| Project Name | Support for Greater Silk Road Initiative 2005 | ||||
| Project Number | 37483-012 | ||||
| Country / Economy | Regional |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Technical Assistance |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Inclusive economic growth Regional integration |
||||
| Drivers of Change | Knowledge solutions |
||||
| Sector / Subsector | Public sector management / Economic affairs management |
||||
| Gender | |||||
| Description | |||||
| Project Rationale and Linkage to Country/Regional Strategy | |||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Regional |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Tan, Vicky C.L. |
| Responsible ADB Department | Central and West Asia Department |
| Responsible ADB Division | Regional Cooperation and Operations Coordination Div, CWRD |
| Executing Agencies |
Asian Development Bank |
| Timetable | |
|---|---|
| Concept Clearance | 21 Sep 2003 |
| Fact Finding | 22 Sep 2003 to 09 Oct 2003 |
| MRM | - |
| Approval | 18 Nov 2004 |
| Last Review Mission | - |
| PDS Creation Date | 10 Sep 2007 |
| Last PDS Update | 22 Feb 2008 |
TA 6199-REG
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 18 Nov 2004 | - | 18 Nov 2004 | 30 Jun 2006 | 30 Sep 2007 | 31 May 2008 |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 900,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 900,000.00 | 17 Feb 2023 | 839,793.84 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Greater Silk Road Initiative 2005 | TA Completion Reports | May 2008 |
| Greater Silk Road Initiative 2005 | Technical Assistance Reports | Dec 2004 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.