Project Name | Research for Demonstration of Carbon Capture, Utilization, and Storage Technologies in Industrial Sectors of Yunnan Province | ||||
Project Number | 55035-001 | ||||
Country / Economy | China, People's Republic of |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP6: Strengthening governance and institutional capacity |
||||
Sector / Subsector | Industry and trade / Trade and services |
||||
Gender | Some gender elements | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | Yunnan CO2 emission peaking target achieved before 2030. |
Project Outcome | |
---|---|
Description of Outcome | CCUS strategy to achieve CO2 emissions peaking and neutrality in Yunnan Province improved |
Progress Toward Outcome | Not yet due. |
Implementation Progress | |
Description of Project Outputs | Study on the role of CCUS technology in achieving carbon emission peaking and carbon neutrality in Yunnan Province produced |
Status of Implementation Progress (Outputs, Activities, and Issues) | Six individual consultants were contracted and mobilized their services. |
Geographical Location | Yunnan |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Keep close communication with the executing agency (Department of Ecology and Environment of Yunnan Province (DEEY) and implementing agency (Division of International Cooperation, DEEY). |
During Project Implementation | Close consultation and coordination with the executing agency (Department of Ecology and Environment of Yunnan Province (DEEY), the implementing agency (Division of International Cooperation, DEEY), the government-owned Wugang Group Kunming Iron and Steel Co., Ltd., other relevant agencies, private sector and other stakeholders will be consulted during project implementation. |
Business Opportunities | |
---|---|
Consulting Services | A consulting firm and national consultants will be engaged during the implementation of the TA. |
Procurement | The TA will support to procure necessary equipment related to CCUS testing and monitoring to enhance EA capacity in promoting CCUS investment projects and monitoring the effectiveness. The equipment includes those testing the capture of CO2 in industrial sector, monitoring and evaluation of stored CO2, and utilization evaluation of CO2, which will cost about $220,000. Given the equipment are standard goods and can be procured in market, the consulting firm to be hired will be responsible for this procurement. |
Responsible ADB Officer | Bano, Alfredo |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | EASI |
Executing Agencies |
Department of Ecology and Environment of Yunnan Province |
Timetable | |
---|---|
Concept Clearance | 13 Jul 2021 |
Fact Finding | 04 Aug 2021 to 06 Aug 2021 |
MRM | - |
Approval | 10 Dec 2021 |
Last Review Mission | - |
Last PDS Update | 21 Sep 2022 |
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
10 Dec 2021 | 14 Dec 2021 | 14 Dec 2021 | 31 Aug 2023 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
300,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 300,000.00 | 21 Sep 2022 | 7,487.43 |