Viet Nam : Emergency Rehabilitation of Calamity Damage Project
The Project's impact will be sustained economic growth in the 10 provinces severely affected by typhoons in 2005. Its outcome will be rapid resumption of livelihoods in the affected areas.
Project Results
-
193,480
households with reduced flood risk
-
193,480
households with reduced flood risk
-
193,480
households with reduced flood risk
The results data reported above are limited to ADB's core sectors, as defined under Strategy 2020 and tracked through indicators in the ADB Results Framework. For definitions of results indicators, please see the ADB Results Framework Indicators Definition.
Project Details
-
Project Officer
Ho, Phong Le
Southeast Asia Department
Request for information -
Country/Economy
Viet Nam -
Modality
-
Sector
- Agriculture, natural resources and rural development
| Project Name | Emergency Rehabilitation of Calamity Damage Project | ||||
| Project Number | 40282-013 | ||||
| Country / Economy | Viet Nam |
||||
| Project Status | Closed | ||||
| Project Type / Modality of Assistance | Loan |
||||
| Source of Funding / Amount |
|
||||
| Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||
| Drivers of Change | |||||
| Sector / Subsector |
Agriculture, natural resources and rural development / Irrigation - Rural flood protection - Rural market infrastructure - Rural water supply services Education / Education sector development Transport / Road transport (non-urban) |
||||
| Gender | No gender elements | ||||
| Description | The Project's impact will be sustained economic growth in the 10 provinces severely affected by typhoons in 2005. Its outcome will be rapid resumption of livelihoods in the affected areas. | ||||
| Project Rationale and Linkage to Country/Regional Strategy | n/a ADB's current country strategy and program for Viet Nam provides an enabling framework to respond to natural disaters. ADB therefore agreed to assist the Government to reinstate essential rural infrastructure damanged by typhoons and storms in 2005. |
||||
| Impact | |||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | The Project continues to make good progress. As of 01 Sep 2011 overall progress was 93% against the elapsed revised loan period of 90.14%. The cumulative contract awards and disbursements were $78.988 million and $77.308 million, equivalent to 98% and 96% of the net loan amount ($80.453 million). |
| Implementation Progress | |
| Description of Project Outputs | 1. Essential infrastructure (roads, flood protection, irrigation systems, and social infrastructure) reinstated 2. Equivalent or enhanced storm and flood protection provided to vulnerable areas |
| Status of Implementation Progress (Outputs, Activities, and Issues) | Project Implementation Progress: 1. (i) implementation progress of 64 subprojects was on track. However, implementation of the other 6 subprojects in Ha Giang, Ha Tinh, Nam Dinh, Nghe An, Quang Binh and Phu Yen, was delayed further from 1 to 4 months in comparison with the implementation plans updated by the last review mission in October 2010; (ii) 45 subprojects were fully completed; (iii) the remaining 25 subprojects are expected to be fully completed by the end of July 2011. The main reasons of the delays of six subprojects were (i) floods of 2010; (ii) design changes of two subprojects in Nam Dinh and Phu Yen provinces; and (iii) weak capacity of contractor of a subproject in Ha Giang Province. These issues were already overcome by the concerned PPMUs and provincial authorities. 2. (i) total ADB loan amount has been committed; and (ii) at completion, the total project cost is estimated at about $94.4 million (105% of the original cost estimate) including $79.92 million (84.7%) of ADB loan and $14.48 million equivalent (15.3%) of the counterpart funds. Issues: 1. Delays in processing civil works contract variations. There are number of civil works contracts, which should be adjusted due to increase of costs of construction materials and labor. However, many PPMUs have not processed these contract variations yet. The Mission requested these PPMUs to process them immediately according to the guidelines of the Ministry of Construction. 2. Delays in procurement of additional works. Procurements of additional works in Ha Giang, Thanh Hoa and Yen Bai provinces have not finalized yet due to the lengthy provincial procedures. As physical completion date of the Project is 30 June 2011, the Mission requested that the civil work contracts of the additional works should be awarded by 15 March 2011. 3. Design change. Change of technical design for the Lien Hop Spillway and Thuong Binh Road Subproject of Ha Giang Province is required to improve its sustainability and effectiveness and this change will delay subproject completion until the end of July 2011. Follow-up actions: 1. PPCs of Ha Giang, Nam Dinh, Nghe An, Phu Tho, Phu Yen, Quang Binh, Quang Tri and Thanh Hoa provinces should provide adequate counterpart funds for their subprojects according to Attachment 2 before 31 March 2011, otherwise their proposals for new subprojects of Loan 2357 (Integrated Rural Development Sector Project in the Central Provinces) and Loans 2682-2683 (Sustainable Rural Infrastructure Development in Northern Mountain Provinces), and their participation in other future ADB financed projects will not be approved by ADB; 2. PPCs should provide adequate O&M funds for the completed subprojects; 3. Ha Giang, Thanh Hoa and Yen Bai PPMUs should finalize immediately the procurement of additional works; 4. Ha Giang PPMU should process immediately the change of technical design for the Lien Hop Spillway and Thuong Binh Road Subproject; 5. PPMUs should process immediately the pending payments for the completed subprojects; and 6. PPMUs should process immediately the pending civil works contract variations required by the increase of construction materials and labor costs according to the guidelines of the Ministry of Construction; |
| Geographical Location | |
| Safeguard Categories | |
|---|---|
| Environment | B |
| Involuntary Resettlement | B |
| Indigenous Peoples | B |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | ADB's discussions with the Ministries of Planning and Investment, Agriculture and Rural Development, and Finance; other central level agencies; and the PPCs, DARDs and other provincial authorities have been frequent and intensive over the period November 2005 July 2006. During the scoping missions (November 2005 and February 2006) and damage needs and assessment mission (27 March 28 April 2006), discussions were held on site with potential beneficiaries and other affected persons. A participatory process was adopted to identify the individual subprojects for inclusion in the Project during the damage and needs assessment mission. The Project's intended support for rehabilitation of infrastructure in four subsectors was given high priority by all stakeholders. In addition, means of ensuring the participation of the poor and other disadvantaged, including women, children, and female-headed households, were prepared. Technical assistance was discussed and agreed for institutional strengthening of the executing agency (MARD) and implementing agencies (DARDs) in each province. A participatory approach will be followed during project implementation. Stakeholder participation in preparation, implementation, operation and maintenance, and monitoring of improved infrastructure will be encouraged by the EA/DARDs as an essential way of lowering costs and ensuring sustainability. Local government institutions and NGOs will be involved during all phases of project implementation and performance monitoring. Preference will be given to local labor, especially from among the landless and poor, in construction contracts. Rehabilitation of infrastructure will help the beneficiaries participate in various social and economic activities. |
| During Project Implementation | |
| Business Opportunities | |
|---|---|
| Consulting Services | One contract for international consulting firm to provide 60 person-mnths of international and 27 person-months of national consultant inputs. Numerous contracts with national consulting firms to prepare feasibility studies and detailed designs for rehabilitation of rural infrastructure wwith a total value of $2.6 million. |
| Procurement | Construction of small-scale rural infrastructure in 35 or more contracts with a total value of about $22.3 million. Construction of medium-scale infrastructure in four or more contracts with a total value of about $20.3 million. |
| Responsible ADB Officer | Ho, Phong Le |
| Responsible ADB Department | Southeast Asia Department |
| Responsible ADB Division | Viet Nam Resident Mission |
| Executing Agencies |
Ministry of Agriculture & Rural Development (MARD) Dr. Hoang Van Xo [email protected] 3rd Floor, 1A Nguyen Cong Tru St., Hanoi, Vietnam |
| Timetable | |
|---|---|
| Concept Clearance | 10 Aug 2006 |
| Fact Finding | 27 Mar 2006 to 28 Apr 2006 |
| MRM | 25 Sep 2006 |
| Approval | 21 Nov 2006 |
| Last Review Mission | - |
| PDS Creation Date | 21 Mar 2007 |
| Last PDS Update | 05 Sep 2011 |
Loan 2273-VIE
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 21 Nov 2006 | 07 Dec 2006 | 23 Apr 2007 | 31 Dec 2009 | 31 Dec 2011 | 08 Aug 2012 |
| Financing Plan | Loan Utilization | ||||
|---|---|---|---|---|---|
| Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
| Project Cost | 59.89 | Cumulative Contract Awards | |||
| ADB | 50.97 | 17 Jun 2022 | 80.00 | 0.00 | 100% |
| Counterpart | 8.92 | Cumulative Disbursements | |||
| Cofinancing | 0.00 | 17 Jun 2022 | 80.00 | 0.00 | 100% |
| Status of Covenants | ||||||
|---|---|---|---|---|---|---|
| Category | Sector | Safeguards | Social | Financial | Economic | Others |
| Rating | - | Satisfactory | Satisfactory | - | - | Satisfactory |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Proposed Supplementary Loan: Emergency Rehabilitation of Calamity Damage Project | Procurement Plans | Nov 2008 |
| Loan Agreement for Emergency Rehabilitation of Calamity Damage Project between Socialist Republic of Viet Nam and ADB dated 7 December 2006 | Loan Agreement (Special Operations) | Dec 2006 |
| Emergency Rehabilitation of Calamity Damage Project | Reports and Recommendations of the President | Oct 2006 |
| Emergency Rehabilitation of Calamity Damage Project | Project/Program Administration Manual | Sep 2007 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
| Title | Document Type | Document Date |
|---|---|---|
| Calamity Damage Rehabilitation Project | Resettlement Planning Documents | Sep 2006 |
| Calamity Damage Rehabilitation Project | Environmental Assessment and Review Framework | Sep 2006 |
| Calamity Damage Rehabilitation Project | Initial Environmental Examination | Sep 2006 |
| Calamity Damage Rehabilitation Project | Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks | Sep 2006 |
Evaluation Documents See also: Independent Evaluation
| Title | Document Type | Document Date |
|---|---|---|
| Viet Nam: Emergency Rehabilitation of Calamity Damage Project | Validations of Project Completion Reports | Sep 2014 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
| Title | Document Type | Document Date |
|---|---|---|
| Proposed Supplementary Loan: Emergency Rehabilitation of Calamity Damage Project | Procurement Plans | Nov 2008 |