China, People's Republic of : Henan Wastewater Management Project
The objectives of the Project are to improve the urban environment and public health through improved wastewater management, and to improve the quality of surface water and groundwater in and downstream of the project countries. Related objectives include: (i) creating municipal wastewater companies and making them efficient and commercially managed (ii) supporting comprehensive approaches to river basin wide pollution prevention and control and (iii) improving cost recovery from users through improved tariffs with gradual increases to full cost recovery.
Project Details
-
Project Officer
Fei, Yue
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Modality
-
Sector
- Water and other urban infrastructure and services
Related Projects
| Project Name | Henan Wastewater Management Project | ||||
| Project Number | 34473-012 | ||||
| Country / Economy | China, People's Republic of |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions |
||||
| Sector / Subsector | Water and other urban infrastructure and services / Urban sewerage |
||||
| Gender | Some gender elements | ||||
| Description | The objectives of the Project are to improve the urban environment and public health through improved wastewater management, and to improve the quality of surface water and groundwater in and downstream of the project countries. Related objectives include: (i) creating municipal wastewater companies and making them efficient and commercially managed (ii) supporting comprehensive approaches to river basin wide pollution prevention and control and (iii) improving cost recovery from users through improved tariffs with gradual increases to full cost recovery. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | A |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | A firm of international consultants, in association with domestic consultants, will be engaged by ADB in accordance with its Guidelines on the Use of Consultants based on the quality and cost based selection method and other arrangements satisfactory to ADB for the engagement of domestic consultants. The TA will require 43 person months of consulting services consisting of 16 person months of international consultants and 27 person months of domesctic consultants. The international consultants will have expertise in wastewater management, environment, social analysis, financial analysis, and economic analysis. The domestic consultants will have expertise in engineering services (wastewater management, sewer network, costing, mechanical, electrical, and instrumentation), environment, sociology, financial analysis, and economic analysis. |
| Procurement | To be determined. |
| Responsible ADB Officer | Fei, Yue |
| Responsible ADB Department | East Asia Department |
| Responsible ADB Division | Urban and Social Sectors Division, EARD |
| Executing Agencies |
Henan Provincial Government (HPG) Mr. Zhao Qingye, Director Planning & Econ. Commission of HenanProv 23, Weier Road, Zhengzhou People's Republic of China |
| Timetable | |
|---|---|
| Concept Clearance | 09 Mar 2000 |
| Fact Finding | 09 Sep 2003 to 25 Sep 2003 |
| MRM | - |
| Approval | 03 Dec 2003 |
| Last Review Mission | - |
| Last PDS Update | 15 Dec 2006 |
TA 4233-PRC
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 03 Dec 2003 | 25 Feb 2004 | 25 Feb 2004 | 31 Aug 2004 | 31 Dec 2006 | 11 Jan 2007 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 800,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 800,000.00 | 17 Jun 2022 | 794,873.30 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Henan Wastewater Management Project | Technical Assistance Reports | Dec 2003 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.