Bangladesh : Rural Infrastructure Improvement
Project Details
-
Project Officer
Fawcett, Brian D.
South Asia Department
Request for information -
Country/Economy
Bangladesh -
Modality
Related Projects
| Project Name | Rural Infrastructure Improvement | ||||||||||
| Project Number | 31304-013 | ||||||||||
| Country / Economy | Bangladesh |
||||||||||
| Project Status | Closed | ||||||||||
| Project Type / Modality of Assistance | Loan |
||||||||||
| Source of Funding / Amount |
|
||||||||||
| Strategic Agendas | Inclusive economic growth |
||||||||||
| Drivers of Change | Governance and capacity development Partnerships |
||||||||||
| Sector / Subsector |
Agriculture, natural resources and rural development / Rural market infrastructure Transport / Road transport (non-urban) - Transport policies and institutional development - Water transport (non-urban) |
||||||||||
| Gender | |||||||||||
| Description | |||||||||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||||||||
| Impact | |||||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Fawcett, Brian D. |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Bangladesh Resident Mission |
| Executing Agencies |
Local Government Engineering Department |
| Timetable | |
|---|---|
| Concept Clearance | 06 Jun 2000 |
| Fact Finding | 24 Jun 2002 to 12 Jul 2002 |
| MRM | 23 Aug 2002 |
| Approval | 02 Dec 2002 |
| Last Review Mission | - |
| PDS Creation Date | 05 Feb 2007 |
| Last PDS Update | 15 Apr 2010 |
Loan 1952-BAN
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 02 Dec 2002 | 03 Feb 2003 | 07 Sep 2003 | 30 Jun 2009 | - | 12 Aug 2009 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 60.00 | Cumulative Contract Awards | |||
| ADB | 60.00 | 17 Feb 2023 | 58.37 | 0.00 | 100% |
| Counterpart | 0.00 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Feb 2023 | 58.37 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Rural Infrastructure Improvement Project | Project/Program Completion Reports | Sep 2010 |
| Rural Infrastructure Improvement Project | Reports and Recommendations of the President | Nov 2002 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
| Title | Document Type | Document Date |
|---|---|---|
| Rural Infrastructure Improvement Project: Jhalokati Bus Stand (Krishnakathi)-Balokdia Road Subproject: Short Resettlement Plan | Resettlement Plans | Sep 2002 |
| Rural Infrastructure Improvement Project: Jhaudia-Halsha Road Subproject: Short Resettlement Plan | Resettlement Plans | Sep 2002 |
| Rural Infrastructure Improvement Project: Paikgacha-Mazidpur Road Subproject: Short Resettlement Plan | Resettlement Plans | Sep 2002 |
| Rural Infrastructure Improvement Project: Resettlement Framework | Resettlement Frameworks | Sep 2002 |
Evaluation Documents See also: Independent Evaluation
| Title | Document Type | Document Date |
|---|---|---|
| Bangladesh: Rural Infrastructure Improvement Project | Validations of Project Completion Reports | Dec 2012 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.