Pakistan : Power Distribution Enhancement Investment Program - Tranche 3

Sovereign Project | 38456-034

The project proposed for financing under the requested PFR are:

1. Secondary Transmission Grid (STG)

a. Augmentation replacement of power transformers with higher capacity transformer;

b. Extension addition of power transformers;

c. Conversion of existing 66-kV substations to 132-kV substations with enhanced transformation and current carrying capacity; and

d. Addition of new 132-kV grid station.

2. STG transmission lines:

a. Conversion of existing 66-kV transmission lines to 132-kV transmission lines;

b. Replacement of existing transmission lines to increase load carrying capacity; and

c. Extension addition of transmission lines.

Project Name
Power Distribution Enhancement Investment Program - Tranche 3
Project Number
38456-034
Country / Economy
  • Pakistan
Project Status
Closed
Project Type / Modality of Assistance
  • Loan
Source of Funding / Amount
Loan 2972-PAK: Power Distribution Enhancement Investment Program - Tranche 3
Source Amount
Ordinary capital resources US$ 245.00 million
Strategic Agendas
  • Inclusive economic growth
Drivers of Change
    Sector / Subsector
    • Energy / Electricity transmission and distribution

    Gender
    No gender elements
    Description

    The project proposed for financing under the requested PFR are:

    1. Secondary Transmission Grid (STG)

    a. Augmentation replacement of power transformers with higher capacity transformer;

    b. Extension addition of power transformers;

    c. Conversion of existing 66-kV substations to 132-kV substations with enhanced transformation and current carrying capacity; and

    d. Addition of new 132-kV grid station.

    2. STG transmission lines:

    a. Conversion of existing 66-kV transmission lines to 132-kV transmission lines;

    b. Replacement of existing transmission lines to increase load carrying capacity; and

    c. Extension addition of transmission lines.

    Project Rationale and Linkage to Country/Regional Strategy
    The project is urgently needed to further alleviate the power distribution system bottlenecks and to reduce prolonged outages and load shedding.
    Impact

    Reliable and quality power supplied and service coverage expanded.

    Project Outcome

    Description of Outcome

    Power distribution systems rehabilitated, augmented and expanded.

    Progress Toward Outcome
    Construction works for rehabilitation, conversion, augmentation, and extensions including addition of new transmission lines and grid station is on going and will be completed by 30 June 2018.

    Implementation Progress

    Description of Project Outputs

    Subprojects commissioned.

    Status of Implementation Progress (Outputs, Activities, and Issues)

    41 subprojects completed by 2017 and remaining would be done before loan closing of 30 June 2018.

    1303 km added to the system by 2017 and more km additions expected by 30 June 2018.

    Works still ongoing for completion of grid stations and would be completed by 30 June 2018.

    Geographical Location
    Attock, Badin, Bahawalnagar, Bahawalpur, Bhakkar, Charsadda, D. G. Khan, D. I. Khan, Faisalabad, Gujrat, Hyderabad, Islamabad, Islamabad, Jhang, Kalat, Karak, Kasur, Khanewal, Khuzdar, Killa Saifullah, Kohat, Lahore, Loralai, Lower Dir, Mandi Bahauddin, Mansehra, Mardan, Mastung, Mianwali, Mirpur Khas, Nowshera, Okara, Pishin, Quetta, Rawalpindi, Sahiwal, Sargodha, Sheikhupura, Sialkot, Swabi, Tank, Toba Tek Singh, Vehari

    Safeguard Categories

    Environment
    B
    Involuntary Resettlement
    B
    Indigenous Peoples
    C

    Summary of Environmental and Social Aspects

    Environmental Aspects

    The project is classified as "B" for environmental safeguards. The Government will cause each DISCO to ensure that (i) the subprojects are designed, constructed, operated, and maintained in accordance with all applicable laws and regulations of Pakistan and ADB's Environment Policy (ADB's Safeguard Policy Statement for subprojects initiated after June 2009); (ii) all subprojects will strictly follow the mitigation measures identified in the IEE, including the EMPs and the EARF; (iii) mitigation measures identified in the EMPs will be incorporated in bidding documents and civil work contracts and implemented under supervision of the DISCOs; and (iv) environmental monitoring reports will be submitted to ADB twice annually during the construction and operation period, including progress made on the mitigation measures, monitoring data, problems encountered, enforcement plan, complaints, violation, or modifications to mitigation measures to take account of unexpected environmental impacts and the acceptability of the residual impact.

    Involuntary Resettlement
    The project is classified as "B" for resettlement. Land Acquisition and Resettlement. Medium/low voltage lines up to 11 kV causing LAR or income impacts will not be eligible for financing under the MFF. However, lines at voltages of 33 kV and above and substation subprojects causing LAR or income impacts will be fully eligible for financing under the MFF. In the case of these subprojects, the Government will cause each DISCO to ensure that (i) all land and rights-of-way required by the subprojects are made available in a timely manner; (ii) the provisions of the relevant LARP are implemented promptly and efficiently according to its terms, applicable laws and regulations of Pakistan, ADB's Policy on Involuntary Resettlement (ADB's Safeguard Policy Statement for subprojects initiated after June 2009); ADB's Operations Manual F2 on Involuntary Resettlement (2003), and the LARP; (iii) the relevant LARP is updated based on the detailed design, prepared in full consultation with the affected persons and disclosed to them prior to submitting the LARP to ADB; (iv) the contractors' activities are in compliance with requirements of the relevant LARP and the LARF, and (v) an independent monitor acceptable to ADB is engaged to carry out monitoring and evaluation and report to ADB in accordance with the requirements of the LARPs. The signing of civl work contracts or a similar milestone will be subject to ADB review and approval of implementation of the relevant LARPs, including the provision of full compensation to the affected people.
    Indigenous Peoples
    The project is classified as "C" for indigenous people. The government will cause each DISCO to ensure that all subprojects affecting trial peoples are constructed and operated in accordance with the requirements of ADB's Policy on Indigenous Peoples (ADB's Safeguard Policy Statement for subprojects initiated after June 2009) as specified in the IPDPs agreed with ADB. Each DISCO will ensure that IPDPs are monitored and evaluated by an independent agency.

    Stakeholder Communication, Participation, and Consultation

    During Project Design
    At the design stage of MFF, stakeholder analysis has been undertaken. All stakeholders were involved in order to reduce the likelihood of grievances and to ensure that benefits are distributed fairly. Since there were no major changes in project design, no separate consultations were undertaken for Tranche 3. However, information on social safeguards and LARPs have been shared through public meetings.
    During Project Implementation
    None.

    Business Opportunities

    Consulting Services
    The DISCOs and PEPCO will be supported by the facility management consultant, already hired under the MFF Support Component, in monitoring the project and providing guidance and technical support to the executing agency and implementing agencies.
    Procurement

    The procurement plan for the Tranche has been prepared for the first 18 months. There will be 23 ICB packages. Procurement experts working in the PMUs have reasonable expertise and have been provided with extensive training by ADB in the past three years. These staff have been actively involved in procurement of goods and turnkey contracts during the previous two tranches. Being familiar with ADB's standard bidding documents and to amplify project readiness, the DISCOs have prepared the first draft bidding documents for ICB contracts. It is expected that a few of the ICB packages will be advertised within Q4 of 2012, and the remaining during Q1 of 2013.

    Advance contracting and retroactive financing of expenditures for the first and subsequent tranches (up to 20% of the proceeds from individual loans under the MFF) were approved by ADB, provided that those expenditures are incurred in accordance with agreed procedures and during the 12 months before the signing of the corresponding individual loan agreement and loan effectiveness under the MFF. Because of the urgent nature of the project, retroactive financing will cover eligible expenditures including works carried out under the categires of turnkey and equipment. Such financing will be subject to compliance with involuntary resettlement requirements stated in the LARPs. The government and the DISCOs were informed that approval of advanced contracting and retroactive financing does not commit ADB to finance any of the proposed subprojects. The DISCOs were also advised that they must comply with all ADB procurement procedures in order to qualify for retroactive financing.

    Contact

    Responsible ADB Officer
    Khattak, Ehtesham Zafar
    Responsible ADB Department
    Central and West Asia Department
    Responsible ADB Division
    Pakistan Resident Mission (PRM)
    Executing Agencies
    Pakistan Electric Power Company (Pvt.) Limited

    Timetable

    Concept Clearance
    -
    Fact Finding
    -
    MRM
    08 Nov 2012
    Approval
    14 Dec 2012
    Last Review Mission
    -
    Last PDS Update
    20 Sep 2018

    Funding

    Loan 2972-PAK

    Milestones
    Approval Signing Date Effectivity Date Closing
    Original Revised Actual
    14 Dec 2012 09 Sep 2013 10 Dec 2013 31 Dec 2016 30 Jun 2018 22 Apr 2019
    Financing Plan
      Total (Amount in US$ million)
    Project Cost 272.00
    ADB 245.00
    Counterpart 27.00
    Cofinancing 0.00
    Loan Utilization
      Date ADB Others Net Percentage
    Cumulative Contract Awards 25 Oct 2022 212.81 0.00 100%
    Cumulative Disbursements 25 Oct 2022 212.81 0.00 100%
    Status of Covenants
    Category Sector Safeguards Social Financial Economic Others
    Rating - Satisfactory Satisfactory Satisfactory - Satisfactory

    Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

    The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

    The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

    In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

    Title Document Type Document Date
    Power Distribution Enhancement Investment Program – Tranche 3: GEPCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: PESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: LESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: HESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: QESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: FESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: MEPCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Program – Tranche 3: IESCO Audited Project Financial Statements (July 2018-June 2019) Audited Project Financial Statements Dec 2019
    Power Distribution Enhancement Investment Project - Tranche 3: Completion Report Project/Program Completion Reports Sep 2019
    Power Distribution Enhancement Investment Program – Tranche 3: FESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: MEPCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: IESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: GEPCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: PESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: LESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: HESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program – Tranche 3: QESCO Audited Project Financial Statements (July 2017-June 2018) Audited Project Financial Statements Dec 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - FESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - QESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - LESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - HESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - PESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - GEPCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - MEPCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Audited Project Financial Statements - IESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3 Procurement Plans Apr 2014
    Project Agreement for Power Distribution Enhancement Investment Program - Project 3 Project/Program Agreements Sep 2013
    Loan Agreement for Power Distribution Enhancement Investment Program - Project 3 Loan Agreement (Ordinary Resources) Sep 2013
    Power Distribution Enhancement Investment Program - Tranche 3: Project Data Sheet (Urdu Translation) Translated PDS Mar 2013

    Safeguard Documents See also: Safeguards
    Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

    Title Document Type Document Date
    Power Distribution Enhancement Investment Program - Tranche 3: IESCO Social Monitoring Report Social Monitoring Reports Jun 2019
    Power Distribution Enhancement Investment Program – Tranche 3: GEPCO Social Monitoring Report (January-June 2019) Social Monitoring Reports Jun 2019
    Power Distribution Enhancement Investment Project - Tranche III: FESCO Final Social Monitoring Report Social Monitoring Reports Feb 2019
    Power Distribution Enhancement Investment Program – Tranche 3: GEPCO Social Monitoring Report (July-December 2018) Social Monitoring Reports Jan 2019
    Power Distribution Enhancement Investment Program – Tranche 3: GEPCO Environmental Monitoring Report (July-December 2018) Environmental Monitoring Reports Jan 2019
    Power Distribution Enhancement Investment Program - Tranche 3: GEPCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: FESCO Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: IESCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: PESCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: MEPCO Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: HESCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: FESCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: MEPCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (July–December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (July–December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (July-December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, HESCO (July–December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, PESCO (July-December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (July-December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, FESCO (July–December 2017) Environmental Monitoring Reports Jan 2018
    Power Distribution Enhancement Investment Program - Tranches 1-4: Social Monitoring Report (July-December 2017) Social Monitoring Reports Dec 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (July-December 2017) Social Monitoring Reports Dec 2017
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Social Monitoring Report (July-December 2017) Social Monitoring Reports Dec 2017
    Power Distribution Enhancement Investment Program - Tranche 3: FESCO Environmental Monitoring Report (January-June 2017) Environmental Monitoring Reports Jul 2017
    Power Distribution Enhancement Investment Program - Tranche 3: GEPCO Environmental Monitoring Report (January-June 2017) Environmental Monitoring Reports Jul 2017
    Power Distribution Enhancement Investment Program - Tranche 3: HESCO Environmental Monitoring Report (January-June 2017) Environmental Monitoring Reports Jul 2017
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Biannual Social Monitoring Report (January-June 2017) Social Monitoring Reports Jul 2017
    Power Distribution Enhancement Investment Program - Tranche 3: MEPCO Biannual Social Monitoring Report (January-June 2017) Social Monitoring Reports Jul 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Chakri Road Subproject Resettlement Plan Resettlement Plans Jun 2017
    Power Distribution Enhancement Investment Program - Tranche 3: IESCO Biannual Social Monitoring Report (January-June 2017) Social Monitoring Reports Jun 2017
    Power Distribution Enhancement Investment Program - Tranche 3: HESCO Biannual Social Monitoring Report (January-June 2017) Social Monitoring Reports Jun 2017
    Power Distribution Enhancement Investment Program - Tranche 3: FESCO Biannual Social Monitoring Report (January-June 2017) Social Monitoring Reports Jun 2017
    Power Distribution Enhancement Investment Program - Tranche 3: 132KV Grid Station Barki Initial Environmental Examination Initial Environmental Examination Apr 2017
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Barki DHA Phase VIII Grid Station Social Due Diligence Report Safeguards Due Diligence Reports Apr 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Underground Cable from Shalamar GIS to Shalamar-II Grid Station Initial Environmental Examination Initial Environmental Examination Mar 2017
    PTEIP - Tranche 3: MEPCO Yazman Grid Station Conversion Initial Environmental Examination Initial Environmental Examination Feb 2017
    Power Distribution Enhancement Investment Program - Tranches 1, 2, 3 and 4: Social Monitoring Report (July-December 2016) Social Monitoring Reports Feb 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, GEPCO (July-December 2016) Social Monitoring Reports Feb 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, PESCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, HESCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (July–December 2016) Environmental Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, FESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, QESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, IESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, LESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, PESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, HESCO (July-December 2016) Social Monitoring Reports Jan 2017
    Power Distribution Enhancement Investment Program - Tranche 3: LESCO Shalamar–Shalamar II Grid Stations Underground Cable Resettlement Due Diligence Report Safeguards Due Diligence Reports Dec 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Dera Murad Jamali, Rojhan Jamali, Usta Muhammad and Jhal Magsi Grid Stations Initial Environmental Examination Initial Environmental Examination Oct 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, FESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, HESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, QESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, PESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (January-June 2016) Environmental Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (January-June 2016) Social Monitoring Reports Aug 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report IESCO (January-June 2016) Social Monitoring Reports Jul 2016
    Power Distribution Enhancement Investment Program - Tranches 1, 2, and 3: Social Monitoring Report (January-June 2016) Social Monitoring Reports Jul 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, HESCO (January-June 2016) Social Monitoring Reports Jul 2016
    PDEIP - Tranche 3: Conversion (from 66k V to 132 kV) of Dera Murad Jamali, Rojhan Jamali, Usta Muhammad, and Jhal Magsi Grid Stations Resettlement Plan Resettlement Plans Jun 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, PESCO (July-December 2015) Social Monitoring Reports Mar 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, HESCO (July-December 2015) Social Monitoring Reports Mar 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (July-December 2015) Environmental Monitoring Reports Feb 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, FESCO (July-December 2015) Social Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, QESCO (July-December 2015) Social Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, GEPCO (June-December 2015) Social Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (July-December 2015) Social Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, IESCO (July-December 2015) Social Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, QESCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, HESCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, FESCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (July-December 2015) Environmental Monitoring Reports Jan 2016
    Power Distribution Enhancement Investment Program - Tranche 3: 132 kV New Sangjani Grid Station and Transmission Line Resettlement Plan Resettlement Plans Dec 2015
    Power Distribution Enhancement Investment Program - Tranche 3: In and Out Construction at Chakri Substation Transmission Line Subproject Resettlement Plan Resettlement Plans Nov 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, GEPCO (January-June 2015) Social Monitoring Reports Nov 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Bara Kahu Grid Station and Transmission Line Resettlement Due Diligence Report Safeguards Due Diligence Reports Oct 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Bi-annual Social Monitoring Report (January-July 2015) Environmental Monitoring Reports Oct 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (January-June 2015) Social Monitoring Reports Oct 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, FESCO (January-June 2015) Social Monitoring Reports Oct 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, LESCO (January-June 2015) Social Monitoring Reports Oct 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, FESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, PESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, HESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, QESCO (January-June 2015) Environmental Monitoring Reports Jul 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, LESCO (July-December 2014) Social Monitoring Reports Apr 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, HESCO (July-December 2014) Social Monitoring Reports Apr 2015
    Power Distribution Enhancement Investment Program - Tranche 3: 132 kV New Matli Grid Station Due Diligence Report Safeguards Due Diligence Reports Apr 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, IESCO (July-December 2014) Social Monitoring Reports Apr 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, LESCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, QESCO (July-December 2014) Social Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, GEPCO (June-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, GEPCO (July-December 2014) Social Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, QESCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, MEPCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, IESCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Social Monitoring Report, MEPCO (July-December 2014) Social Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, FESCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Biannual Environmental Monitoring Report, PESCO (July-December 2014) Environmental Monitoring Reports Jan 2015
    Power Distribution Enhancement Investment Program - Tranche 3: Hala Road GS - Hala, 132 kV Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Tando Muhammad Khan - New Matli,132 kV Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: M16: Shahdan Lund–Shah Sadar Din 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Construction of Double Circuit 132 kV Transmission Line from Loralai to Quetta Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Tando Ghulam Ali - Digri,132 kV Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of 66Kv to 132Kv Malikwal Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of 66Kv to 132Kv Siranwali Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Chistian–Daharanawala, 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Digri - Tando Jan Muhammad, 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Mianchanu–Chak 83 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Construction of Double Circuit 132 kV Transmission Line from Khuzdar to Quetta Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Tando Jan Muhammad - Naukot, 132 kV Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of 66Kv to 132Kv of the Daska Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Haroonabad–Faqirwali, 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Hasilpur–Chunnawala 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: New Matli - Tando Ghulam Ali, 132 kV Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of Head Marala Grid Station from 66Kv to 132Kv Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Faqirwali–Fort Abbas, 132 kV Single Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Mubarak Pur 132kV Grid Station and Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Digri Conversion from 66 KV to 132 KV and Tando Ghulam Ali – 132 KV Digri SDT Transmission Line Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of 132 KV SDT Transmission Line from 132 KV Tando Jan Muhammad to 132 KV Noukot Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of 132 KV New Matli Grid Station and Tando Muhammad Khan – 132 KV New Matli Double Circuit Transmission Line Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Tando Jan Muhammad Conversion from 66 KV to 132 KV and Tando Jan Muhammad -132 KV Digri SDT Transmission Line Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Tando Ghulam Ali Conversion from 66 KV to 132 KV and New Matli – 132 KV TG Ali SDT Transmission Line Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program Tranche 3 Resettlement Frameworks Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: 132 KV Taru Jabba New Substation Development Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Augmentation of PESCO Subprojects (Rehman Baba, Swabi, Bannu, D.I.Khan, Kotal Town Kohat, Jalala, Jehangir and Batal) Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Chakri Road Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 30 Km Double Circuit 132 KV Transmission Line Subproject Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program – Tranche 3: Conversion of 66 KV Shah Sadar Din Grid Station to 132KV and 132KV SDT Transmission Line from Shahdan Lund to Shah Sadar Din Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of Malikwal Grid Station from 66kV to 132kV and Double Circuit 132kV Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66KV Daraban to 132KV Grid Station and 132 KV SDT Transmission Line to feed Daraban Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Burhan-New Wah Cct 1 &2 132 kV Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: In & Out Construction at Chakri Sub Station Transmission Line Subproject Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Transmission Line from Jinah Hydropower - 220 KV Daud Khel to 66 KV Kalabagh Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of New 132 KV Mubarak Pur Grid Station Initial Environmental Examination Oct 2012
    Construction of 132KV Extension Bay at 220/132KV Hala Road DGS and 132KV Hala DGS Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66 KV to 132 KV Dahranwala Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of Head Marala Grid Station from 66kV to 132kV and Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program – Tranche 3: Augmentation of MEPCO Sub-Projects Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: 132 KV Sakhi Chashma New Substation Development Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Khuzdar - Quetta Industrial 132KV Double Circuit Transmission line Subproject Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Darban Grid Station Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: New Rawat - Sowan Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 45 Km 132 KV transmission line from 66 KV Grid Station 18-Hazari to 66 KV Grid Station Garh Maharaja Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66KV to 132 KV Chak 83/12-L Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66 KV to 132 KV Fort Abbas Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of Siranwali Grid Station from 66kV to 132kV and Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Power Transformer's Extension Subprojects (Dalazak, Karak, Tank, Hussai and Timergara) Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 kV New Sangjani Grid Station & Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV 60 Km Double Circuit Toba Tek Singh-Havile Bahadar Shah Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: New 132KV Chunawala Grid Station Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66 KV Faqirwali Grid Station to 132 KV Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Conversion of Daska Grid Station from 66kV to 132kV and Double Circuit Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Conversion of 66KV Kulachi to 132KV Grid Station and 132 KV Double Circuit Transmission Line to feed Kulachi Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Loralai - Quetta Industrial 132KV Double Circuit Transmission Line Subproject Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Kulachi Grid Station Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Sangjani - Zero Point 132kV Transmission Line Resettlement Plans Oct 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Double Circuit Three Km 132 KV Transmission Line subproject from Piplan-Rakh Dagran Grid Station Resettlement Plans Oct 2012
    Construction of 132 KV SDT Transmission Line from 220/132 KV Hala Road to Hala Initial Environmental Examination Oct 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Rakh Dagran Grid Station and Piplan Bhakkar In & Out Rakh Dagran Grid Station Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Hazari Grid Station and Havelli Bahadar Shah to 18 - Hazari Grid Station Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program (Proposed Tranche 3): Environmental Assessment and Review Framework Environmental Assessment and Review Framework Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Kala Bagh Grid Station and Jinnah Hydropower - Daud Khel In & Out Kala Bagh Grid Station Initial Environmental Examination Sep 2012
    Construction of New 60km Double Circuit 132Kv Transmission Line from 220Kv Grid Station Toba Tek Singh to Havelli Bahadar Shah Grid Station Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Garh Maharaja Grid Station and Hazari to GM Raja Grid Station Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of New 132Kv Grid Station at DHA Phase-VI Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of New 132Kv Grid Station at Sadhoki Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of New 132Kv Grid Station at DHA Phase-VII Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Construction of New 132Kv Grid Station at Fruit Mandi Initial Environmental Examination Sep 2012
    Power Distribution Enhancement Investment Program – Proposed Tranche 3 Environmental Assessment and Review Framework Sep 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132KV Rewat - Sowan Double Circuit Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Augmentation & Extension of Power Transformer Subprojects Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Construction of 132Kv Grid Station at Shahbaz Khel District Mianwali Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: In and Out Construction at 132KV Chakri Grid Station Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: Construction of 132Kv Grid Station at Faisalabad City, near Railway Colony Faisalabad Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Chakri Road Grid Station with New 132 KV Double Circuit Feeding Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Koh-E-Noor Textile Mill – Chakri Road Double Circuit Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Sang Jani – Zero Point Double Circuit Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Proposed Tranche 3: Transformer’s Augmentation & Extension Sub-Projects Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Sang Jani II Grid Station and New 132 KV Double Circuit Feeding Transmission Line Initial Environmental Examination Aug 2012
    Power Distribution Enhancement Investment Program - Tranche 3: 132 KV Burhan–New Wah Double Circuit Transmission Line Initial Environmental Examination Aug 2012

    Evaluation Documents See also: Independent Evaluation

    Title Document Type Document Date
    Pakistan: Power Distribution Enhancement Investment Program—Tranche 3 Validations of Project Completion Reports Jul 2020

    Related Publications

    None currently available.


    The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

    Requests for information may also be directed to the InfoUnit.

    Tenders


    Contracts Awarded

    Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
    PROCUREMENT OF 132/11.5KV, 31.5/40 MVA POWER TRANS FORMERS (03 NOS.) Loan 2972 14 Mar 2018 CHINT ELECTRIC CO, LTD, CHINA | NO.3555,SIXIAN ROAD,SONGJIANG DISTRICT, SHANGHAI P.R.CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited 1,035,000.00 1,035,000.00
    PROCUREMENT OF 132/11.5KV, 20/26 MVA POWER TRANSFO RMERS (08 NOS.) Loan 2972 04 Jan 2018 CHINT ELECTRIC CO, LTD, CHINA | NO. 3555, SIXIAN ROAD, SONGJIANG DISTRIC T, SHANGHAI, P.R. CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited 2,281,000.00 2,281,000.00
    PROCUREMENT OF CONDUCTOR Loan 2972 03 Jul 2017 NEWAGE CABLES (PVT.) LTD. | HOUSE 33-K, GULBERG-II LAHORE PAKISTAN Pakistan Electric Power Company (Pvt.) Limited 1,249,799.00 1,248,080.00
    PROCUREMENT OF 132KV TOWERS AND STEEL GANTRIES Loan 2972 05 Jul 2017 ASSOCIATED TECHNOLOGIES (PVT.) LTD. | 142-D MODEL TOWN LAHORE PAKISTAN Pakistan Electric Power Company (Pvt.) Limited 2,259,383.00 2,250,868.00
    Procurement of Plant, Design, Supply, Installation and Commissioning of Dera Murad Jamali, Rojhan Jamali, Usta Muhammad and Jhal Magsi 132 KV Trans Lines Loan 2972 10 Mar 2017 Northeast China International Electric Power | 18 Ningbo Road, Heping District Shenyang China, People's Republic of Pakistan Electric Power Company Pvt. Limited 11,619,682.91 11,619,682.91
    Procurement/Supply of Hardware Material Loan 2972 21 Apr 2017 Sa-Ra Energy Construction Trade and Industry | Masuh Akar Mah 1405 Sok. No. 6 06520 Balgat - Ankara Turkey Pakistan Electric Power Company Pvt. Limited 129,902.10 129,902.00
    Procurement of Fog Type Disc Insulator (80Kn and 100Kn) Loan 2972 18 Apr 2017 Suzhou Porcelain Insulator Works Co., Ltd. | No. 20 Chunhui Road, Weiting District, Sip Suzhou, Pr. China, 215122 China, People's Republic of Pakistan Electric Power Company Pvt. Limited 157,287.50 157,285.09

    Procurement Plan

    Title Document Type Document Date
    Power Distribution Enhancement Investment Program - Tranche 3 Procurement Plans Apr 2014