Bangladesh : Railway Sector Investment Program - Tranche 2

Sovereign Project | 32234-043

The projects proposed for financing under the requested PFR are:

1. Financing of the funding gap due to cost overrun in the Tongi-Bhairab Bazar Double Track subproject under the first tranche;

2. Rehabilitation of yards and extension of loops at different stations in the Darsana - Ishurdi - Sirajganj Bazar section; and

3. Upgrading of Signaling at 11 Stations between Ishurdi and Darsana.

4. Supervision Consultancy Services

Project Name Railway Sector Investment Program - Tranche 2
Project Number 32234-043
Country / Economy Bangladesh
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2845-BAN: Railway Sector Investment Program - Tranche 2
Ordinary capital resources US$ 150.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Sector / Subsector

Transport / Rail transport (non-urban)

Gender Some gender elements
Description

The projects proposed for financing under the requested PFR are:

1. Financing of the funding gap due to cost overrun in the Tongi-Bhairab Bazar Double Track subproject under the first tranche;

2. Rehabilitation of yards and extension of loops at different stations in the Darsana - Ishurdi - Sirajganj Bazar section; and

3. Upgrading of Signaling at 11 Stations between Ishurdi and Darsana.

4. Supervision Consultancy Services

Project Rationale and Linkage to Country/Regional Strategy

1. A framework financing agreement (FFA) for the Railway Sector Investment Program (RSIP) was signed on 7 September 2006 between the Government of Bangladesh and the Asian Development Bank (ADB). The RSIP was approved on 10 October 2006 by ADB's Board of Directors as a multitranche financing facility (MFF) for $430 million. The RSIP is based on the Government's Sector Roadmap and Investment Plan for 2007 2013 and will improve the performance of the railway sector by implementing (i) a reform project of sector policy, organizational, and capacity building reforms to make Bangladesh Railway (BR) more commercially focused, and improve governance and accountability; and (ii) an investment project of infrastructure and rolling stock capacity improvement investments to overcome capacity bottlenecks in sectors where such investments are both economically and financially viable, e.g., the Dhaka Chittagong and the Dhaka Darsana Khulna corridors.

2. The MFF is structured such that the reform project will provide continuous support to implement the agreed reform agenda, whilst the investment program will be supported by a series of four tranches. The reform and the investment projects are integrated as approval of subsequent tranches for investment subprojects is dependent on the implementation of specific reform actions agreed upon in the railway reform action plan in the FFA.

3. The first tranche under the MFF was approved on 13 February 2007 and comprises of two loans: (i) loan 2316 for $100 million from ADB's ordinary capital resources to finance investment projects; and (ii) loan 2317 for $30 million equivalent from ADB's special fund resources to finance the reform project.

4. The second tranche with a loan for $150 million was scheduled for approval in January 2008. It will finance (i) construction of other subprojects in the Dhaka Chittagong corridor and Dhaka Darsana Khulna corridor studied and prepared under the first loan and that satisfy the agreed subproject selection criteria in the FFA, and (ii) construction supervision consulting services for the approved subprojects.

Impact Efficient and safe railway transport in the Dhaka-Chittagong and Dhaka-Ishurdi-Darsana-Khulna/India corridor
Project Outcome
Description of Outcome Improved railway transport capacity in the Dhaka-Chittagong and Dhaka-Ishurdi-Darsana-Khulna/India corridors
Progress Toward Outcome

1. Tongi-Bhairab Bazar Double Line Track Construction is completed and under full operation.

2. Rehabilitation of yards and extension of loops at different stations in the Darsana-Ishurdi- Sirajganj Bazar section. Physical Progress is 100% by the end of August 2016.

3. Upgrading of Signaling at 11 Stations between Ishurdi and Darsana package: ongoing and physical progress is 48% till end of August 2016.

4. Supervision Consultancy Services: ongoing.

Implementation Progress
Description of Project Outputs

1. Tongi-Bhairab Bazar Double Track completed;

2. Signaling system Darsana-Ishurdi improved

3. Yards rehabilitated and loops extended in the Darsana-Ishurdi-Sirajganj Bazar section

Status of Implementation Progress (Outputs, Activities, and Issues)

1. Construction of Tongi-Bhairab Bazar Double Track Line is completed.

2. Rehabilitation of yards and extension of loops at different stations in the Darsana-Ishurdi- Sirajganj Bazar section. Progress is recorded as 100% in August 2016.

3. Upgrading of Signaling at 11 Stations between Ishurdi and Darsana package: ongoing and progress is recorded as 48% at the end of August 2016. Partial financing to this contract is transferred to Loan 2317.

4. Supervision Consultancy Services: ongoing.

Geographical Location Bhairab Bazar, Chuadanga District, Darsana, Gazipur District, Ishurdi, Kishorganj District, Kushtia, Kushtia District, Narsingdi District, Pabna District, Sirajganj, Sirajganj District, Tongi
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects

In accordance with ADB's Safeguard Policy Statement 2009, and the Environment Assessment and Review Framework for the MFF, tranche 2 is categorized as _B_ for environmental impacts. Given that no construction work has started yet in the Tongi Bhairab Bazar Double Track project, for which the Initial Environmental Examination (IEE) report was prepared during the processing of tranche 1, due diligence on environment safeguards mainly focused on fulfillment of planning and pre-construction requirements. The updated EMP including mitigation costs has been included in the bidding documents. Monitoring checklists for monitoring EMP implementation during construction has been prepared by the supervision consultant. A renewed environmental clearance valid until June 2012 has been obtained from the Department of Environment for the Tongi Bhairab Bazar Double Track project.

Activities under subproject 2 is limited to improving the signaling system with minimal physical construction, hence it is categorized as _C_ for environmental impact. Subproject 3 involves rehabilitation of yards and extension of loops requiring generation construction wastes hence it has been categorized as _B_. Accordingly an environmental review report for subproject 2 and an IEE for subproject 3 have been prepared.

Considering that the projects do not fall in any protected areas or other environmentally sensitive areas and there are minimal physical construction activities, there are no long term significant environmental impacts anticipated from the project.

Involuntary Resettlement

Tranche 2 is categorized as _A_ for resettlement impacts due to the resettlement impacts from the Tongi Bhairab Bazar Double Track project, which is partially funded under tranche 2. The RP for this project has been prepared and approved by ADB under tranche 1. The RP has been updated due to the land price escalation and further approved by ADB and uploaded to the ADB website, According to the census, 14,512 persons will be affected by the project, out of which 509 households will have impact on residential structures. 1,099 households will have impact on commercial structures. These are mainly squatters. 348 households would lose narrow strips of agricultural land. The total land acquisition and resettlement budget for the subproject is Tk1,545 million.

Details of compensation rates for the loss of land and structures, shifting assistance, income restoration assistance, and additional support provisions for the vulnerable groups are provided in the resettlement framework and also in the RP. Meaningful consultation and information disclosure during the preparation of RP with the project displaced persons including land acquisition and compensation process and to general public through the ADB website were undertaken. If during implementation any modification or additional land requirement or involuntary resettlement impacts are identified, a related RP will be prepared or modified in accordance with the applicable laws referred to in the RP, and prior approval of the ADB will be obtained before any further implementation of the relevant section of the subproject.

No land acquisition or resettlement is required for subprojects 2 and 3, therefore due diligence reports have been prepared and were submitted together with the PFR.

Indigenous Peoples The tranche is categorized as _C_ as there is no impact on indigenous people. An indigenous people planning framework was prepared to address any unanticipated impacts on indigenous peoples during the implementation of existing subprojects or any additional subprojects. In accordance with the framework, if any significant impacts on indigenous people are identified, an indigenous peoples plan will be prepared and submitted to ADB for approval.
Stakeholder Communication, Participation, and Consultation
During Project Design

In the course of social assessment of the project influence area, a series of participatory consultations were held with program stakeholders and beneficiaries in various socioeconomic groups. Focus group discussions were organized at various locations with randomly selected groups of men, women, and indigenous people residing in the project areas. Sessions exclusively for women were also held. Informants articulated the perceived benefits from the railway improvement program. They were positive about the need for the program especially for improved accessibility for the villagers as well as better amenities reaching the households in the project influence area.

Bangladesh Railway will organize further consultations with the project stakeholders and beneficiaries to apprise them of economic development in the program states. The perceptions and priorities of the people will be taken into consideration when finalizing the project design and preparing mitigation measures to address any risks.

During Project Implementation Consultation and participation will take place. No separate consultation and participation (C&P) plan is prepared however, approach for C&P is outlined in the resettlement framework and resettlement plan.
Business Opportunities
Consulting Services Recruitment of consultants will be carried out in accordance with ADB's Guidelines on the Use of Consultants (2010, as amended from time to time). ADB will select the consultants and the executing agency will negotiate and contract with the consultants thus selected. This recruitment process will help to ensure that consulting services are available in a timely manner. The COSO-staff outposted to the Bangladesh Resident Mission will support all procurement activities.
Procurement

Procurement will be carried out in accordance with ADB's Procurement Guidelines (2010, as amended from time to time). ADB will review documents and submission related to procurement at all major milestone prior to proceeding with the procurement process.

The procurement rules for selection of contractors required by international financial institutions such as the ADB are considered sufficiently robust to deter corruption at the bid selection stage. National procurement regulation has also improved through the Public Procurement Act, 2006, and through related Public Procurement Rules (2008) with subsequent amendments and the establishment of a Central Procurement Technical Unit under the Implementation Monitoring and Evaluation Division of the Ministry of Planning. During implementation of the tranche, reports will be submitted to executing agencies and ADB in line with submission milestones to ensure the quality and timeliness of contractors' work.

Responsible ADB Officer Mohammad Islam
Responsible ADB Department South Asia Department
Responsible ADB Division Bangladesh Resident Mission
Executing Agencies
Bangladesh Railway
Mr. A. H. M. Roushanuzzaman
16 Abdul Gani Road
Bangladesh Railway, Rail Bhaban,
Dhaka, Bangladesh
Timetable
Concept Clearance -
Fact Finding -
MRM 17 Nov 2011
Approval 22 Dec 2011
Last Review Mission -
Last PDS Update 27 Sep 2016

Loan 2845-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
22 Dec 2011 27 Aug 2012 05 Nov 2012 30 Jun 2016 - 28 Dec 2016
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 165.18 Cumulative Contract Awards
ADB 150.00 17 Jun 2022 149.93 0.00 100%
Counterpart 15.18 Cumulative Disbursements
Cofinancing 0.00 17 Jun 2022 149.93 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory - - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Railway Sector Investment Program - Tranches 1, 2, and 3: Environmental Due Diligence Report Safeguards Due Diligence Reports Feb 2016
Railway Sector Investment Program - Tranche 2: Tongi-Bhairab Bazar Double Line Project - Environmental and Social Monitoring Report (December 2015) Environmental and Social Monitoring Reports Dec 2015
Bangladesh Railway Sector Improvement Project - Tongi-Bhairab Bazar Double Line Project: Sixth Semiannual Social Monitoring Report (January-June 2015) Social Monitoring Reports Aug 2015
Bangladesh Railway Sector Improvement Project - Tongi-Bhairab Bazar Double Line Project: Environmental Monitoring Report (January-June 2015) Environmental Monitoring Reports Jun 2015
RSIPR - Tongi-Bhairab Bazar Double Line Project: Final Interim Report on Updated Full Resettlement Plan Implementation (January-June 2014) Social Monitoring Reports Mar 2015
Railway Sector Investment Program - Tranche 2: Safeguard Due Diligence Report Safeguards Due Diligence Reports Jan 2015
Bangladesh Railway Sector Improvement Project - Tongi-Bhairab Bazar Double Line: Fourth Semiannual Social Monitoring Report (January - June 2014) Social Monitoring Reports Jun 2014
Railway Sector Investment Program: Tongi-Bhairab Bazar Double Line Project: Environmental Monitoring Report (September 2013-June 2014) Environmental Monitoring Reports Jun 2014
Railway Sector Investment Program: Tongi-Bhairab Bazar Double Line Project: Annual Environmental Monitoring Report (August 2013) Environmental Monitoring Reports Aug 2013
Railway Sector Investment Program: Tongi-Bhairab Bazar Double Line Project: Social Monitoring Report (January-June 2013) Social Monitoring Reports Jun 2013
Railway Sector Investment Program: Tongi-Bhairab Bazar Double Line Project: Annual Environmental Monitoring Report (October 2012) Environmental Monitoring Reports Oct 2012
Railway Sector Investment Program - PFR2: Initial Environmental Examination Initial Environmental Examination Oct 2011

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Bangladesh: Railway Sector Investment Program (Tranches 1, 2, and 4) Validations of Project Completion Reports Aug 2020

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

Title Document Type Document Date
Railway Sector Investment Program - Tranche 2 Procurement Plans Mar 2014