Philippines: Railway Project Implementation Support and Institutional Strengthening

Project Name Railway Project Implementation Support and Institutional Strengthening
Project Number 52083-006
Country / Economy Philippines
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 9570-PHI: Railway Project Implementation Support and Institutional Strengthening
Japan Fund for Prosperous and Resilient Asia and the Pacific US$ 2.00 million
TA 9570-PHI: Railway Project Implementation Support and Institutional Strengthening (Supplementary)
Technical Assistance Special Fund US$ 900,000.00
TA 9570-PHI: Railway Project Implementation Support and Institutional Strengthening
Technical Assistance Special Fund US$ 500,000.00
TA 9570-PHI: Railway Project Implementation Support and Institutional Strengthening
Technical Assistance Special Fund US$ 500,000.00
Operational Priorities OP1: Addressing remaining poverty and reducing inequalities
OP5: Promoting rural development and food security
Sector / Subsector

Transport / Rail transport (non-urban)

Gender No gender elements
Description The project will support the construction of the 51-kilometer (km) section of a new railway line connecting Metro Manila and the regional center in Clark and the Clark International Airport, located in the Central Luzon Region, around 100 km north of Manila. The new railway line will (i) provide affordable, reliable, and safe public transport; (ii) reduce greenhouse gas emissions; and (iii) cut the journey time by half to less than one hour. It is proposed that the project will be financed by a multitranche financing facility with an amount of $2.75 billion from regular ordinary capital resources.
Project Rationale and Linkage to Country/Regional Strategy The project will support the national spatial strategy (NSS) of the Philippine Development Plan 2017-2022 which serves as the basis for policies on urban and infrastructure development in according with AmBisyon Natin 2040.The Government' Build, Build, Build program, in which this project is included, builds upon this national strategy.
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Angeles, Apalit, Calumpit, Clark Special Economic Zone, Mabalacat, Malolos, Minalin, San Fernando, Santo Tomas
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design The TA will support the stakeholder communication, and consultation activities of the Project.
During Project Implementation The social safeguards and communication consultants engaged under the TA supported the stakeholder communication, and consultation activities of the Project in coordination with the Department of Transportation.
Business Opportunities
Consulting Services ADB will engage the consultants following the ADB Procurement Policy (2017, as amended from time to time) and its associated project administration instructions and/or staff instructions.
Procurement The TA resources will be disbursed following ADB's Technical Disbursement Handbook (2010, as amended from time to time). The equipment will be turned over to the recipient government agency or disposed of in accordance with ADB's instructions.
Responsible ADB Officer Roesner, Markus
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Transport and Communications Division, SERD
Executing Agencies
Department of Transportation
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 22 Aug 2018
Last Review Mission -
Last PDS Update 28 Sep 2022

TA 9570-PHI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
22 Aug 2018 25 Sep 2018 25 Sep 2018 31 Aug 2020 30 Jun 2024 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
1,900,000.00 2,000,000.00 0.00 0.00 0.00 0.00 3,900,000.00 09 Jan 2023 2,069,522.76

ADB provides the information contained in this project data sheet (PDS) solely as a resource for its users without any form of assurance. Whilst ADB tries to provide high quality content, the information are provided "as is" without warranty of any kind, either express or implied, including without limitation warranties of merchantability, fitness for a particular purpose, and non-infringement. ADB specifically does not make any warranties or representations as to the accuracy or completeness of any such information.