Viet Nam: Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing

Sovereign (Public) Project | 40080-025 Status: Active

The Asian Development Bank is working with Viet Nam to develop a metro rail service in Ha Noi to cut traffic congestion and carbon emissions and improve transport access in the capital. The project supports the development of a 12.5 kilometer-long dual track rail line between Nhon and Ha Noi stations on Line 3 of the metro system, one of four priority lines planned.

 
Project Name Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing
Project Number 40080-025
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3364-VIE: Ha Noi Metro Line Sysem Project (Line 3: Nhon-Hanoi Station Section) - Additional Financing
concessional ordinary capital resources lending / Asian Development Fund US$ 5.80 million
Loan 3363-VIE: Ha Noi Metro Line Sysem Project (Line 3: Nhon-Hanoi Station Section) - Additional Financing
Ordinary capital resources US$ 59.00 million
Loan 8302-VIE: Ha Noi Metro Line Sysem Project (Line 3: Nhon-Hanoi Station Section) - Additional Financing
Clean Technology Fund US$ 50.00 million
Loan: Ha Noi Metro Line Sysem Project (Line 3: Nhon-Hanoi Station Section) - Additional Financing
European Investment Bank US$ 77.00 million
Direction G n rale du Tr sor US$ 93.50 million
Agence Francaise de Developpement US$ 75.90 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Partnerships
Sector / Subsector

Transport / Urban public transport

Gender Equity and Mainstreaming Effective gender mainstreaming
Description The project will develop a 12.5 kilometer (km) dual-track rail line between the suburb of Nhon and the main railway station of Viet Nam's capital city, Ha Noi , 3.5 km underground, 8.5 km elevated, and 0.5 km on a transition ramp. The project works include a depot with ancillary buildings at Nhon, elevated viaducts, a transition tunnel portal, bored tunnels, and 12 stations. The project will provide electrical and mechanical systems, including all railway systems required to operate a modern metro line. The project also includes support for detailed design, procurement, construction supervision, design verification, project management, and capacity development.
Project Rationale and Linkage to Country/Regional Strategy Line 3 of the Ha Noi metro system is one of four priority rail lines planned under the government's urban transport master plan for Ha Noi that was approved by the Prime Minister in 2008. The project will enhance access to transport in six districts of Ha Noi and form an integral part of a better public transport system that aims to improve connectivity and raise the share of public rail and bus transport to 40% of passenger demand. This will shift travelers from comparatively high-carbon urban travel modes such as private motorcycles and cars and reduce greenhouse gas emissions. Nine civil works and equipment contracts and four consulting services contracts have been financed with cofinancing from Agence Francaise de Developpement (AFD), Direction Generale du Tresor (DGT) of France, the European Investment Bank (EIB) and the Asian Development Bank (ADB). ADB is financing the civil works contract for the tunnel section of line 3 and four underground stations through contract package 3. The additional loans will finance an expected increase in the cost of the civil works contract, as well as consulting services for a second phase of project management support (PMS).
Impact An integrated sustainable public transport system in six districts of Ha Noi
Project Outcome
Description of Outcome Competitive metro rail services along the project corridor.
Progress Toward Outcome The additional financing is integrated with the original loan L2741-VIE.
Implementation Progress
Description of Project Outputs

1. Metro line 3 is operational.

2. Improved implementation capacity of MRB.

Status of Implementation Progress (Outputs, Activities, and Issues) The additional financing is integrated with the original loan L2741-VIE.
Geographical Location Ba Dinh District, Cau Giay District, Dong Da District, Hanoi, Hoan Kiem, Huyen Tu Liem
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The additional financing is integrated with the original loan L2741-VIE.
Involuntary Resettlement The additional financing is integrated with the original loan L2741-VIE.
Indigenous Peoples The additional financing is integrated with the original loan L2741-VIE.
Stakeholder Communication, Participation, and Consultation
During Project Design The additional financing is integrated with the original loan L2741-VIE.
During Project Implementation The additional financing is integrated with the original loan L2741-VIE.
Business Opportunities
Consulting Services ADB will finance phase 2 of project management support consulting services from its proposed additional financing. The method is under Quality- and cost-based selection (80:20, full technical proposal). The contract package has an estimated total 216 person-months (127 person-months international, 89 person-months national)
Procurement International competitive bidding
Responsible ADB Officer Mizusawa, Daisuke
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
Ha Noi People's Committee
79 Dinh Tien Hoang Street, Hoam Kiem,
Ha Noi, Vietnam
Timetable
Concept Clearance 18 Mar 2015
Fact Finding 16 Mar 2015 to 27 Mar 2015
MRM 02 Sep 2015
Approval 11 Dec 2015
Last Review Mission -
Last PDS Update 26 Sep 2018

Loan 3363-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
10 Dec 2015 08 Nov 2016 05 May 2017 31 Dec 2019 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 329.40 Cumulative Contract Awards
ADB 59.00 10 Dec 2015 0.00 0.00 0%
Counterpart 24.00 Cumulative Disbursements
Cofinancing 246.40 10 Dec 2015 0.13 0.00 0%

Loan 3364-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
10 Dec 2015 08 Nov 2016 05 May 2017 31 Dec 2019 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 5.80 Cumulative Contract Awards
ADB 5.80 10 Dec 2015 4.13 0.00 72%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 10 Dec 2015 0.00 0.00 0%

Loan 8302-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
10 Dec 2015 08 Nov 2016 05 May 2017 31 Dec 2019 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 50.00 Cumulative Contract Awards
ADB 0.00 10 Dec 2015 0.00 0.00 0%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 50.00 10 Dec 2015 0.00 0.13 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section): Audited Project Financial Statements (Fiscal year ended 31 December 2017) Audited Project Financial Statements Oct 2018
Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing: Report and Recommendation of the President Reports and Recommendations of the President Nov 2016
ADB-HC Project Agreement for Loans 3363 and 8302-VIE: Ha Noi Metro Rail System Project (Line 3: Nhon - Ha Noi Station Section) - Additional Financing Project/Program Agreements Nov 2016
ADB-HC Project Agreement for Loan 3364-VIE: Ha Noi Metro Rail System Project (Line 3: Nhon - Ha Noi Station Section) - Additional Financing Project/Program Agreements Nov 2016
Loan Agreement (Special Operations) for Loan 3364-VIE: Ha Noi Metro Rail System Project (Line 3: Nhon - Ha Noi Station Section) - Additional Financing Loan Agreement (Special Operations) Nov 2016
Loan Agreement (Ordinary Operations) for Loan 3363-VIE: Ha Noi Metro Rail System Project (Line 3: Nhon - Ha Noi Station Section) - Additional Financing Loan Agreement (Ordinary Resources) Nov 2016
Loan Agreement (Special Operations) for Loan 8302-VIE: Ha Noi Metro Rail System Project (Line 3: Nhon - Ha Noi Station Section) - Additional Financing Loan Agreement (Special Operations) Nov 2016
Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing: Gender Action Plan Gender Action Plans Nov 2015
Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing: Procurement Plan Procurement Plans Oct 2015
Ha Noi Metro Rail System Project (Line 3: Nhon-Ha Noi Station Section) - Additional Financing: Project Administration Manual Project/Program Administration Manual Oct 2015
Hệ thống Tuyến đường sắt Đô thị tại Hà Nội (Tuyến số 3: Nhổn-Ga đường sắt Hà Nội) (Tài trợ bổ sung) : Bảng Dữ liệu Dự án Translated PDS Mar 2015

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
PROJECT MANAGEMENT SUPPORT (PHASE 2) Loan 3364 15 May 2018 8PF GETINSA EUROSTUDIOS, S.L RAMON DE AGUINAGA,8 28028, MADRID,SPAIN SPAIN SPAIN Ha Noi People's Committee Consulting Services 4,508,396.00 4,140,272.00