fbpx 37641-012: Hunan Flood Control Project | Asian Development Bank

China, People's Republic of: Hunan Flood Control Project

Sovereign (Public) Project | 37641-012 Status: Closed

This project shall enable municipality level districts to have flood control capability against once in 50 100 years bid flood, and county level districts to have the capability against once in 20 years big flood. Objectives of the project are in four folds: (i) building a complete enclosure for flood control of affected districts (ii) strengthen the urban flood defense system, so as to improve its ability of flood control and drainage, as well as to reduce flood damage (iii) develop flood control mechanisms through early warning, forecasting and deciding system for flood control and (iv) improve the flood flowing conditions and environment along the river ways. Main components of the project are (i) construct new dikes to raise the existing standards against flood Iii) leeve and foundation seepage control (iii) filling embankment behind dikes (iv) curtain grouting (v) high pressure jet grouting (vi) construct new flood protection walls and strengthen existing ones and (vii) rehabilitate sluice gates.

Project Details

Project Officer
Bolt, Richard S.M. East Asia Department Request for information
Country
  • China, People's Republic of
Modality
  • Technical Assistance
Sector
  • Water and other urban infrastructure and services
 
Project Name Hunan Flood Control Project
Project Number 37641-012
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 4324-PRC: Hunan Flood Control Project
Technical Assistance Special Fund US$ 150,000.00
Technical Assistance Special Fund US$ 150,000.00
Spanish Cooperation Fund for Technical Assistance US$ 550,000.00
Spanish Cooperation Fund for Technical Assistance US$ 550,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector

Water and other urban infrastructure and services / Urban flood protection

Gender Equity and Mainstreaming No gender elements
Description This project shall enable municipality level districts to have flood control capability against once in 50 100 years bid flood, and county level districts to have the capability against once in 20 years big flood. Objectives of the project are in four folds: (i) building a complete enclosure for flood control of affected districts (ii) strengthen the urban flood defense system, so as to improve its ability of flood control and drainage, as well as to reduce flood damage (iii) develop flood control mechanisms through early warning, forecasting and deciding system for flood control and (iv) improve the flood flowing conditions and environment along the river ways. Main components of the project are (i) construct new dikes to raise the existing standards against flood Iii) leeve and foundation seepage control (iii) filling embankment behind dikes (iv) curtain grouting (v) high pressure jet grouting (vi) construct new flood protection walls and strengthen existing ones and (vii) rehabilitate sluice gates. Upon completion of the Project, the standard for flood control in Hunan shall be improved from the previous protection against once in 10 20 years flood to that against once in 100 years flood the standard in other built up areas at municipality level shall be improved from previous protection against once in 10 years flood to once in 50 years and standard in country level districts shall be improved from the previous once in 5 years to once in 20 years.
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services A total of 51.5 person months of consulting services will be required (14.5 international and 37 domestic). The international consultants will provide expertise in (i) flood management, (ii) financial and economic analysis, (iii) resettlement planning and social impact analysis (poverty reduction), and (iv) environmental impact assessment. The domestic consultants will have expertise in (i) flood management, (ii) hydraulic structure engineering, (iii) project economics and financial analysis, (iv) environmental protection and conservation, (v) socioeconomic analysis, (vi) resettlement, and (vi) institutional and legal aspects of flood management. An international consulting firm in association with domestic consultants will be engaged according to ADB's Guidelines on the Use of Consultants and other arrangements satisfactory to ADB for the selection and recruitment of domestic consultants. ADB will select and engage consultants on the basis of the quality and cost based selection method, following simplified technical proposal procedures.
Procurement None.
Responsible ADB Officer Bolt, Richard S.M.
Responsible ADB Department East Asia Department
Responsible ADB Division Agriculture, Environment and Natural Resources Div, EARD
Executing Agencies
Hunan Provincial Government
Ms. Li Kuangyun, Director
[email protected]
418 North Shaoshan Road Shangsha City, Hunan Province People's Republic of China
Timetable
Concept Clearance 10 Mar 2003
Fact Finding 03 Feb 2004 to 13 Feb 2004
MRM -
Approval 29 Mar 2004
Last Review Mission -
Last PDS Update 31 Mar 2006

TA 4324-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
29 Mar 2004 21 Jul 2004 21 Jul 2004 31 Jan 2005 15 Jan 2007 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
850,000.00 550,000.00 0.00 0.00 0.00 0.00 1,400,000.00 29 Mar 2004 689,601.43

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Hunan Flood Control Project Consultants' Reports Jul 2005
Preparing the Hunan Flood Management Project (Cofinanced by the Government of Spain) Technical Assistance Reports Mar 2004

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Hunan Flood Management Sector Project: Xupu County Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Chenzhou City Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Jiangyong County Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Youxian County Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Jishou City Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Shuangfeng County Initial Environmental Examination Initial Environmental Examination Nov 2009
Hunan Flood Management Sector Project: Zhuzhou County Initial Environmental Examination Initial Environmental Examination Mar 2009
Hunan Flood Management Sector Project: Liling City Initial Environmental Examination Initial Environmental Examination Mar 2009
Hunan Flood Management Sector Project: Ningyuan County Initial Environmental Examination Initial Environmental Examination Mar 2009
Hunan Flood Management Sector Project: Xiangtan City Initial Environmental Examination Initial Environmental Examination Mar 2009
Hunan Flood Management Sector Project: Lianyuan City Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Hengyang County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Xintian County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Baojing County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Shaodong County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Luxi County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Fenghuang County Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Zhuzhou City Initial Environmental Examination Initial Environmental Examination Apr 2008
Hunan Flood Management Sector Project: Zhongfang County Initial Environmental Examination Initial Environmental Examination Jul 2007
Hunan Flood Management Sector Project: Qiyang County Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Jianghua County Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Shaoyang City Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Longhui County Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Cili County Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Shimen County Initial Environmental Examination Initial Environmental Examination Jun 2007
Hunan Flood Management Sector Project: Lengshuijiang City Initial Environmental Examination Initial Environmental Examination Jun 2007
Urban Flood Control Project: Shimen County Resettlement Plans Jun 2007
Urban Flood Control Project: Shimen County Resettlement Plan Resettlement Plans Jun 2007
Urban Flood Control Project: Youxian County Resettlement Plans Jun 2007
Urban Flood Control Project: Youxian County Resettlement Plan Resettlement Plans Jun 2007
Urban Flood Control Project: Chenzhou City Resettlement Plans Jun 2007
Urban Flood Control Project: Chenzhou City Resettlement Plan Resettlement Plans Jun 2007
Urban Flood Control Project: Jishou City Resettlement Plans Jun 2007
Urban Flood Control Project: Jishou City Resettlement Plan Resettlement Plans Jun 2007
Urban Flood Control Project: Lengshuijiang City Resettlement Plans Jun 2007
Urban Flood Control Project: Lengshuijiang City Resettlement Plan Resettlement Plans Jun 2007
Urban Flood Control Project: Cili County Resettlement Plans Mar 2007
Urban Flood Control Project: Cili County Resettlement Plan Resettlement Plans Mar 2007
Hunan Flood Management Sector Project: Hengyang City Initial Environmental Examination Initial Environmental Examination Apr 2006
Hunan Flood Management Sector Project: Yongzhou City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Leiyang City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Loudi City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Sangzhi City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Wugang City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Chenxi City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Xinhua City Initial Environmental Examination Initial Environmental Examination Jul 2005
Hunan Flood Management Sector Project: Huaihua City Initial Environmental Examination Initial Environmental Examination Jul 2005

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.