The Asian Development Bank is working with Fiji to strengthen agriculture in partnership with private companies. The project is helping private sector-led industry organizations prepare strategic business plans and obtain financial support for research and development, as well as marketing activities.
Project Name | Alternative Livelihoods Development Project | ||||||||||||
Project Number | 32541-013 | ||||||||||||
Country | Fiji |
||||||||||||
Project Status | Closed | ||||||||||||
Project Type / Modality of Assistance | Loan Technical Assistance |
||||||||||||
Source of Funding / Amount |
|
||||||||||||
Strategic Agendas | Inclusive economic growth |
||||||||||||
Drivers of Change | Private sector development |
||||||||||||
Sector / Subsector |
Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Agricultural production - Agro-industry, marketing, and trade Education / Technical and vocational education and training Finance / Inclusive finance - Small and medium enterprise finance and leasing Transport / Road transport (non-urban) |
||||||||||||
Gender Equity and Mainstreaming | |||||||||||||
Description | |||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | |
Indigenous Peoples |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Gloerfelt-Tarp, Thomas |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | Pacific Operations Division |
Executing Agencies |
Ministry of Agriculture Dr. Richard Beyer Robinson Complex, Grantham Road Raiwaqa, Suva, Fiji Private Mail Bag, Suva, Fiji |
Timetable | |
---|---|
Concept Clearance | 11 May 1999 |
Fact Finding | 15 Jul 2003 to 01 Aug 2003 |
MRM | 04 Sep 2003 |
Approval | 28 Mar 2005 |
Last Review Mission | - |
PDS Creation Date | 17 Nov 2006 |
Last PDS Update | 23 Oct 2008 |
Loan 2158-FIJ
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
28 Mar 2005 | 29 Jun 2005 | 06 Sep 2005 | 30 Jun 2011 | - | 01 Dec 2008 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 49.78 | Cumulative Contract Awards | |||
ADB | 25.00 | 28 Mar 2005 | 0.35 | 0.00 | 70% |
Counterpart | 15.95 | Cumulative Disbursements | |||
Cofinancing | 8.82 | 28 Mar 2005 | 0.50 | 0.00 | 100% |
TA 4572-FIJ
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
28 Mar 2005 | 13 Apr 2005 | 13 Apr 2005 | 31 Mar 2007 | 31 Dec 2007 | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
600,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 600,000.00 | 28 Mar 2005 | 161,176.74 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Alternative Livelihoods Development Project | Project/Program Completion Reports | Jun 2009 |
Alternative Livelihoods Development Project | Reports and Recommendations of the President | Mar 2005 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Alternative Livelihoods Development Project | Environmental Assessment and Measures | Mar 2005 |
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Fiji: Alternative Livelihoods Development Project | Validations of Project Completion Reports | Dec 2012 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.