| Project Name | Sustainable Infrastructure Assistance Program - Strengthening Results-Based Lending Independent Monitoring in Irrigation (Subproject 10) | ||||||||
| Project Number | 46380-020 | ||||||||
| Country / Economy | Indonesia |
||||||||
| Project Status | Closed | ||||||||
| Project Type / Modality of Assistance | Technical Assistance |
||||||||
| Source of Funding / Amount |
|
||||||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships |
||||||||
| Sector / Subsector | Agriculture, natural resources and rural development / Irrigation |
||||||||
| Gender | Some gender elements | ||||||||
| Description | The transaction technical assistance (TRTA) is a subproject under Technical Assistance Cluster 0013-INO: Sustainable Infrastructure Assistance Program as agreed with the Australian Government Department of Foreign Affairs and Trade. The TRTA supports the implementation of the Integrated Participatory Development and Management of Irrigation Program, specifically on (i) strengthening financial management system and capacity towards results based financing; (ii) upgrading the monitoring and evaluation system and procedures to ensure timely and accurate reporting of the Program and disbursement linked indicators (DLIs); and (iii) strengthening capacity to verify achievement of the DLIs and the program action plan. | ||||||||
| Project Rationale and Linkage to Country/Regional Strategy | The TRTA is included in ADB''s country operations business plan, 2017 -2019 for Indonesia. The TRTA is supporting the Ministry of Public Works and Housing in effectively implementing the Integrated Participatory Development and Management of Irrigation Program to accelerate the delivery of the 2015-2019 National Medium Term Development Plan targets. | ||||||||
| Impact | |||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Nation-wide |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | Stakeholder consultations and workshops were conducted to identify key gaps in government legal framework and formulate recommendations on delivery of the irrigation improvement program objectives. |
| During Project Implementation | The TA facilitated consultations with the relevant government agencies and stakeholders to finalize the key independent verification guidelines for disbursement-linked indicators; technical guidelines for water user empowerment and performance assessment; Irrigated Agriculture Management Plan; preparation for operation and maintenance; and social and environment safeguards. |
| Business Opportunities | |
|---|---|
| Consulting Services | A total of 9 individual consultants have been engaged by ADB: 1 international consultant (i) Information System Specialist; and 8 national consultants (ii) Irrigation Management Specialist; (iii) Irrigation Infrastructure Specialist; (iv) Financial Management Specialist; (v) Institutional Specialist; (vi) Geographic Information System and Mapping Specialist; (vii) Information System Specialist; (viii) Office Coordinator; and (ix) a National Web Developer and Designer. |
| Procurement | Equipment, training, workshops and surveys were procured and organized accordance with ADB''s Procurement Policy (2017, as amended from time to time) and ADB Procurement Regulations for ADB Borrowers - Goods, Works, Non-consulting and Consulting Services (2017, as amended from time to time). |
| Responsible ADB Officer | Quincieu, Eric |
| Responsible ADB Department | Southeast Asia Department |
| Responsible ADB Division | Environment, Natural Resources & Agriculture Division, SERD |
| Executing Agencies |
Directorate General of Water Resources Jl. Pattimura No.20, Jakarta |
| Timetable | |
|---|---|
| Concept Clearance | - |
| Fact Finding | - |
| MRM | - |
| Approval | 24 Aug 2017 |
| Last Review Mission | - |
| Last PDS Update | 30 Sep 2019 |
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 24 Aug 2017 | 28 Aug 2017 | 28 Aug 2017 | 30 Jun 2019 | 31 Dec 2019 | 28 Feb 2020 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 0.00 | 820,000.00 | 50,000.00 | 0.00 | 0.00 | 0.00 | 870,000.00 | 17 Jun 2022 | 812,618.54 |
| Project Page | https://www.adb.org//projects/46380-020/main |
| Request for Information | http://www.adb.org/forms/request-information-form?subject=46380-020 |