Cambodia : Stung Chinit Irrigation and Rural Infrastructure Project

Sovereign Project | 29257-013

Project Details

  • Project Officer
    Serrat, Olivier D.
    Southeast Asia Department
    Request for information
  • Country/Economy
    Cambodia
  • Sector
    • Agriculture, natural resources and rural development
Project Name Stung Chinit Irrigation and Rural Infrastructure Project
Project Number 29257-013
Country / Economy Cambodia
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1753-CAM: Stung Chinit Irrigation and Rural Infrastructure Project
Asian Development Fund US$ 16.00 million
Loan: Stung Chinit Irrigation and Rural Infrastructure Project
Agence Francaise de Developpement US$ 2.60 million
Strategic Agendas Environmentally sustainable growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Sector / Subsector

Agriculture, natural resources and rural development / Agricultural production - Irrigation

Transport / Road transport (non-urban)

Gender Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Serrat, Olivier D.
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Cambodia Resident Mission (CARM)
Executing Agencies
Ministry of Rural Development
Ministry of Water Resources and Meteorology
Timetable
Concept Clearance 11 Jul 1996
Fact Finding 07 Feb 2000 to 25 Feb 2000
MRM 11 Apr 2000
Approval 05 Sep 2000
Last Review Mission -
PDS Creation Date 28 Feb 2007
Last PDS Update 23 Jan 2009

Loan 1753-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Sep 2000 12 Oct 2000 28 Feb 2001 30 Jun 2007 30 Jun 2008 04 Dec 2008
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 16.40 Cumulative Contract Awards
ADB 16.00 17 Feb 2023 14.74 0.00 100%
Counterpart 0.40 Cumulative Disbursements
Cofinancing 0.00 17 Feb 2023 14.74 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Stung Chinit Irrigation and Rural Infrastructure Project Project/Program Completion Reports Dec 2009
Stung Chinit Irrigation and Rural Infrastructure Project Reports and Recommendations of the President Aug 2000

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Stung Chinit Irrigation and Rural Infrastructure Project: Resettlement Completion Report Social Monitoring Reports Sep 2009
Final Report on Income Restoration Program under Additional Impacts Resettlement Plans Sep 2009
Stung Chinit Irrigation and Rural Infrastructure Project: Final Report on Income Restoration Program under Additional Impacts Resettlement Plans Sep 2009
Stung Chinit Irrigation and Rural Infrastructure Project: Final Report on Income Restoration Program under Additional Impacts Resettlement Plans Sep 2009
Final Report on Income Restoration Program under Resettlement Plan Phase III (Ochork Tributary) Resettlement Plans Jul 2009
Report on Additional Impacts to RP Phase I and II (Out of Resettlement Scope) Stung Chinit Irrigation Project Resettlement Plans Apr 2009
Final Report on Income Restoration Program under Resettlement Plan Phase II (Stung Chinit Reservoir) Resettlement Plans Jul 2008
Stung Chinit Irrigation and Rural Infrastructure Project (Loan No. 1753-CAM [SF]): Irrigation Scheme Resettlement Plans Nov 2006
Stung Chinit Irrigation and Rural Infrastructure Project (Loan No. 1753-CAM [SF]): Stung Chinit Reservoir Resettlement Planning Documents Nov 2006
Stung Chinit Irrigation and Rural Infrastructure Project (Loan No. 1753-CAM [SF]): Ochork Tributary Resettlement Plans Nov 2006
Stung Chinit Irrigation and Rural Infrastructure Project (Loan No. 1753-CAM [SF]): Irrigation Scheme Resettlement Plans Nov 2006
Stung Chinit Irrigation and Rural Infrastructure Project (Loan No. 1753-CAM [SF]): Ochork Tributary Resettlement Plans Nov 2006

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Cambodia: Stung Chinit Irrigation and Rural Infrastructure Project Validations of Project Completion Reports Dec 2012

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.