Nepal: Regional Development Strategy
Project Details
-
Project Officer
Yokoyama, Kenichi
South Asia Department
Request for information -
Country/Economy
Nepal -
Modality
- Technical Assistance
Project Name | Regional Development Strategy | ||||
Project Number | 37404-012 | ||||
Country / Economy | Nepal |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Inclusive economic growth |
||||
Drivers of Change | Governance and capacity development |
||||
Sector / Subsector | Public sector management / Economic affairs management |
||||
Gender Equity and Mainstreaming | |||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Yokoyama, Kenichi |
Responsible ADB Department | South Asia Department |
Responsible ADB Division | Nepal Resident Mission |
Executing Agencies |
National Planning Commission Mr. Puspa Lal Shakya [email protected] Singha Durbar National Planning Commission Singha Durbar Kathmandu, Nepal or P.O. Box 1284 |
Timetable | |
---|---|
Concept Clearance | 16 Sep 2003 |
Fact Finding | 26 Apr 2005 to 29 Apr 2005 |
MRM | - |
Approval | 21 Dec 2005 |
Last Review Mission | - |
PDS Creation Date | 20 Jul 2006 |
Last PDS Update | 26 Jul 2010 |
TA 4752-NEP
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
21 Dec 2005 | 31 Jan 2006 | 31 Jan 2006 | 31 Mar 2007 | 28 Feb 2010 | 22 Jul 2010 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
760,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 760,000.00 | 17 Jun 2022 | 731,665.94 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Regional Development Strategy | TA Completion Reports | Oct 2010 |
Regional Development Strategy | Technical Assistance Reports | Dec 2005 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.