Project Name Flood Damage Emergency Reconstruction Project
Project Number 46009-001
Country Cambodia
Project Status Active
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Grant 0285-CAM: Flood Damage Emergency Reconstruction Project
Government of Australia US$ 5.25 million
Loan 2852-CAM: Flood Damage Emergency Reconstruction Project
Concessional ordinary capital resources / Asian Development Fund US$ 55.00 million
Grant 0285-CAM: Flood Damage Emergency Reconstruction Project (Additional Financing)
Government of Australia US$ 6.68 million
Loan 3125-CAM: Flood Damage Emergency Reconstruction Project (Additional Financing)
Concessional ordinary capital resources / Asian Development Fund US$ 75.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector

Agriculture, natural resources and rural development - Irrigation - Rural water policy, institutional and capacity development

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description The project will rehabilitate infrastructure (national, provincial, and rural roads and irrigation facilities) damaged by the 2011 flood to be implemented from April 2012 to March 2015.
Project Rationale and Linkage to Country/Regional Strategy ADB received high level request from the Royal Government of Cambodia to provide emergency assistance to rehabilitate flood damaged infrastructure.
Impact

Current Project

Economic and social recovery from the 2011 floods in project provinces

Overall project

Economic and social recovery from the 2011 and 2013 floods in the project provinces accelerated

Project Outcome

Description of Outcome

Current Project

Restoration of critical public and social infrastructure assets to their original standards or better

Overall project

Reconstruction of critical infrastructure to restore livelihoods and access and protect against future flooding

Progress Toward Outcome Overall implementation progress is on track. Most subprojects have been completed, while the remaining subprojects are almost completed.
Implementation Progress
Description of Project Outputs

Output 1: Current project: National and provincial roads damaged by floods (including bridges and culverts) rehabilitated and reconstructed

Output 2: Current project: Rural roads damaged by floods (including bridges and culverts) rehabilitated and reconstructed

Output 3: Current project: Irrigation facilities rehabilitated and reconstructed

Output 4: Current project: Project managed and monitored efficiently

Output 1: Overall project: unchanged

Output 2: Overall project: unchanged

Output 3: Overall project: Irrigation facilities rehabilitated and flood management improved

Output4: Overall project: unchanged

Status of Implementation Progress (Outputs, Activities, and Issues)

Under the FDERP, all subprojects for rehabilitation of national/provincial roads, and bridges/culverts on these roads completed.

Under the FDERP, all subprojects for rehabilitation of rural roads, and bridges/culverts on these roads completed.

All irrigation subprojects under the FDERP were completed.

For national/provincial roads component under the FDERP- Additional Financing, all three Stage 2 contracts have been completed. The seven contracts under stage 3 have been awarded. Five contracts have been completed while the remaining 2 contracts are almost completed. The overall progress of the construction works is estimated at 85%.

For rural roads component under the FDERP- Additional Financing, the overall progress of the construction works is estimated at 98%.

For irrigation component under the FDERP-AF, Stage 3 civil works consists of nine subprojects which were packed into eight contract packages and one package of the installation of 8 Automatic Weather Stations (AWS) and 10 hydromet stations. The contract amount of the nine packages totaled $12.02 million. Two packages consist of CW12 and CW13 were added to the original 9 subprojects. CW12 is under construction while CW13 is in procurement stage.

Construction works for five packages, MOWRAM-CW01B, CW06 Lot 1, CW07, CW10, CW11 have been completed; CW06 Lot 2 has been completed. The overall progress of CW08 and CW09 is 69% and 90% respectively. Together, Stage 2 and 3 subprojects will be capable of irrigating 70,394 ha which are equivalent to about 188% of the target irrigated areas of this output.

The installation of eight AWS and ten hydrological stations have been completed. The hydrological data obtaining from AWS and hydromet stations have been uploaded into MOWRAM website. The training to PIU staff has also been provided by the supplier.

Geographical Location

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects Environmental Management Plans (EMPs) for roads and irrigation sub-projects have been prepared. EMPs have been incorporated into the civil works bidding documents and in the contracts. The initial environmental examinations (IEEs) have also been prepared. The EA/IAs, consultants and ADB Project team are monitoring implementation of EMPs closely.
Involuntary Resettlement A resettlement framework was prepared prior to project approval. The subprojects approved so far are classified as Category C for involuntary resettlement.
Indigenous Peoples The Project is not affecting indiginous people as defined under ADB's Safeguard Policy Statement (2009).
Stakeholder Communication, Participation, and Consultation
During Project Design The project team have had numerious consultations with relevant government ministries, including the National Committee for Disaster Management, and selected development partners during the Reconnaissance Mission in December and Fact-finding mission in January-Feb 2012.
During Project Implementation The project team have conducted consultations with the relevant Government ministries and project beneficiaries during project review missions and site visits.

Responsible Staff

Responsible ADB Officer Nida, Ouk
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Cambodia Resident Mission
Executing Agencies
Ministry of Economy and Finance
[email protected]
Street 92, Sangkat Wat Phnom
Khan Daun Penh, Phnom Penh City
Cambodia
Ministry of Public Works and Transport
[email protected]
4th Floor Eastern Building
Corner Norodom Boulevard Street 106
Phnom Penh, Cambodia
Ministry of Rural Development
[email protected]
169 Corner Road Soviet Blvd.
Phnom Penh
Cambodia
Ministry of Water Resources and Meteorology
364 Monivong Blvd, Khan Chamkamorn Phnom Penh, Cambodia

Timetable

Concept Clearance 09 Jan 2012
Fact Finding 26 Jan 2012 to 10 Feb 2012
MRM 29 Feb 2012
Approval 27 Mar 2012
Last Review Mission -
Last PDS Update 16 Mar 2017

Grant 0285-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Mar 2012 04 Apr 2012 14 May 2012 30 Sep 2015 30 Sep 2017 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 11.93 Cumulative Contract Awards
ADB 0.00 27 Mar 2012 0.00 11.93 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 11.93 27 Mar 2012 0.00 11.68 98%

Loan 2852-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Mar 2012 04 Apr 2012 14 May 2012 30 Sep 2015 - 10 Mar 2016
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 61.93 Cumulative Contract Awards
ADB 55.00 27 Mar 2012 0.00 50.87 99%
Counterpart 6.93 Cumulative Disbursements
Cofinancing 0.00 27 Mar 2012 0.00 51.64 100%

Loan 3125-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Apr 2014 23 Apr 2014 30 May 2014 30 Sep 2017 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 75.00 Cumulative Contract Awards
ADB 75.00 11 Apr 2014 0.00 64.02 95%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 11 Apr 2014 0.00 55.11 82%

 
This page was generated from https://www.adb.org/projects/46009-001/main on 30 March 2017