Myanmar: Second Mandalay Urban Services Improvement Project

Project Name
Second Mandalay Urban Services Improvement Project
Project Number
50109-002
Country / Economy
  • Myanmar
Project Status
Proposed
Project Type / Modality of Assistance
  • Grant
  • Loan
Source of Funding / Amount
Loan: Second Mandalay Urban Services Improvement Project
Source Amount
concessional ordinary capital resources lending / Asian Development Fund US$ 150.00 million
Strategic Agendas
  • Environmentally sustainable growth
  • Inclusive economic growth
Drivers of Change
  • Gender Equity and Mainstreaming
  • Governance and capacity development
  • Partnerships
Sector / Subsector
  • Transport / Urban public transport

  • Water and other urban infrastructure and services / Urban sanitation - Urban sewerage - Urban solid waste management - Urban water supply

Gender
Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Outcome
Outputs
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Business Opportunities

Consulting Services

One package of consulting services with a value of $975,000 will

be procured. through firm(s). The TA will require 10 positions and 22 person-months (pm) of

international, and 13 positions and 44 pm of national consulting services. The consultants will be

engaged through firm(s). The quality- and cost-based selection method with quality-cost ratio of

90:10, using simplified technical proposal procedures, will be followed. The time-based contract

will be used. ADB will select and engage the consultant in accordance with the Guidelines on Use (2013, as amended from time to time). The consultants may procure equipment through shopping in accordance with the ADB's Procurement Guidelines (2015, amended from

time to time). Upon completion of the TA, equipment procured under the TA will be transferred to

the executing agencies.

Procurement

The consultants may procure equipment through shopping in accordance with the ADB's Procurement Guidelines (2015, amended from

time to time). Upon completion of the TA, equipment procured under the TA will be transferred to

the executing agencies

Contact

Responsible ADB Officer
Eri Honda
Responsible ADB Department
Southeast Asia Department
Responsible ADB Division
Urban Development and Water Division, SERD

Timetable

Concept Clearance
-
Fact Finding
-
MRM
-
Approval
-
Last Review Mission
-
Last PDS Update
04 Aug 2017

Funding


ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.