Project Name
Key Indicators for Asia and the Pacific 2021-2023 Subproject 2: Key Indicators for Asia and the Pacific 2022
Project Number
53344-003
Country / Economy
  • Regional
Project Status
Closed
Project Type / Modality of Assistance
  • Technical Assistance
Source of Funding / Amount
TA 6797-REG: Key Indicators for Asia and the Pacific 2021-2023 Subproject 2: Key Indicators for Asia and the Pacific 2022
Source Amount
Technical Assistance Special Fund US$ 800,000.00
Operational Priorities
  • OP6: Strengthening governance and institutional capacity
Sector / Subsector
  • Public sector management / Economic affairs management

Gender
No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Evidence-based policymaking, investment decision, and project design in ADB regional member economies influenced

Project Outcome

Description of Outcome

Use of Key Indicators for Asia and the Pacific and other relevant statistical data and analysis for evidence-based policymaking by government officials and economic researchers sustained

Progress Toward Outcome

Implementation Progress

Description of Project Outputs

1. Key Indicators for Asia and the Pacific 2022 and Basic Statistics 2022 finalized and published

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Regional

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Business Opportunities

Consulting Services
Preparation of statistical tables for KI 2022 and other related data products will require time-based inputs from national consultants selected via individual selection process. An estimated 280 person-months of national consultancy inputs would be required to prepare statistical tables for KI 2022, conduct research and analysis for the KI Special Supplements, update the indicators for BS 2022, work on updating statistics on GVC, update and enhance KIDB and the Statistics Portal, and prepare infographics and other requirements of the final outputs. Preparation of data stories will also be incorporated in the TOR of selected national consultants. An estimated six person-months of output-based and time-based international consultancy inputs may be needed for writing data stories and statistical commentaries for KI and its supplements, editing, providing IT-related advice and support for KI, and writing commissioned papers for the topic of the special supplements. ADB will engage the consultants following the ADB Procurement Policy (2017, as amended from time to time) and its associated project administration instructions and/or staff instructions.
Procurement
Statistical and other software and licenses, survey data sets, data subscriptions, and IT equipment will be procured under the TA as needed and in coordination with relevant departments (e.g., ITD for IT-related procurement). Micro-level data such as surveys on household income and expenditure, labor force, among others, will be procured depending on data requirements of research activities of EROD-SDI and other divisions in ERCD, subject to the item allocation on the TA's cost estimates and financing plan. This will also include subscriptions on a limited basis to special databases that are used as source of information for the special supplements and special studies to be conducted by ERCD staff. IT equipment may be procured based on needs determined during TA implementation. Procurement will follow the ADB Procurement Policy (2017, as amended from time to time) and the associated staff instructions. Procurement and disbursement will have to be cleared with the Project Lead, and subject to set thresholds, with EROD-SDI Head.

Contact

Responsible ADB Officer
Martinez, Arturo Jr. M.
Responsible ADB Department
Economic Research and Development Impact Department
Responsible ADB Division
Statistics and Data Innovation Unit (EROD-SDI)
Executing Agencies
Asian Development Bank

Timetable

Concept Clearance
-
Fact Finding
19 Aug 2021 to 19 Aug 2021
MRM
-
Approval
08 Oct 2021
Last Review Mission
-
Last PDS Update
14 Oct 2021

Funding

TA 6797-REG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
08 Oct 2021 - 08 Oct 2021 30 Jun 2023 - 01 Nov 2023
Financing Plan/TA Utilization
ADB Cofinancing Counterpart Total
Gov Beneficiaries Project Sponsor Others
800,000.00 0.00 0.00 0.00 0.00 0.00 800,000.00
Cumulative Disbursements
Date Amount
27 Nov 2023 739,613.90
 
This page was generated from /projects/53344-003/main on 06 June 2024