Kyrgyz Republic : Third Road Rehabilitation
Project Details
-
Project Officer
Miller, Jeffrey M.
Central and West Asia Department
Request for information -
Country/Economy
Kyrgyz Republic -
Modality
Related Projects
Project Name | Third Road Rehabilitation | ||||
Project Number | 30311-013 | ||||
Country / Economy | Kyrgyz Republic |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Inclusive economic growth |
||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||
Gender Equity and Mainstreaming | Some gender elements | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | |
Indigenous Peoples |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Miller, Jeffrey M. |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Kyrgyz Resident Mission |
Executing Agencies |
Ministry of Transport, Architecture, Construction and Communications (formerly Ministry of Transport and Roads) |
Timetable | |
---|---|
Concept Clearance | 01 May 1997 |
Fact Finding | 27 Feb 2001 to 16 Mar 2001 |
MRM | 18 May 2001 |
Approval | 31 Oct 2001 |
Last Review Mission | - |
PDS Creation Date | 10 Nov 2006 |
Last PDS Update | 06 Oct 2008 |
Loan 1853-KGZ
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
31 Oct 2001 | 29 Apr 2002 | 12 Sep 2002 | 30 Apr 2005 | 30 Jul 2007 | 10 Dec 2007 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 50.00 | Cumulative Contract Awards | |||
ADB | 40.00 | 17 Feb 2023 | 45.89 | 0.00 | 100% |
Counterpart | 10.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Feb 2023 | 45.89 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Third Road Rehabilitation Project | Project/Program Completion Reports | Oct 2008 |
Third Road Rehabilitation Project | Reports and Recommendations of the President | Sep 2001 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Kyrgyz Republic: Road Rehabilitation Project, Second Road Rehabilitation Project, and Third Road Rehabilitation Project [Loans: 1444-KGZ (SF), 1630-KGZ (SF), 1853-KGZ (SF)] | Project Performance Evaluation Reports | Aug 2010 |
Kyrgyz Republic: Third Road Rehabilitation Project | Validations of Project Completion Reports | Nov 2009 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.