Sri Lanka : North East Province Coastal Community Development
The goal of the Project is to reduce proverty in vulnerable coastal communities in the three districts (Trincomalee, Batticoloa, and Ampara) of eastern Sri Lanka. The Project purpose is sustainable livelihood development and sound management of natural resources. The Project is organized into five components: (i) Coastal Resource Planning; (ii) Natural Resource Management and Development; (iii) Livelihood Improvement in Vulnerable Communities Outside the Special Management Areas; (iv) Provision of Fisheries Infrastructure; and (v) Project Implementation Support.
Project Results
-
7,583
microfinance loan accounts opened / end borrowers reached
The results data reported above are limited to ADB's core sectors, as defined under Strategy 2020 and tracked through indicators in the ADB Results Framework. For definitions of results indicators, please see the ADB Results Framework Indicators Definition.
Project Details
-
Project Officer
Salgado, Nissanka Amila Buddika
South Asia Department
Request for information -
Country/Economy
Sri Lanka -
Modality
-
Sector
- Agriculture, natural resources and rural development
Related Projects
| Project Name | North East Province Coastal Community Development | ||||||||
| Project Number | 33249-013 | ||||||||
| Country / Economy | Sri Lanka |
||||||||
| Project Status | Closed | ||||||||
| Project Type / Modality of Assistance | Loan |
||||||||
| Source of Funding / Amount |
|
||||||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development |
||||||||
| Sector / Subsector | Agriculture, natural resources and rural development / Water-based natural resources management |
||||||||
| Gender | Gender equity | ||||||||
| Description | The goal of the Project is to reduce proverty in vulnerable coastal communities in the three districts (Trincomalee, Batticoloa, and Ampara) of eastern Sri Lanka. The Project purpose is sustainable livelihood development and sound management of natural resources. The Project is organized into five components: (i) Coastal Resource Planning; (ii) Natural Resource Management and Development; (iii) Livelihood Improvement in Vulnerable Communities Outside the Special Management Areas; (iv) Provision of Fisheries Infrastructure; and (v) Project Implementation Support. | ||||||||
| Project Rationale and Linkage to Country/Regional Strategy | Coastal communities in the East are characterized by high levels of poverty, weak and fragmented social institutions, inadequate and damaged physical infrastructure, and reduced access to services and markets. The long period of conflict has disrupted livelihoods, resulted in a loss of productive assets (fishing boats and gear) and household possessions, limited access to the natural resource base, and encouraged nonsustainable resource use practices. Communities lack social cohesiveness, and displacement and loss of family members and property have traumatized people, thus diminishing self-reliance and motivation. Women have been particularly affected and have experienced conflict differently from men. The conflict has resulted in a large proportion of households with female heads (FHHs) without social acceptance and the means to earn a livelihood. Institutional capacity at the provincial and district levels for natural resource management and planning is also extremely limited. In addition, nonenforcement of environmental rules and regulations is resulting in increasingly adverse impacts on coastal communities and the natural resource base upon which residents depend for their livelihood. The scale of the economic damage and social dislocation due to the conflict has severely strained the Government's ability to provide development assistance. It has therefore turned to the international community, particularly the Asian Development Bank (ADB), for support. The Project was designed in line with the Governments poverty reduction strategy. Also, ADB's Country Strategy and Program endorsed the Government's priority to reduce poverty and faciliate development of sustainable natural resource management system with the aim of improving livelihoods and supporting sustainable long-term economic growth. |
||||||||
| Impact | Reduce poverty and meet basic needs in coastal communities of the Eastern Province | ||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | Sustainable livelihood improvement and sound management of natural resources in the Eastern Province [Taken from the Project Framework] |
| Progress Toward Outcome | -- |
| Implementation Progress | |
| Description of Project Outputs | Component 1: Sustainable Livelihood Improvement Output 1: Livelihoods improved in a sustainable manner Output 2: Livelihoods of coastal Vedda communities improved in a sustainable Manner Component 2: Resource Management in 3 SMAs Output 1: Community-level resource management improved Output 2: SMA plans prepared and operationalized Output 3: Study of coastal resource management issues in Northern Province Component 3: Coastal Resource Planning Output 1: Coastal resource management capacity strengthened and improved Output 2: Environmental enforcement strengthened and improved 4. FISHERIES DEVELOPMENT Output 1: Harbor facilities at Valaichchenai and Cod Bay rehabilitated Output 2: Harbor management and operational efficiency improved Output 3: Productivity of east coast fishing industry improved Component 5: Project Implementation Support Project management and monitoring services established |
| Status of Implementation Progress (Outputs, Activities, and Issues) | 8,460 beneficiaries (50% to women) received micro credit to the amount of Rs. 256 Mn for various types of livelihood activities. 20 Micro-credit NGOs are enaged with NDTF and disbursed funds worth of Rs. 256 million. Trincomalee 04 Batticaloa 06 Ampara - 08 Agreement signed between respective GAs and LEDS providers (Agromart, Practical Action & SEEDS). Training programs for over13,764 benficiaries have been held. There are no Veddah communities at present in the project area. However 4 villages identified. The so called Veddah communities totally refused any special treatment which they considered as derogatory remarks on them. PNA of Vedda communities completed in 4 GN Divisions of Trincomallee districts so far User groups are being established Completed Target is not realistic. smaller scale and larger scale interventions were finalized and 58 completed 3 SMA committees established and committee meetings held regularly. SMA plans approved by ABD and CEA has prepared environmental profiles for 3 SMAs Smaller scale and larger scale interventions were finalized and 58 completed. 3 Natural Resource Planners were recruited and fieled. The Natural Resources Planner from Trincomalee was fielded on 15 April 2005 while the Natural Resource Planner from Batticaloa and Ampara were fielded on 2 May 2005. Consultants in package II has been recruited bu t were only mobilized in November 2007, due to the volatile security situation. On GOSL's request, Northern Study will not be underatken through the project funds. The PPS has been unable to provide key staff to be deployed full time, due to lack of staff. Consultancy team is stationed in the PPS Provincial inter agency planning group established and meetings are held regularly. Preparation of coastal resource management plan completed. Prepration of Coastal Resourse Plans are completed. Inter Agency Planning group meeting held regularly with CCD, CEA, NARA, UDA and other relevant provincial agencies. Valuable materials for preparation of coastal resource plan have been collected from CCD, CEA, NARA and Department of Physical Planning. Construction work at Valachchenai and Cod Bay is completed. Completed Completed The PMO and DPOs are fully staffed and have sufficient equipment. The PO was established on 1 December 2003 and district project offices (DPOs) were established on 1 January 2004. The PO and DPOs are fully staffed according to the revised staffing schedule, which was approved by the Department of Management Services and subsequently by ADB. Adding the DPD to the PO staff could ease the responsibilities currently shouldered by the PD. IEC Audio & Video Equipments procured and distributed to 3 districts. Staff trained on that field. Reporting systems Monitoring formats in use. Web-site developed on the project is being regularly updated MIS developed . |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | The Project will require consultants for (i) project management and implementation; (ii) provision of core technical advisory services; (iii) strategic and technical feasibility studies in coastal resource planning; (iv) community level interventions in small-scale social infrastructure, livelihood improvement, and environmental restoration/management; (v) establishment of a livelihood and enterprise development unit; (vi) delivery of micro-credit; (vii) designs and feasibility studies for fisheries harbor rehabilitation; (viii) preparation of a resettlement plan for the rehabilitation of Valaichchenai harbor; and (ix) baseline surveys for evaluating Project impacts. Generally, the consultants will be recruited domestically, but there will be a requirement for some international inputs in specialized areas. The consultants will be engaged in accordance with ADB's Guidelines on the Use of Consultants and other arrangements satisfactory to ADB for the recruitment of domestic consultants. |
| Procurement | Goods and services financed from the proceeds of the ADB loan will be procured in accordance with ADB's Guidelines for Procurement. All goods to be purchased through local competitive bidding (LCB) will be procured in accordance with the Government procedures acceptable to ADB. ADB-financed civil works contracts estimated to cost the equivalent of $1.0 million and above will be awarded on the basis of international competitive bidding (ICB), while other ADB-financed civil works contracts of less than $1.0 million will be carried out by prequalified contractors selected under the Government's LCB procedures satisfactory to ADB. The award of contracts with a value equivalent to $500,000 and above will need prior ADB approval. Supply contracts estimated to cost the equivalent of more than $500,000 will be awarded on the basis of ICB and $500,000 or less will be awarded on the basis of international shopping. Minor items costing less than $100,000 equivalent may be procured through direct purchase. |
| Responsible ADB Officer | Salgado, Nissanka Amila Buddika |
| Responsible ADB Department | South Asia Department |
| Responsible ADB Division | Sri Lanka Resident Mission |
| Executing Agencies |
Ministry of NationBuilding & Estate Infrastructure S.M. Croos, Project Director [email protected] 56, Central Road, Orr's Hill, Trincomalee |
| Timetable | |
|---|---|
| Concept Clearance | 23 Jul 2002 |
| Fact Finding | 19 May 2003 to 06 Jun 2003 |
| MRM | 15 Aug 2003 |
| Approval | 16 Jun 2004 |
| Last Review Mission | - |
| PDS Creation Date | 05 Feb 2007 |
| Last PDS Update | 25 Apr 2011 |
Loan 2027-SRI
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 28 Nov 2003 | 16 Jun 2004 | 16 Nov 2004 | 30 Jun 2010 | 30 Jun 2011 | 24 Jan 2012 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 21.50 | Cumulative Contract Awards | |||
| ADB | 20.00 | 17 Jun 2022 | 19.76 | 0.00 | 100% |
| Counterpart | 0.00 | Cumulative Disbursements | |||
| Cofinancing | 1.50 | 17 Jun 2022 | 19.76 | 0.00 | 100% |
| Status of Covenants | ||||||
|---|---|---|---|---|---|---|
| Category | Sector | Safeguards | Social | Financial | Economic | Others |
| Rating | Satisfactory | Satisfactory | Satisfactory | Satisfactory | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| North East Province Coastal Community Development Project | Summary Poverty Reduction and Social Strategies | Nov 2003 |
| North East Coastal Community Development Project | Project/Program Completion Reports | Aug 2012 |
| North East Coastal Community Development Project | Reports and Recommendations of the President | Nov 2003 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
| Title | Document Type | Document Date |
|---|---|---|
| North East Coastal Community Development Project: Resettlement Framework | Resettlement Frameworks | Nov 2003 |
Evaluation Documents See also: Independent Evaluation
| Title | Document Type | Document Date |
|---|---|---|
| Sri Lanka: North East Coastal Community Development Project | Validations of Project Completion Reports | Sep 2014 |
Related Publications
| Title | Document Type | Document Date |
|---|---|---|
| Gender Mainstreaming Case Study: Sri Lanka - North East Coastal Community Development Project and Tsunami-Affected Areas Rebuilding Project | Reports | Oct 2015 |
| Gender Equality Results Case Studies: Sri Lanka | Reports | Dec 2010 |
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Improving Livelihoods of Coastal Communities in Sri Lanka
Following 20 years of civil conflict, up to 50% of the 110,000 households in the coastal area of the country’s east were estimated to be poor. The conflict destroyed livelihood assets, displaced people, and eroded government institutional capacity. Females headed many fractured households due to losses of male family members.Sri Lanka: North East Coastal Community Development Project - 2010
This case study is on the Sri Lanka North East Coastal Community Development Project (NECCDEP) that focus on reducing poverty and meeting basic needs in three conflict-affected provinces, by improving sustainable livelihoods and the management of natural resources.Sri Lanka: Microcredit and Training Improve Women's Income
An ADB-supported project provides villagers in Sri Lanka's eastern coastal communities with opportunities to move beyond a past ravaged by conflict and natural calamity, and has shown that poverty reduction can be achieved even in situations of conflict and disaster.
Tenders
Contracts Awarded
Procurement Plan
None currently available.