Regional : Greater Mekong Subregion Phnom Penh Plan for Development Management II
The TA will follow the broad goal of phase I: to improve the efficiency and effectiveness of development management in the GMS countries to enhance economic growth and social development. Building on the achievements of the previous project, the aim of the TA is to continue to develop a core group of development managers with the capacity to operate as motivated and competent change agents through training programs focusing mainly on middle- and senior-level executive management training at premier educational institutions in the region.
Project Details
-
Project Officer
Perdiguero, Alfredo
Southeast Asia Department
Request for information -
Country/Economy
Regional -
Modality
-
Sector
- Public sector management
- Project Name
- Greater Mekong Subregion Phnom Penh Plan for Development Management II
- Project Number
- 37624-012
- Country / Economy
- Regional
- Project Status
- Closed
- Project Type / Modality of Assistance
- Technical Assistance
- Source of Funding / Amount
-
TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II Source Amount Technical Assistance Special Fund US$ 800,000.00 TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II (2nd Supplementary) Source Amount People's Republic of China Poverty Reduction and Regional Cooperation Fund US$ 500,000.00 TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II (Supplementary) Source Amount International Fund for Agricultural Development US$ 350,000.00 Technical Assistance Grant Fund (FRA) US$ 1.61 million TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II (3rd Supplementary) Source Amount International Fund for Agricultural Development US$ 500,000.00 TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II (4th Supplementary) Source Amount Technical Assistance Special Fund US$ 250,000.00 TA 6237-REG: Greater Mekong Subregion Phnom Penh Plan for Development Management II (5th Supplementary) Source Amount Technical Assistance Special Fund US$ 310,000.00 - Strategic Agendas
- Regional integration
- Drivers of Change
- Governance and capacity development
- Sector / Subsector
Public sector management / Economic affairs management - Public administration
- Gender
- No gender elements
- Description
- The TA will follow the broad goal of phase I: to improve the efficiency and effectiveness of development management in the GMS countries to enhance economic growth and social development. Building on the achievements of the previous project, the aim of the TA is to continue to develop a core group of development managers with the capacity to operate as motivated and competent change agents through training programs focusing mainly on middle- and senior-level executive management training at premier educational institutions in the region.
- Project Rationale and Linkage to Country/Regional Strategy
The project is in line with the priorities identified by the GMS Working Group on human resources development (HRD) and the regional cooperation.
- Impact
Project Outcome
- Description of Outcome
- Progress Toward Outcome
Implementation Progress
- Description of Project Outputs
- Status of Implementation Progress (Outputs, Activities, and Issues)
- Geographical Location
- Regional
Summary of Environmental and Social Aspects
- Environmental Aspects
- Involuntary Resettlement
- Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
- During Project Design
- During Project Implementation
Business Opportunities
- Consulting Services
- The TA will be implemented by individually recruited international and local consultants who will staff the PPP Secretariat under the close supervision of ADB staff.
Contact
- Responsible ADB Officer
- Perdiguero, Alfredo
- Responsible ADB Department
- Southeast Asia Department
- Responsible ADB Division
- Thailand Resident Mission (TRM)
- Executing Agencies
-
Asian Development Bank
Timetable
- Concept Clearance
- 18 Mar 2003
- Fact Finding
- 19 Mar 2003 to 05 Apr 2003
- MRM
- -
- Approval
- 29 Mar 2005
- Last Review Mission
- -
- PDS Creation Date
- 19 Jun 2006
- Last PDS Update
- 15 Jul 2009
Funding
TA 6237-REG
Approval | Signing Date | Effectivity Date | Closing | ||
---|---|---|---|---|---|
Original | Revised | Actual | |||
29 Mar 2005 | - | 29 Mar 2005 | 31 Mar 2007 | 31 Dec 2008 | 30 Apr 2009 |
ADB | Cofinancing | Counterpart | Total | |||
---|---|---|---|---|---|---|
Gov | Beneficiaries | Project Sponsor | Others | |||
1,360,000.00 | 2,963,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,323,000.00 |
Date | Amount |
---|---|
17 Jun 2022 | 3,354,708.23 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Greater Mekong Subregion Phnom Penh Plan for Development Management Phase II | TA Completion Reports | Feb 2011 |
RETA 6237: Greater Mekong Subregion: Phnom Penh Plan for Development Management II | TA Change in Scope, Amount, and Implementation Arrangements | Aug 2005 |
RETA 6237: Greater Mekong Subregion: Phnom Penh Plan for Development Management II - Supplementary Grants from Government of France and New Zealand Aid: Change in Scope | Technical Assistance Reports | Jul 2005 |
Greater Mekong Subregion Phnom Penh Plan for Development Management II | Technical Assistance Reports | Apr 2005 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.