| Project Name | Public Sector Resource Management | ||||
| Project Number | 36168-012 | ||||
| Country / Economy | Sri Lanka |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Inclusive economic growth |
||||
| Drivers of Change | Governance and capacity development |
||||
| Sector / Subsector | Public sector management / Public expenditure and fiscal management |
||||
| Gender | No gender elements | ||||
| Description | The TA will help prepare a Public Sector Resource Management Project, suitable for ADB financing, which will assist the Government to lower the fiscal deficit by establishing a more effective and efficient fiscal administration through strengthening institutional capacity for revenue mobilization and expenditure management. The project will assist the Government to (i) establish an autonomous Revenue Authority, combining the existing Inland Revenue, Excise, and Customs Departments; and (ii) implement streamlined budgeting procedures and expenditure control processes within the Ministry of Finance. The consulting services under this TA will focus on the preparatory work needed to establish the Revenue Authority, as support for improved public expenditure management is being covered under a separate ADB TA. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | C |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | A consulting firm will be engaged to provide a total of 30 person-months of consulting services, 11 person-months of international and 19 person-months of domestic. The international consultants will have expertise in tax administration, human resource management, and information technology systems. The domestic consultants will have expertise in inland revenue, customs administration, tax law, human resource management, and information technology systems. |
| Procurement | To be determined. |
| Responsible ADB Officer | Zveglich Jr., Joseph Ernest |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Public Management, Financial Sector and Trade Division, SARD |
| Executing Agencies |
Ministry of Finance and Planning Mr. Faiz Mohideen P.O. Box 277 The Secretariat Building, Colombo 1 Sri Lanka |
| Timetable | |
|---|---|
| Concept Clearance | 10 Mar 2002 |
| Fact Finding | 28 May 2002 to 07 Jun 2002 |
| MRM | - |
| Approval | 23 Aug 2002 |
| Last Review Mission | - |
| Last PDS Update | 01 Feb 2007 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 23 Aug 2002 | 12 Sep 2002 | 12 Sep 2002 | 31 Jul 2003 | 31 Dec 2004 | 31 Oct 2005 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 500,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 500,000.00 | 17 Jun 2022 | 471,393.54 |