| Project Name | Strategic Policy Study on Collaborative Control of Air Pollution and Carbon Emissions in the Transport Sector | ||||
| Project Number | 51027-001 | ||||
| Country / Economy | China, People's Republic of |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Governance and capacity development Knowledge solutions |
||||
| Sector / Subsector | Transport / Transport policies and institutional development |
||||
| Gender | No gender elements | ||||
| Description | |||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | The objectives of controlling air pollution and GHG emissions in the PRC's transport sector in 2025 achieved. |
||||
| Project Outcome | |
|---|---|
| Description of Outcome | Policies on controlling air pollution and GHG emissions in the PRC's transport sector improved |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | Guideline on assessing the co-benefits of policies and measures for controlling air pollution and GHG emissions in the transport sector drafted Strategy for enhancing collaborative control of air pollution and GHG emissions in the transport sector drafted |
| Status of Implementation Progress (Outputs, Activities, and Issues) | The TA is extended until 31 December 2021 to complete all TA activities. |
| Geographical Location | Nation-wide |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | The Ministry of Transport, and other government agencies concerned with air pollution and carbon emission control were consulted during project design. |
| During Project Implementation | The TA became effective on 8 Nov 2017. MOT was consulted on consultant engagement. MOT is constantly giving advise about the TA. |
| Responsible ADB Officer | Lu, Xuedu |
| Responsible ADB Department | East Asia Department |
| Responsible ADB Division | EASI |
| Executing Agencies |
Comprehensive Planning Department, Ministry of Transport Ministry of Transportation |
| Timetable | |
|---|---|
| Concept Clearance | 23 Jun 2017 |
| Fact Finding | 10 Jul 2017 to 14 Jul 2017 |
| MRM | - |
| Approval | 28 Sep 2017 |
| Last Review Mission | - |
| Last PDS Update | 23 Sep 2021 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 28 Sep 2017 | 08 Nov 2017 | 08 Nov 2017 | 30 Sep 2019 | 31 Dec 2021 | 31 Mar 2022 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 350,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 350,000.00 | 11 Aug 2022 | 301,847.85 |
| Project Page | https://www.adb.org//projects/51027-001/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=51027-001 |
| Date Generated | 05 June 2023 |