China, People's Republic of: Strategic Policy Study on Collaborative Control of Air Pollution and Carbon Emissions in the Transport Sector

Project Name Strategic Policy Study on Collaborative Control of Air Pollution and Carbon Emissions in the Transport Sector
Project Number 51027-001
Country / Economy China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 9393-PRC: Strategic Policy Study on Collaborative Control of Air Pollution and Carbon Emissions in the Transport Sector
Climate Change Fund US$ 350,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Knowledge solutions
Sector / Subsector

Transport / Transport policies and institutional development

Gender No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

The objectives of controlling air pollution and GHG emissions in the PRC's transport sector in 2025 achieved.

Project Outcome
Description of Outcome

Policies on controlling air pollution and GHG emissions in the PRC's transport sector improved

Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Guideline on assessing the co-benefits of policies and measures for controlling air pollution and GHG emissions in the transport sector drafted

Strategy for enhancing collaborative control of air pollution and GHG emissions in the transport sector drafted

Status of Implementation Progress (Outputs, Activities, and Issues) The TA is extended until 31 December 2021 to complete all TA activities.
Geographical Location Nation-wide
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design The Ministry of Transport, and other government agencies concerned with air pollution and carbon emission control were consulted during project design.
During Project Implementation The TA became effective on 8 Nov 2017. MOT was consulted on consultant engagement. MOT is constantly giving advise about the TA.
Responsible ADB Officer Lu, Xuedu
Responsible ADB Department East Asia Department
Responsible ADB Division EASI
Executing Agencies
Comprehensive Planning Department, Ministry of Transport
Ministry of Transportation
Timetable
Concept Clearance 23 Jun 2017
Fact Finding 10 Jul 2017 to 14 Jul 2017
MRM -
Approval 28 Sep 2017
Last Review Mission -
Last PDS Update 23 Sep 2021

TA 9393-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
28 Sep 2017 08 Nov 2017 08 Nov 2017 30 Sep 2019 31 Dec 2021 31 Mar 2022
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
350,000.00 0.00 0.00 0.00 0.00 0.00 350,000.00 11 Aug 2022 301,847.85

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.

Source URL: https://www.adb.org/projects/51027-001/main