| Project Name | Small and Medium Enterprise Development II | ||||
| Project Number | 36117-012 | ||||
| Country / Economy | Sri Lanka |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Inclusive economic growth |
||||
| Drivers of Change | Governance and capacity development Private sector development |
||||
| Sector / Subsector | Industry and trade / Small and medium enterprise development |
||||
| Gender | No gender elements | ||||
| Description | The purpose of SMESDP II is to further promote the growth and sustainability of SMEs in Sri Lanka. The TA will support: (i) policy reforms for SME development and economic growth; (ii) the improvement of industrial technology to increase competitiveness and export trade for SMEs; (iii) increase access to commercial finance for SMEs; (iv) the improvement of the enabling environment for SMEs; and (v) the infrastructure for the manufacturing and marketing of SME products. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | TA will be implemented over a five month period commencing in July 2005. A team of 4 international consultants and 4 national consultants will provide a total of 21 person-months of consulting services. A team of international consultants from a firm will be recruited in accordance with ADB's Guidelines on the Use of Consultants. National consultants will be engaged in accordance with procedures satisfactory to ADB. |
| Procurement | To be determined. |
| Responsible ADB Officer | Shah, Syed Ali-Mumtaz H. |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Public Management, Financial Sector and Trade Division, SARD |
| Executing Agencies |
Ministry of Finance and Planning P.O. Box 277 The Secretariat Building, Colombo 1 Sri Lanka |
| Timetable | |
|---|---|
| Concept Clearance | 10 Mar 2005 |
| Fact Finding | 31 Jan 2005 to 11 Feb 2005 |
| MRM | - |
| Approval | 18 Aug 2005 |
| Last Review Mission | - |
| Last PDS Update | 19 Oct 2007 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 18 Aug 2005 | 22 Sep 2005 | 22 Sep 2005 | 30 Apr 2006 | 31 Dec 2006 | 30 Nov 2007 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 550,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 550,000.00 | 17 Jun 2022 | 508,490.65 |