The TA will identify and prepare a project for upstream natural gas development. The ensuing project is expected to include rehabilitation of existing gas wells and pipeline network.
Project Name | Natural Gas Development Project | ||||
Project Number | 37085-012 | ||||
Country | Afghanistan |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
Drivers of Change | Private sector development |
||||
Sector / Subsector | Energy / Oil and gas transmission and distribution |
||||
Gender Equity and Mainstreaming | No gender elements | ||||
Description | The TA will identify and prepare a project for upstream natural gas development. The ensuing project is expected to include rehabilitation of existing gas wells and pipeline network. | ||||
Project Rationale and Linkage to Country/Regional Strategy | To achieve economic progress through infrastructure development, support to the energy sector is a major intervention. A 5-10 year development program will be defined to support government investment and private sector participation. | ||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | International consultants will be engaged for a total of 16 person-months and domestic consultants for 42 person-months. The consulting team will be selected and engaged through a firm in accordance with ADB's Guidelines on the Use of Consultants, and other procedures acceptable to ADB for the selection and engagement of domestic consultants. The simplied technical proposal format and quality and cost-based selection will be used. |
Procurement | TBD |
Responsible ADB Officer | Mannapbekov, Nariman |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Transport and Communications Division, CWRD |
Executing Agencies |
Ministry of Mines and Petroleum H.E. Dip Eng. Mohammad Ibrahim Adel Kabul, Afghanistan |
Timetable | |
---|---|
Concept Clearance | 10 Mar 2005 |
Fact Finding | 05 Jul 2005 to 09 Jul 2005 |
MRM | - |
Approval | 06 Oct 2005 |
Last Review Mission | - |
PDS Creation Date | 14 Jun 2006 |
Last PDS Update | 29 Aug 2007 |
TA 4666-AFG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
06 Oct 2005 | 10 Nov 2005 | 10 Nov 2005 | 31 Mar 2007 | 31 Dec 2007 | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
995,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 995,000.00 | 06 Oct 2005 | 658,433.10 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Preparing the Natural Gas Development Project | Consultants' Reports | Dec 2007 |
Preparing the Natural Gas Development Project | Technical Assistance Reports | Oct 2005 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.