Viet Nam : SME Development Program Loan - Subprogram II

Sovereign Project | 38335-013

Project Name SME Development Program Loan - Subprogram II
Project Number 38335-013
Country / Economy Viet Nam
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2284-VIE: SME Development Program Loan - Subprogram II
Asian Development Fund US$ 20.00 million
Loan: SME Development Program Loan - Subprogram II
Agence Francaise de Developpement US$ 16.40 million
KfW Bankengruppe US$ 7.57 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Private sector development
Sector / Subsector

Industry and trade / Small and medium enterprise development

Gender
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Cyhn, Jin W.
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Public Management, Financial Sector and Trade Division, SERD
Executing Agencies
Ministry of Planning and Investment
Timetable
Concept Clearance 09 Aug 2005
Fact Finding 24 Jul 2006 to 28 Jul 2006
MRM 31 Aug 2006
Approval 12 Dec 2006
Last Review Mission -
PDS Creation Date 15 Mar 2006
Last PDS Update 16 Apr 2010

Loan 2284-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
12 Dec 2006 16 Jan 2007 05 Jun 2007 01 Jul 2008 31 Mar 2009 31 Mar 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 20.00 Cumulative Contract Awards
ADB 20.00 17 Feb 2023 20.18 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 17 Feb 2023 20.18 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Viet Nam: Small and Medium-Sized Enterprise Development Program Cluster (Subprograms 1 and 2) Validations of Project Completion Reports Dec 2012

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.