38456-037: Power Distribution Enhancement Investment Program - Tranche 4 | Asian Development Bank

Pakistan: Power Distribution Enhancement Investment Program - Tranche 4

Sovereign (Public) Project | 38456-037 Status: Active

ADB is supporting efforts of Pakistan to improve the reliability of electricity supply in the country. The project covers investment in the secondary transmission grid, energy loss reduction and distribution of power, spare power transformers for emergencies. It will add 5,021 megavolt-amperes of transformer capacity and improve distribution efficiency.  

 
Project Name Power Distribution Enhancement Investment Program - Tranche 4
Project Number 38456-037
Country Pakistan
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4
Ordinary capital resources US$ 167.20 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector

Energy / Conventional energy generation

Gender Equity and Mainstreaming No gender elements
Description The project comprises physical investments in subprojects covering (i) secondary transmission grid (STG): augmentation and extension of 132-kV power transformers at existing substations; (ii) energy loss reduction and distribution of power: replacement of overloaded distribution transformers with higher capacity and adding additional distribution transformer capacity on the 11-kV feeders; and (iii) strategic spares: spare power transformers for emergencies. The project will add 5,021 megavolt-amperes (MVA) of transformer capacity and will improve the distribution system''s efficiency and delivery.
Project Rationale and Linkage to Country/Regional Strategy The project is urgently needed to further alleviate the power distribution system bottlenecks and to reduce prolonged outages and load shedding. The project will help the DISCOs improve reliability and quality of power supply to customers. The outcome will be removal of power system bottlenecks by reducing the overloading of the system and increasing the transmission capacity of the substations through distribution system augmentation and expansion.
Impact Reliable and quality power supplied and service coverage expanded.
Project Outcome
Description of Outcome Capacity of the power distribution systems increased.
Progress Toward Outcome Capacity of power distribution system is improving and would be increased further by 2018.
Implementation Progress
Description of Project Outputs Subprojects commissioned.
Status of Implementation Progress (Outputs, Activities, and Issues)

154 STG projects completed by 2017 and more to be done by 2018.

112 extension works completed by 2017 and more to be done by 2018.

Geographical Location Barana, Bhakkar, Bhalwal, Bhalwala, Bhamb, Bhawana, Chak One Hundred Twenty-Eight, Chiniot, Faisalabad, Jaranwala, Jauharabad, Jhang City, Jhumra, Kamalia, Khiwa, Khurrianwala, Kirana, Kirana, Lalian, Pir Mahal, Sammundri, Tandlianwala, Thikriwala, Toba Tek Singh
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects Due diligence was undertaken to assess the environmental implications of the project activities. The project is limited to up gradation of grid stations, which involves transformer replacement, or transformer addition and no civil works are anticipated and all replacement activities will take place within the boundaries of the existing grid stations. Accordingly, the project has been classified as C for environmental safeguards requiring no further environmental assessment. An environmental assessment review framework was prepared for the MFF in 2009, which was updated in 2012 to fulfill the requirements of ADB's SPS 2009. All subprojects are required to comply with ADB's Prohibited Investment Activities' list. Each DISCO has established an environment and social impact cell and, in compliance with the loan agreement, hired one environment specialist to implement the environmental mitigation measures detailed in the environment management plans of ongoing previous tranches.
Involuntary Resettlement The project is classifed as "C" for resettlement. All works are proposed to be carried out entirely within existing grid stations and no land acquisition resettlement impacts are anticipated. As a result, there is no need to update the approved and disclosed Land Acquisition and Resettlement Framework for tranche 4 processing.
Indigenous Peoples The project is classifed as "C" for indigenous peoples. The project will have no impact on indigenous peoples.
Stakeholder Communication, Participation, and Consultation
During Project Design No direct consultation will be undertaken.
During Project Implementation No direct consultation will be undertaken.
Business Opportunities
Consulting Services There will be no recruitment of consulting services.
Procurement There are eight international competitive bidding (ICB) packages covering activities such as procurement of transformers, panels, cables and allied equipment, etc. If applicable (based on the thresholds indicated in the procurement plan), individual lots under the ICB packages that did not lead to contract awards will be procured under national competitive bidding (NCB). There will be two civil works contracts under NCB.
Responsible ADB Officer Khattak, Ehtesham Zafar
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Pakistan Resident Mission
Executing Agencies
Pakistan Electric Power Company (Pvt.) Limited
[email protected]
403-WAPDA House
Shahra-i-Quaid-i-Azam
Lahore-54000, Pakistan
Timetable
Concept Clearance -
Fact Finding -
MRM 20 Nov 2013
Approval 13 Dec 2013
Last Review Mission -
Last PDS Update 20 Sep 2018

Loan 3096-PAK

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Dec 2013 30 Apr 2014 18 Jul 2014 30 Jun 2017 30 Jun 2018 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 167.20 Cumulative Contract Awards
ADB 167.20 13 Dec 2013 142.45 0.00 95%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 13 Dec 2013 130.92 0.00 87%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - QESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - IESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - LESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - FESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - MEPCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - GEPCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - PESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - HESCO (July 2015-June 2016) Audited Project Financial Statements Dec 2016
Amendment to the Loan Agreement for Loan 3096-PAK: Power Distribution Enhancement Investment Program - Project 4 Loan Agreement (Ordinary Resources) Jan 2016
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - PESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - HESCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
Power Distribution Enhancement Investment Program - Tranche 4: Audited Project Financial Statements - GEPCO (July 2014-June 2015) Audited Project Financial Statements Dec 2015
Power Distribution Enhancement Investment Program - Tranche 4: Procurement Plan Procurement Plans Jul 2015
Loan Agreement for Power Distribution Enhancement Investment Program - Project 4 Loan Agreement (Ordinary Resources) Apr 2014
Project Agreement for Power Distribution Enhancement Investment Program - Project 4 Project/Program Agreements Apr 2014

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Power Distribution Enhancement Investment Program - Tranche 4: MEPCO Environmental Monitoring Report (January-June 2018) Environmental Monitoring Reports Jul 2018
Power Distribution Enhancement Investment Program - Tranche 4: FESCO Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
Power Distribution Enhancement Investment Program - Tranche 4: MEPCO Social Monitoring Report (January-June 2018) Social Monitoring Reports Jul 2018
Power Distribution Enhancement Investment Program - Tranches 1-4: Social Monitoring Report (July-December 2017) Social Monitoring Reports Dec 2017
Power Distribution Enhancement Investment Program - Tranche 4: Biannual Environmental Monitoring Report, MEPCO (January-June 2017) Environmental and Social Monitoring Reports Jul 2017
Power Distribution Enhancement Investment Program - Tranche 4: Biannual Social Monitoring Report, FESCO (January-June 2017) Environmental and Social Monitoring Reports Jun 2017
PTEIP - Tranche 4: MEPCO Buch Villas Grid Station Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: MEPCO Choti Grid Station Conversion Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: MEPCO Punjab Government Employees Housing Society Grid Station Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: LESCO 132 kV GIS Grid Station Punjab University Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: IESCO Conversion of 66 kV Tamman Grid Station to 132 kV and New 132 kV Transmission Line Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: IESCO Conversion of 66 kV Danda Shah Bilawal Grid Station to 132 kV and New 132 kV Transmission Line Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: IESCO Conversion of 66 kV Jand Grid Station to 132 kV and New 132 kV Transmission Line Initial Environmental Examination Initial Environmental Examination Feb 2017
PTEIP - Tranche 4: IESCO Conversion of 66 kV Lakarmar Grid Station to 132 kV and New 132 kV Transmission Line Initial Environmental Examination Initial Environmental Examination Feb 2017
Power Distribution Enhancement Investment Program - Tranches 1, 2, 3 and 4: Social Monitoring Report (July-December 2016) Social Monitoring Reports Feb 2017
Power Distribution Enhancement Investment Program - Tranche 4: LESCO Sunny View-Mcleod-Qurtaba Underground Cable Initial Environmental Examination Initial Environmental Examination Feb 2017
Power Distribution Enhancement Investment Program - Tranche 4: Biannual Social Monitoring Report, MEPCO (July-December 2016) Social Monitoring Reports Jan 2017
Power Distribution Enhancement Investment Program - Tranche 4: LESCO Qartaba–Mcleod Grid Stations Underground Cable Resettlement Due Diligence Report Safeguards Due Diligence Reports Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: LESCO Punjab University Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Dec 2016
Power Distribution Enhancement Investment Program - Tranche 4: LESCO Sunny View–Mcleod Grid Stations Underground Cable Resettlement Due Diligence Report Safeguards Due Diligence Reports Sep 2016
PDEIP - Tranche 4: 132 kV Feeding Transmission Line of Jand Grid Station Resettlement Plan Resettlement Plans Aug 2016
PDEIP - Tranche 4: 132 kV Feeding Transmission Line of Lakkarmar Grid Station Resettlement Plan Resettlement Plans Aug 2016
PDEIP - Tranche 4: 132 kV Feeding Transmission Line of Tamman Grid Station Resettlement Plan Resettlement Plans Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: LESCO Punjab University Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: IESCO Tamman Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: IESCO Jand Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: IESCO Danda Shah Bilwal Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: IESCO Lakkarmar Grid Station Resettlement Due Diligence Report Safeguards Due Diligence Reports Aug 2016
Power Distribution Enhancement Investment Program - Tranche 4: Biannual Social Monitoring Report, MEPCO (January-June 2016) Social Monitoring Reports Jul 2016
Power Distribution Enhancement Investment Program - Tranche 4: Biannual Social Monitoring Report (LESCO) (January-June 2015) Social Monitoring Reports Nov 2015
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (FESCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (MEPCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (GEPCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (PESCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (HESCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (QESCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (IESCO) Safeguards Due Diligence Reports Jun 2013
Power Distribution Enhancement Investment Program - Tranche 4: Resettlement Due Diligence Report (LESCO) Safeguards Due Diligence Reports Jun 2013

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
3096-PAK: Power Distribution Enhancement Investment Program – Tranche 4 [ADB-TRANCHE-IV-PESCO-07(S)-2017 (Lots 1-9)] Invitation for Bids Closed 20 Oct 2017 12 Dec 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-IESCO-Tranche-IV-NCB-01-Package # (I, II & III) (Civil Works)] Invitation for Bids Closed 19 Sep 2017 01 Nov 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program – Tranche 4 [ADB-TRANCHE-IV-PESCO-01(S)-2014-R (Lot-2, Lot-3 & Lot-4)] REBIDDING Invitation for Bids Closed 10 Aug 2017 21 Sep 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-TRANCHE-IV-HESCO-02(S)-2017] Invitation for Bids Closed 08 May 2017 13 Jul 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-Tranche-IV-IESCO-01(S)-2017 ICB-01(S)] Invitation for Bids Closed 28 Apr 2017 15 Jun 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-QESCO-4(S)-2017-Rebid-2(NCB)] Invitation for Bids Closed 28 Apr 2017 01 Jun 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-TRANCHE-IV-PESCO-01(S)-2014 (Lots I to IX)] Invitation for Bids Closed 21 Apr 2017 06 Jun 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-TRANCHE-IV-LESCO-03(S)-2017] Invitation for Bids Closed 19 Apr 2017 06 Jun 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-MEPCO-01-TR-IV-2017 (NCB)] Invitation for Bids Closed 10 Apr 2017 10 May 2017
Loan No. 3096-PAK: Power Distribution Enhancement Investment Program - Tranche 4 [ADB-TRANCHE-IV-MEPCO-04-R-LOT-3-CIVIL WORKS] REBIDDING Invitation for Bids Closed 10 Apr 2017 15 May 2017
Loan No. 3096-PAK:  Power Distribution Enhancement Investment Program - Tranche 4 [ADB-QESCO-4(S)-2017-Rebid(NCB)] Invitation for Bids Closed 24 Feb 2017 04 Apr 2017

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
TROCUREMENT OF 132/11.5KV, 31.5/40 MVA POWER TRANS FORMERS-DIRECT CONTRACTING(15%) Loan 3096 07 Mar 2018 CHINT ELECTRIC CO., LTD. NO. 1255 WENHE ROAD, SONGJIANG DISTRICT SHANGHAI, 201614, P.R.CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited SUPPLY OF GOODS 1,964,181.00 1,964,181.00
PROCUREMENT OF TOWERS TYPE ZM-1,ZM-30,ZM-60 & LEG EXTENSIONS,132KV BEAMS,COLUMNS,EARTH MAST,11KV STR UCTURE,BUS BAR STRUCTURE,EARTHING PLATFORM,EA TOW Loan 3096 10 Jan 2018 THANH LONG GROUP JOINT STOCK COMPANY VIETNAM VIET NAM,SOC REP OF Pakistan Electric Power Company (Pvt.) Limited SUPPLY OF GOODS 2,492,259.00 2,492,259.00
PROCUREMENT OF 5.NOS. 132/11.5KV, 31.5/40 MVA, 3-P HASE POWER TRANSFORMERS WITH CONTROL CUBICLE, ALL ALLIED ACCESSORIES AND SPARE PARTS Loan 3096 04 Jan 2018 CHINT ELECTRIC CO., LTD. NO. 3555, SIXIAN ROAD, SONGJIANG DISTRIC T, SHANGHAI CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited SUPPLY OF GOODS 1,490,390.00 1,490,390.00
PROCUREMENT OF PLANT,DESIGN,SUPPLY,INSTALLATION,TE STING,COMMISSIONING AND CIVIL WORKS FOR 132KV GIS PUNJAB UNIVERSITY GRID STATION ON TURNKEY BASIS Loan 3096 28 Nov 2017 M/S DESCON-CHINT CONSORTIUM LTD, LAHORE 18-KM FEROZEPUR ROAD, P.O.BOX 1201 LAHOR E, 54760, PAKISTAN PAKISTAN Pakistan Electric Power Company (Pvt.) Limited TURNKEY 3,380,458.00 3,380,458.00
LOT 1(R): PROCUREMENT OF 18.NO. 132/11.5KV, 31.5/4 0MVA, 3-PHASE POWER TRANSFORMERS WITH ALLIED ACCES SORIES AND SPARE PARTS Loan 3096 22 Sep 2017 M/S CHINT ELECTRIC CO., LTD., CHINA NO.3555, SIXIAN ROAD, SONGJIANG DISTRICT SHANGHAI, CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited SUPPLY OF GOODS 5,365,410.00 5,365,410.00
ADB-LESCO-01(S)-2016-LOT-1-PROCURMENT OF 132/11.5 KV, 20/26 MVA POWER TRANSFORMERS (04 NOS.) Loan 3096 19 Sep 2017 M/S CHINT ELECTRIC CO., CHINA C/O ZSS CORP., NO. 1255 WENHE ROAD, SONGJIANG DISTRICT SHANGHAI, 201614 P.R.CHINA CHINA,PEOPLE'SREP.OF Pakistan Electric Power Company (Pvt.) Limited SUPPLY OF GOODS 1,020,000.00 1,020,000.00
Proc. of Plant/Design/Supply/Installation/Testing/ & Commissioning of New 132Kv Sanjar Pur Sadiqabad Grid Station along with Transmission Line Loan 3096 16 Jun 2017 Descon Engineering Ltd. 18 Km Ferozepur Road, Lahore, Pakistan Pakistan Electric Power Company (Pvt.) Limited Turnkey 2,096,300.00 2,090,552.00
Plant/Design/Supply/Installation/Testing/Commissioning Two Line Bays, 1 20/26Mva Power Transformer Bay for Conversion From 66Kv To 132Kv Choti Grid Loan 3096 16 Jun 2017 Descon Engineering Ltd. 18 Km Ferozepur Road, Lahore, Pakistan Pakistan Electric Power Company (Pvt.) Limited Turnkey 2,177,154.00 2,171,116.00
Design, Supply, Installation, Laying, Testing, Commissioning Underground Copper Cable 1000Mm - 132KV Mcleod Road - 132KV Qartaba Grid Stations (3.9KM) Loan 3096 31 Mar 2017 Ls Networks - Ls Cable and System (Consortium) 12F, Ls Yongsan Tower, 92 Hangang-Daero Yongsan-Gu, Seoul, 140-702 Korea, Republic Of Pakistan Electric Power Company Pvt. Limited Supply of Goods 3,279,759.64 3,279,975.67
WA#0031 and WA#0032 Loan 3096 31 Mar 2017 Ls Networks - Ls Cables and System (Consortium) 12F, Ls Yongsan Tower, 92 Hangang-Daero Yongsan-Gu, Seoul, 140-702 Korea, Republic Of Pakistan Electric Power Company Pvt. Limited Supply of Goods 5,670,243.00 5,670,243.00
Design, Manufacturing, Survey, Supply, Soil Testing, Laying, Installation, Testing and Comm. of 132KV XLPE Double Circuit Copper Conductor (Sunny View-Mcleod Road) Loan 3096 28 Mar 2017 Chint Electric Co., Ltd. No. 1255 Wenhe Road, Songjiang District Shanghai, 201614 China, People's Republic of Pakistan Electric Power Company Pvt. Limited Supply of Goods 1,818,022.17 1,812,622.74
Procurement of Power Transformers Through Repeat Order by Lesco (6 Nos.) Loan 3096 07 Mar 2017 Associated Technologies (Pvt). Ltd. 142-D Model Town Lahore Pakistan Pakistan Electric Power Company Pvt. Limited Supply of Goods 1,731,240.88 1,731,240.88
Procurement of 132KV Steel Towers Loan 3096 26 Jan 2017 Shaanxi Jc Engineering and Trading Co. Ltd. No. 216, Han Guang Nan Road, Jiaxiang Tower Xi'An China, People's Republic of Pakistan Electric Power Company Pvt. Limited Supply of Goods 556,500.00 556,500.00