Project Name
Capacity Development of Ministry of Transportation in Project Preparation and Implementation (Subproject 5)
Project Number
52152-008
Country / Economy
  • Indonesia
Project Status
Active
Project Type / Modality of Assistance
  • Technical Assistance
Source of Funding / Amount
TA 9947-INO: Capacity Development of Ministry of Transportation in Project Preparation and Implementation
Source Amount
Government of Australia US$ 1.00 million
TA 9947-INO: Capacity Development of Ministry of Transportation in Project Preparation and Implementation (Subproject 5)
Source Amount
Government of Australia US$ 500,000.00
Operational Priorities
  • OP1: Addressing remaining poverty and reducing inequalities
  • OP2: Accelerating progress in gender equality
  • OP6: Strengthening governance and institutional capacity
Sector / Subsector
  • Transport / Air transport - Transport policies and institutional development - Urban public transport - Water transport (non-urban)

Gender
Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Nation-wide, Indonesia

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Heriawan, Andri
Responsible ADB Department
Sectors Group
Responsible ADB Division
Transport Sector Office (SG-TRA)
Executing Agencies
Directorate General of Civil Aviation
Directorate General of Railways
Directorate General of Sea Transportation

Timetable

Concept Clearance
-
Fact Finding
-
MRM
-
Approval
11 Feb 2020
Last Review Mission
-
Last PDS Update
12 Feb 2020

Funding

TA 9947-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Feb 2020 - 11 Feb 2020 28 Feb 2023 31 Dec 2025 -
Financing Plan/TA Utilization
ADB Cofinancing Counterpart Total
Gov Beneficiaries Project Sponsor Others
0.00 1,500,000.00 0.00 0.00 0.00 0.00 1,500,000.00
Cumulative Disbursements
Date Amount
01 Jul 2024 547,648.73
 