China, People's Republic of: Shaanxi Roads Development

Sovereign Project | 30424-013 Status: Closed

Project Details

Project Officer
Ojiro, Makoto East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Loan
Sector
  • Transport
 
Project Name Shaanxi Roads Development
Project Number 30424-013
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1838-PRC: Shaanxi Roads Development
Ordinary capital resources US$ 250.00 million
Loan: Shaanxi Roads Development
China Construction Bank US$ 181.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Shaanxi Province

Safeguard Categories

Environment A
Involuntary Resettlement A
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Responsible Staff

Responsible ADB Officer Ojiro, Makoto
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
Shaanxi Provincial Communications Department
Tian Quanliang
Xi'an, Shaanxi Province

Timetable

Concept Clearance 13 Mar 1998
Fact Finding 27 Nov 2000 to 07 Dec 2000
MRM 14 Feb 2001
Approval 30 Aug 2001
Last Review Mission -
PDS Creation Date 24 Nov 2006
Last PDS Update 08 Dec 2010

Loan 1838-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
30 Aug 2001 10 Jun 2002 08 Nov 2002 31 Mar 2006 31 Jul 2009 07 Jan 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 757.00 Cumulative Contract Awards
ADB 250.00 30 Aug 2001 220.38 0.00 89%
Counterpart 326.00 Cumulative Disbursements
Cofinancing 181.00 30 Aug 2001 248.46 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Shaanxi Roads Development Project Project/Program Completion Reports Jul 2010

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Shaanxi Roads Development Project Summary Environmental Impact Assessments Feb 2001

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
People’s Republic of China: Shaanxi Roads Development Project Validations of Project Completion Reports Dec 2011

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.