37192-044: Power Transmission Enhancement Investment Program Tranche 4 | Asian Development Bank

Pakistan: Power Transmission Enhancement Investment Program Tranche 4

Sovereign (Public) Project | 37192-044 Status: Active

The Asian Development Bank is helping Pakistan upgrade its power transmission network to improve safety and accommodate additional electricity from generating plants that will come on stream in future. Tranche 4 of the program will fund a more than 280 km-long transmission line to transfer electricity from the Guddu power plant, and build and upgrade grid stations for more reliable power delivery.

 
Project Name Power Transmission Enhancement Investment Program Tranche 4
Project Number 37192-044
Country Pakistan
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3203-PAK: Power Transmission Enhancement Investment Program - Tranche 4
Ordinary capital resources US$ 248.00 million
Loan 8311-PAK: Power Transmission Enhancement Investment Program Tranche 4
Agence Francaise de Developpement US$ 82.50 million
Strategic Agendas Inclusive economic growth
Drivers of Change Knowledge solutions
Partnerships
Sector / Subsector

Energy / Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description ADB approved a multitranche financing facility (MFF) for the Power Transmission Enhancement Investment Program on 13 December 2016 for an amount not exceeding $800 million. Under tranche 4 the government seeks ADB financing for 10 subprojects covering (i) line bay extension and 281 kilometers (km) of 500-kilovolt (kV) transmission line from the 500-kV Muzaffargarh grid station for electricity evacuation from the 747-MW Guddu power plant; (ii) four new 220-kV grid stations and in/out transmission lines at Chakdara, D.I. Khan, Lalian, and Nowshehra; (iii) installation of a static var system (SVS) at 220-/132-kV Quetta industrial grid station; (iv) extension of 500-kV grid stations at Jamshoro and Gujranwala, and augmentation of 500-kV grid station at Rewat; and (v) the procurement of construction and operational equipment.
Project Rationale and Linkage to Country/Regional Strategy The power system needs the new subprojects to meet network demand, safety and security requirements, and to cater for additional generation capacity which is under construction and planned for the future economic growth of Pakistan. Expanding and upgrading the transmission backbone will provide reliable and high-quality supply to meet increasing demand from industrial, commercial, agricultural, and domestic customers.
Impact Enhanced power transmission operations and management.
Project Outcome
Description of Outcome An expanded and reliable 500-kV and 220-kV transmission system.
Progress Toward Outcome By Q3 2018, all remaining contracts were awarded. Project will be completed within closing period of L8311 ending Dec 2019.
Implementation Progress
Description of Project Outputs Transmission lines and substations commissioned.
Status of Implementation Progress (Outputs, Activities, and Issues) Target achievable. All contracts were awarded in Q3 2018
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The tranche's safeguards classifications and requirements are B for environment.
Involuntary Resettlement

Nowshehra LAPRP has been approved by ADB and is currently under implementation.

Lalian Grid Station involves litigation requiring complete updating of LARP which is under preparation after finalization of new alternate site identified by NTDC. Construction suspended till further notice and finalization of site.

Indigenous Peoples The tranche's safeguards classifications and requirements are C for indigenous peoples. No subproject under tranche 4 will affect people classified as Indigenous Peoples, as defined by ADB's SPS and by the Indigenous People Development Framework prepared for the project.
Stakeholder Communication, Participation, and Consultation
During Project Design All consumers (urban, rural, industrial, agricultural, commercial and domestic) connected to the grid are potential beneficiaries; however, their direct participation cannot contribute to the project design.
During Project Implementation Those affected directly by land acquisition and resettlement were closely consulted in preparation of the land acquisition and resettlement plan (LARP) or due diligence reports (DDR) for each subproject as applicable, and will participate in its implementation.
Business Opportunities
Consulting Services NTDC engaged two international and one national procurement experts, through the project preparation consulting firm, to assist with bid preparation and evaluation. NTDC will engage additional individual consultants to help the PMU with procurement, project supervision, and safeguards monitoring, using the project support component.
Procurement

NTDC will continue as the executing and implementing agency for tranche 4. The established PMU, which managed the previous three tranches, will be expanded to include all functions required for implementation, including procurement, contract execution and management, and safeguards implementation and monitoring. The PMU is headed by the General Manager (Projects), and includes an ESIC. The new PMU structure will include a Chief Engineer (Material Procurement and Management) responsible for all procurement and financial matters related to contract management.

The invitation for bids for the subprojects are all expected to be released within the first half of 2015.

Responsible ADB Officer Khattak, Ehtesham Zafar
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Pakistan Resident Mission
Executing Agencies
National Transmission & Despatch Company Limited
WAPDA House
Shahrah-e-Quaid-e-Azam
Lahore, Pakistan
Timetable
Concept Clearance -
Fact Finding 08 Sep 2014 to 19 Sep 2014
MRM 09 Oct 2014
Approval 03 Dec 2014
Last Review Mission -
Last PDS Update 22 Sep 2018

Loan 3203-PAK

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
03 Dec 2014 12 Dec 2014 06 Mar 2015 31 Dec 2016 - 30 Oct 2017
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 335.30 Cumulative Contract Awards
ADB 248.00 03 Dec 2014 51.89 0.00 99%
Counterpart 87.30 Cumulative Disbursements
Cofinancing 0.00 03 Dec 2014 52.56 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory - - Unsatisfactory - Satisfactory

Loan 8311-PAK

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
29 Sep 2016 20 Jul 2017 20 Jul 2017 01 Aug 2020 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 82.50 Cumulative Contract Awards
ADB 0.00 29 Sep 2016 0.00 82.95 96%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 82.50 29 Sep 2016 0.00 58.45 67%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory - - Unsatisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Power Transmission Enhancement Investment Program – Tranche 4: Environmental Monitoring Report (July-December 2018) Environmental Monitoring Reports Jan 2019
Power Transmission Enhancement Investment Program - Tranche 3: Social Monitoring Report (October-December 2018) Social Monitoring Reports Jan 2019
Power Transmission Enhancement Investment Program - Tranche 4: Social Monitoring Report (April-June 2018) Social Monitoring Reports Oct 2018
Power Transmission Enhancement Investment Program - Tranche 4: Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
Power Transmission Enhancement Investment Program - Tranche 4: Environmental Monitoring Report (January-June 2017) Environmental and Social Monitoring Reports Jul 2017
Power Transmission Enhancement Investment Program - Tranche 4: Lalian 220 kV Grid Station and Associated Transmission Line Resettlement Plan Resettlement Plans Nov 2016
Power Transmission Enhancement Investment Program - Tranche 4: Nowshera 220 kV Grid Station Resettlement Plan Resettlement Plans Oct 2016
Power Transmission Enhancement Investment Program - Tranche 4: Social Monitoring Report Social Monitoring Reports Aug 2016
PTEIPT (Tranche 4) - Dispersal of Power from 747 MW Power Plant at Guddu to Muzaffargarh: Initial Environmental Examination Initial Environmental Examination Jun 2016
PTEIPT (Tranche 4) - 220 kV Dera Ismail Khan Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Jun 2016
PTEIPT (Tranche 4) - 220 kV Lalian Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Jun 2016
PTEIPT (Tranche 4) - 220 kV Nowshera Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Jun 2016
PTEIPT (Tranche 4) - 220 kV Chakdarra Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Jun 2016
Power Transmission Enhancement Investment Program - Tranches 3 and 4: Social Monitoring Report (October-December 2015) Social Monitoring Reports Jan 2016
Power Transmission Enhancement Investment Program - Tranche 4: Chakdara 220 kV Grid Station and Transmission Line Draft Land Acquisition and Resettlement Plan Resettlement Plans Jan 2016
Pakistan Power Transmission Enhancement Investment Program - Tranche 4: Environmental Assessment and Review Framework Environmental Assessment and Review Framework Dec 2014
PTEIPT (Tranche 4) - 220 kV Dera Ismail Khan Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Dec 2014
PTEIPT (Tranche 4) - Dispersal of Power from 747 MW Power Plant at Guddu to Muzaffargarh: Initial Environmental Examination Initial Environmental Examination Dec 2014
PTEIPT (Tranche 4) - 220 kV Chakdarra Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Dec 2014
PTEIPT (Tranche 4) - 220 kV Nowshera Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Dec 2014
PTEIPT (Tranche 4) - Augmentation in Gujranwala, Rawat, Jamshoro, and Quetta Grid Stations: Initial Environmental Examination Initial Environmental Examination Dec 2014
PTEIPT (Tranche 4) - 220 kV Lalian Grid Station and Allied Transmission Line: Initial Environmental Examination Initial Environmental Examination Dec 2014
Power Transmission Enhancement Investment Program - Tranche 4: Nowshera 220 kV Grid Station Draft Land Acquisition and Resettlement Plan Resettlement Plans Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: 220 kV Chakdarra Grid Station and Allied Transmission Line Initial Environmental Examination Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: Augmentation/Extension Works Initial Environmental Examination Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: 220 kV Lalian Grid Station and Allied Transmission Line Initial Environmental Examination Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: 220 kV Dera Ismail Khan Grid Station and Allied Transmission Line Initial Environmental Examination Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: The Construction of New 220 kV Nowshera Grid Station and Allied 2 km Transmission Line Initial Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: Dispersal of Power from 747 MW Power Plant at Guddu to Muzaffargarh Initial Environmental Initial Environmental Examination Sep 2014
Power Transmission Enhancement Investment Program - Tranche 4: Chakdara 220 kV Grid Station and Transmission Line Draft Land Acquisition and Resettlement Plan Resettlement Plans Aug 2014
Power Transmission Enhancement Investment Program - Tranche 4: Resettlement Framework Resettlement Frameworks Aug 2014
Power Transmission Enhancement Investment Program - Tranche 4: 500 kV Muzaffargarh Extension and Transmission Line Draft Land Acquisition and Resettlement Plan Resettlement Plans Aug 2014
Power Transmission Enhancement Investment Program - Tranche 4: D.I. Khan District 220 kV Grid Station and Transmission Line Land Acquisition and Resettlement Plan Resettlement Plans Aug 2014
Power Transmission Enhancement Investment Program - Tranche 4: Lalian 220 kV Grid Station and Transmission Line Land Acquisition and Resettlement Plan Resettlement Plans Aug 2014

Evaluation Documents See also: Independent Evaluation

None currently available.


The Access to Information Policy establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Loan No. 8311-PAK(AFD): Power Transmission Enhancement Investment Program – Tranche 4 [ADB-71-RB-2-2017] Invitation for Bids Closed 21 Sep 2017 02 Nov 2017
External Monitoring Consultant (Social Safeguards) Individual - Consulting Closed 19 Sep 2017 25 Sep 2017
Loan No. 8311-PAK: Power Transmission Enhancement Investment Program Tranche 4 [ADB-70R2-2017] Invitation for Bids Closed 04 Jul 2017 15 Aug 2017
Loan No. 8311-PAK: Power Transmission Enhancement Investment Program - Tranche 4 [ADB-77R-2017] REBIDDING Invitation for Bids Closed 27 Mar 2017 08 May 2017

Contracts Awarded

No contracts awarded for this project were found