43 person months of consulting services consisting of 16 person months of international consultants and 27 person months of domesctic consultants. The international consultants will have expertise in wastewater management, environment, social analysis, financial analysis, and economic analysis. The domestic consultants will have expertise in engineering services (wastewater management, sewer network, costing, mechanical, electrical, and instrumentation), environment, sociology, financial analysis, and economic analysis.
Procurement To be determined.
Responsible ADB Officer Fei, Yue
Responsible ADB Department East Asia Department
Responsible ADB Division Urban and Social Sectors Division, EARD
Executing Agencies
Henan Provincial Government (HPG)
Mr. Zhao Qingye, Director
Planning & Econ. Commission of HenanProv 23, Weier Road, Zhengzhou People's Republic of China
Timetable
Concept Clearance 09 Mar 2000
Fact Finding 09 Sep 2003 to 25 Sep 2003
MRM -
Approval 03 Dec 2003
Last Review Mission -
Last PDS Update 15 Dec 2006

TA 4233-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
03 Dec 2003 25 Feb 2004 25 Feb 2004 31 Aug 2004 31 Dec 2006 11 Jan 2007
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
800,000.00 0.00 0.00 0.00 0.00 0.00 800,000.00 17 Jun 2022 794,873.30

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.