Lao People's Democratic Republic : Greater Mekong Subregion: Northern Economic Corridor Project
Project Details
-
Project Officer
Nangia, Rita
Southeast Asia Department
Request for information -
Country/Economy
Lao People's Democratic Republic -
Modality
-
Sector
- Transport
Related Projects
Project Name | Greater Mekong Subregion: Northern Economic Corridor Project | ||||||||||
Project Number | 34231-013 | ||||||||||
Country / Economy | Lao People's Democratic Republic |
||||||||||
Project Status | Closed | ||||||||||
Project Type / Modality of Assistance | Loan |
||||||||||
Source of Funding / Amount |
|
||||||||||
Strategic Agendas | Inclusive economic growth Regional integration |
||||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions |
||||||||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||||||||
Gender | Effective gender mainstreaming | ||||||||||
Description | |||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Safeguard Categories | |
---|---|
Environment | A |
Involuntary Resettlement | |
Indigenous Peoples |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Nangia, Rita |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Transport and Communications Division, SERD |
Executing Agencies |
Ministry of Comm, Trans., Post & Construction |
Timetable | |
---|---|
Concept Clearance | 29 Aug 2000 |
Fact Finding | 25 Apr 2002 to 10 May 2002 |
MRM | 11 Jun 2002 |
Approval | 20 Dec 2002 |
Last Review Mission | - |
PDS Creation Date | 08 Aug 2007 |
Last PDS Update | 14 Jul 2009 |
Loan 1989-LAO
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
20 Dec 2002 | 07 Feb 2003 | 09 Feb 2004 | 30 Jun 2007 | 30 Jun 2009 | 30 Jun 2009 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 30.00 | Cumulative Contract Awards | |||
ADB | 30.00 | 17 Feb 2023 | 34.10 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Feb 2023 | 34.10 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Greater Mekong Subregion Northern Economic Corridor Project | Summary Poverty Reduction and Social Strategies | Nov 2003 |
Greater Mekong Subregion Northern Economic Corridor Project (Lao People's Democratic Republic) | Reports and Recommendations of the President | Nov 2002 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Greater Mekong Subregion: Northern Economic Corridor Project in the Lao People’s Democratic Republic | Project Performance Evaluation Reports | Dec 2014 |
Lao People’s Democratic Republic: Greater Mekong Subregion: Northern Economic Corridor Project | Validations of Project Completion Reports | Dec 2012 |
Related Publications
Title | Document Type | Document Date |
---|---|---|
Assessing Impact in the Greater Mekong Subregion: An Analysis of Regional Cooperation Projects | Reports | Apr 2014 |
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Increasing Cross-Border Trade Opens Opportunities for Thailand Province
Chiang Rai province in northern Thailand is an emerging economic hub in the Greater Mekong Subregion, benefiting from the resurgence of activity on the ancient Southern Silk Road.Ancient Trade Route Delivers New Opportunities to Greater Mekong Subregion
A modern highway and bridge connecting three countries in the Greater Mekong Subregion are reviving an ancient trade route and bringing new life to local communities.Paving the Way for Tourism in Lao PDR
The improvement of Route 3 highway and trade links have led to a boom in tourism and related economic activities in landlocked Lao People’s Democratic Republic.Driving Development Along an Ancient Mekong Trade Route
A highway mirroring a strand of the ancient Tea Horse Trail is expanding tourism, trade, and families' standard of living in rural People's Republic of China, the Lao PDR, and Thailand.Tea and Prosperity Along Ancient Trade Route
A new ADB-supported road stretching from the People's Republic of China through Lao PDR following the Tea Horse pathway is enhancing the region's potential for economic growth.New Highway Revives Old Tea Horse Road
A new ADB-supported highway in Lao PDR is revitalizing ancient trade routes and bringing new life to communities that dot the landscape along their paths.
Tenders
Contracts Awarded
Procurement Plan
None currently available.